D1: Critical path analysis – Edexcel IAL Decision Mathematics (WDM1)

10 questions

0 / 0Answer a question to start your score.
New quizSaved 0

Quick quiz: 10 random questions from this topic. Answer them all, then open the Summary.

Advertisement
1
WDM1 D1 A · Jun 2026 · Question 6May/June 2026D1 A12 marks
Loading question…
Question text

6.
E(13)
F(9)
K(7)
N(9)
A(8)
B(6)
G(5)
L(3)
P(10)
C(9)
H(8)
M(11)
I(6)
Q(8)
D(11)
J(13)
Figure 4
A project is modelled by the activity network shown in Figure 4. The activities are
represented by the arcs. The number in brackets on each arc gives the time, in days,
to complete the corresponding activity. Each activity requires exactly one worker. The
project is to be completed in the shortest possible time.
(a) Complete the diagram in the answer book to show the early event times and the late
event times.
(4)
(b) State the critical activities.
(1)
(c) Calculate a lower bound for the minimum number of workers required to complete
the project in the shortest possible time.
(2)
(d) Calculate the total float for activity L, showing your working.
(1)
(e) Draw a schedule on the grid in the answer book to show how the project can be
completed in the shortest possible time using the minimum number of workers.
(4)
(Total for Question 6 is 12 marks)

2
WDM1 D1 · Jun 2024 · Section 1, Question 2May/June 2024D110 marks
Loading question…
Question text

2.
G(2)
D(4)
L(3)
H(4)
F(3)
E(3)
I(6)
M(2)
A(5)
B(4)
J(7)
N(2)
C(7)
K(7)
Figure 1
[The sum of the durations of all the activities is 59 days.]
The network in Figure 1 shows the activities that need to be undertaken to complete
a project. Each activity is represented by an arc and the duration, in days, of the
corresponding activity is shown in brackets. Each activity requires one worker.
The project is to be completed in the shortest possible time.
(a) (i) Complete Diagram 1 in the answer book to show the early event times and the
late event times.
(ii) State the minimum completion time of the project.
(5)
(b) Calculate a lower bound for the number of workers needed to complete the project
in the minimum time. You must show your working.
(1)
(c) Schedule the activities using the minimum number of workers so that the project is
completed in the minimum time.
(4)
(Total for Question 2 is 10 marks)

3
WDM1 D1 · Jan 2024 · Section 2, Question 1January 2024D113 marks
Loading question…
Question text

1.
D(5)
L(12)
E(2)
A(4)
B(3)
G(5)
J(6)
Key:
F(6)
early
C(7)
H(6)
K(5)
event
time
late
event
I(6)
time
Diagram 1
Question 1 continued
0
2
4
6
8
10
12
14
16
18
20
22
24
26
28
Grid 1
(Total for Question 1 is 13 marks)

Advertisement
4
WDM1 D1 · Jun 2023 · Section 2, Question 1May/June 2023D110 marks
Loading question…
Question text

1.
Key:
E(5)
I(2)
Early
event
time
Late
event
N(3)
F(6)
A(5)
time
D(4)
B(7)
J(7)
K(5)
P(6)
G(2)
Q(5)
C(6)
L(4)
H(4)
M(8)
Diagram 1
Question 1 continued
0
2
4
6
8
10
12
14
16
18
20
22
24
26
28
30
32
34
36
Grid 1
(Total for Question 1 is 10 marks)

5
WDM1 D1 · Jan 2024 · Section 2, Question 4January 2024D17 marks
Loading question…
Question text

4.
Question 4 continued
Only use this blank space if you need to redraw your activity network.
(Total for Question 4 is 7 marks)

6
WDM1 D1 A · Jan 2026 · Question 6January 2026D1 A14 marks
Loading question…
Question text

6.
F(9)
3
5
A(4)
J(8)
E(7)
I(2)
B(5)
K(5)
8
9
1
2
6
D(4)
G(7)
C(7)
4
H(6)
7
Figure 3
A project is modelled by the activity network shown in Figure 3. The activities are
represented by the arcs. The number in brackets on each arc gives the time required,
in hours, to complete the activity. The numbers in circles are the event numbers. Each
activity requires one worker.
(a) Complete Diagram 1 in the answer book to show the early event times and the late
event times.
(4)
(b) State the minimum project completion time.
(1)
(c) Calculate a lower bound for the minimum number of workers required to complete
the project in the minimum time. You must show your working.
(2)
(d) On Grid 1 in your answer book, draw a cascade (Gantt) chart for this project.
(4)
(e) On Grid 2 in your answer book, construct a scheduling diagram to show that
this project can be completed with three workers in just one more hour than the
minimum project completion time.
(3)
(Total for Question 6 is 14 marks)

7
WDM1 D1 A · Jun 2026 · Question 2May/June 2026D1 A7 marks
Loading question…
Question text

2.
Activity
Immediately preceding activities
A
–
B
–
C
–
D
A
E
A
