D1: Critical path analysis – Edexcel IAL Decision Mathematics (WDM1)
33 questions · page 1 of 3 · Clear filters
Question text
5.
Activity
Immediately preceding activities
A
–
B
–
C
A
D
A
E
A, B
F
A, B
G
C, D
H
E
I
E
J
F, G, H, I
K
F, I
L
K
(a) Draw the activity network described in the precedence table, using activity on arc
and the minimum number of dummies.
(5)
(b) Given that all activities have the same duration, state the critical activities.
(1)
(Total for Question 5 is 6 marks)
Question text
7.
D(4)
A(7)
J(9)
E(6)
B(6)
K(7)
F(5)
G(5)
L(6)
C(8)
H(6)
M(7)
Figure 3
A project is modelled by the activity network shown in Figure 3. The activities are
represented by the arcs. The number in brackets on each arc gives the time, in days, to
complete the activity. Each activity requires exactly one worker. The project is to be
completed in the shortest possible time.
(a) Complete the diagram in the answer book to show the early event times and the late
event times.
(4)
(b) Calculate the total float for activity M
(1)
(c) Calculate a lower bound for the minimum number of workers required to complete
the project in the minimum time.
(2)
(d) Draw a Gantt (cascade) chart on the grid in the answer book.
(4)
(e) Use the Gantt chart to determine the minimum number of workers required to
complete the project in the minimum time. You must make specific reference to the
number of workers, activities and times.
(2)
The start of activity H is now delayed by 3 days.
(f) Determine what effect this has on the completion time for the project, justifying
your answer.
(2)
(Total for Question 7 is 15 marks)
Question text
7.
D(4)
E(6)
J(9)
A(7)
B(6)
F(5)
K(7)
Key:
early
event
G(5)
L(6)
C(8)
time
late
event
time
H(6)
M(7)
Question 7 continued
0
2
4
6
8
10
12
14
16
18
20
22
24
(Total for Question 7 is 15 marks)
Question text
2.
Activity
Immediately preceding activities
A
–
B
–
C
–
D
A
E
A
F
A, B, C
G
A, B, C
H
C
I
G, H
J
E, F, I
K
D, J
L
E, F, I
M
G, H
N
G, H
(a) Draw the activity network described in the precedence table above, using activity on
arc and the minimum number of dummies.
(5)
Given that all of the activities have the same duration,
(b) determine the critical activities.
(2)
(Total for Question 2 is 7 marks)
Question text
6.
E(13)
F(9)
K(7)
N(9)
A(8)
B(6)
G(5)
L(3)
P(10)
C(9)
H(8)
M(11)
I(6)
Q(8)
D(11)
J(13)
Figure 4
A project is modelled by the activity network shown in Figure 4. The activities are
represented by the arcs. The number in brackets on each arc gives the time, in days,
to complete the corresponding activity. Each activity requires exactly one worker. The
project is to be completed in the shortest possible time.
(a) Complete the diagram in the answer book to show the early event times and the late
event times.
(4)
(b) State the critical activities.
(1)
(c) Calculate a lower bound for the minimum number of workers required to complete
the project in the shortest possible time.
(2)
(d) Calculate the total float for activity L, showing your working.
(1)
(e) Draw a schedule on the grid in the answer book to show how the project can be
completed in the shortest possible time using the minimum number of workers.
(4)
(Total for Question 6 is 12 marks)
Question text
7.
D(10)
I(8)
A(7)
M(7)
N(9)
E(9)
B(5)
F(8)
J(5)
P(6)
G(13)
K(9)
C(8)
Q(11)
H(8)
L(6)
Figure 3
A project is modelled by the activity network shown in Figure 3. The activities are
represented by the arcs. The number in brackets on each arc gives the time, in days, to
complete the activity. Each activity requires exactly one worker. The project is to be
completed in the shortest possible time.
(a) Complete the table in the answer book to show the immediately preceding activities
for the network.
(3)
(b) Complete the diagram in the answer book to show the early event times and the late
event times.
(4)
(c) State the critical activities.
(1)
(d) Calculate a lower bound for the minimum number of workers required to complete
the project in the minimum time.
(2)
(e) On the grid in the answer book, draw a schedule to show how the activities can be
completed in the minimum time, using the minimum number of workers.
(4)
(Total for Question 7 is 14 marks)
Question text
4. Draw the activity network described in this precedence table, using activity on arc and
dummies only where necessary.
(5)
Activity
Immediately preceding activities
–
A
–
B
–
C
D
B, C
E
A
F
C
G
D, E
H
D, E
I
F, G
J
C
K
G, H
(Total for Question 4 is 5 marks)
Question text
6.
F(9)
3
5
A(4)
J(8)
E(7)
I(2)
B(5)
K(5)
8
9
1
2
6
D(4)
G(7)
C(7)
4
H(6)
7
Figure 3
A project is modelled by the activity network shown in Figure 3. The activities are
represented by the arcs. The number in brackets on each arc gives the time required,
in hours, to complete the activity. The numbers in circles are the event numbers. Each
activity requires one worker.
(a) Complete Diagram 1 in the answer book to show the early event times and the late
event times.
(4)
(b) State the minimum project completion time.
(1)
(c) Calculate a lower bound for the minimum number of workers required to complete
the project in the minimum time. You must show your working.
(2)
(d) On Grid 1 in your answer book, draw a cascade (Gantt) chart for this project.
(4)
(e) On Grid 2 in your answer book, construct a scheduling diagram to show that
this project can be completed with three workers in just one more hour than the
minimum project completion time.
(3)
(Total for Question 6 is 14 marks)
Question text
7:
D(6)
I(7)
M(6)
A(8)
E(4)
J(2)
F(8)
K(6)
N(4)
B(12)
G(8)
C(14)
L(6)
H(5)
Figure 3
A project is modelled by the activity network shown in Figure 3. The activities are
represented by the arcs. The number in brackets on each arc gives the time, in days,
to complete the corresponding activity. Each activity requires exactly one worker. The
project is to be completed in the shortest possible time.
(a) Complete the precedence table in the answer book to show the immediately
preceding activities for the project.
(3)
(b) Complete the diagram in the answer book to show the early event times and the late
event times.
(4)
(c) Calculate a lower bound for the minimum number of workers required to complete
the project in the minimum time.
(2)
(d) Draw a Gantt (cascade) chart on the grid in the answer book.
(4)
(e) Use the Gantt chart to determine the minimum number of workers required to
complete the project in the minimum time. You must make specific reference to the
number of workers, activities and times.
(3)
(Total for Question 7 is 16 marks)
Question text
4.
Activity
Immediately preceding activities
A
‑
B
‑
C
‑
D
A
E
A, B, C
F
A, B, C
G
C
H
D, E, F
I
F
J
F, G
K
F, G
(a) Draw the activity network described in the precedence table above, using activity on
arc and the minimum number of dummies.
(5)
Given that
•
activity D has a duration of 2 hours
•
activity I has a duration of 2 hours
•
every other activity has a duration of 1 hour
•
D and I are critical activities
(b) determine which other activities are critical.
(1)
(Total for Question 4 is 6 marks)
Question text
7.
D(17)
2
7
E(5)
A(8)
N(11)
L(5)
I(10)
B(6)
F(9)
P(9)
1
3
5
8
11
J(11)
M(4)
C(7)
Q(12)
G(8)
4
6
9
10
H(6)
K(12)
R(10)
Figure 3
A project is modelled by the activity network shown in Figure 3. The activities are
represented by the arcs. The number in brackets on each arc gives the time, in days, to
complete the activity. Each activity requires exactly one worker. The project is to be
completed in the shortest possible time.
(a) Explain the purpose of the dummy between event 10 and event 11
(1)
(b) Complete Diagram 1 in the answer book to show the early event times and the late
event times.
(4)
(c) State the critical activities.
(1)
(d) Calculate the maximum number of days by which activity K could be delayed
without lengthening the completion time of the project. You must make the numbers
used in your calculation clear.
(2)
(e) Draw a Gantt (cascade) chart on the grid in the answer book.
(4)
(f) Use the Gantt chart to determine a lower bound for the minimum number of workers
required to complete the project in the minimum time. You must make specific
reference to the number of workers, activities and times.
(2)
(Total for Question 7 is 14 marks)
Question text
7.
Key:
Early
event
D(17)
time
Late
event
time
N(11)
E(5)
A(8)
L(5)
I(10)
P(9)
B(6)
F(9)
J(11)
M(4)
C(7)
G(8)
Q(12)
H(6)
K(12)
R(10)
Diagram 1
Question 7 continued
0
2
4
6
8
10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 40 42 44
(Total for Question 7 is 14 marks)
Question text
2.
G(2)
D(4)
L(3)
H(4)
F(3)
E(3)
I(6)
M(2)
A(5)
B(4)
J(7)
N(2)
C(7)
K(7)
Figure 1
[The sum of the durations of all the activities is 59 days.]
The network in Figure 1 shows the activities that need to be undertaken to complete
a project. Each activity is represented by an arc and the duration, in days, of the
corresponding activity is shown in brackets. Each activity requires one worker.
The project is to be completed in the shortest possible time.
(a) (i) Complete Diagram 1 in the answer book to show the early event times and the
late event times.
(ii) State the minimum completion time of the project.
(5)
(b) Calculate a lower bound for the number of workers needed to complete the project
in the minimum time. You must show your working.
(1)
(c) Schedule the activities using the minimum number of workers so that the project is
completed in the minimum time.
(4)
(Total for Question 2 is 10 marks)
Question text
6.
Activity
Immediately preceding activities
A
‑
B
‑
C
A
D
‑
E
A, B, D
F
D
G
A, B, D
H
F, G
I
A
J
F, G
K
C, E, H, I
L
I
M
C, E, H, I
(a) Draw the activity network for the project described in the precedence table, using
activity on arc and the minimum number of dummies.
(5)
0
2
4
6
8
10
12
14
16
18
20
22
M
B
G
H
A
D
C
E
F
I
J
K
Grid 1
A cascade chart for all the activities of the project, except activity L, is shown on
Grid 1.
The time taken to complete each activity is given in hours and each activity requires
one worker.
The project is to be completed in the minimum time using as few workers as possible.
(b) State the critical activities of the project.
(1)
(c) Use the cascade chart to determine the minimum number of workers needed to
complete the project in the shortest possible time. You must make specific reference
to time and activities. (You do not need to provide a schedule of the activities.)
(2)
The duration of activity L is x hours. Given that the total float of activity L is at most
7 hours,
(d) determine the range of possible values for x.
(2)
(Total for Question 6 is 10 marks)
Question text
2.
Key:
G(2)
Early
event
D(4)
time
Late
L(3)
H(4)
F(3)
event
time
E(3)
I(6)
M(2)
A(5)
B(4)
J(7)
N(2)
C(7)
K(7)
Diagram 1
Question 2 continued
0
2
4
6
8
10
12
14
16
18
20
22
24
(Total for Question 2 is 10 marks)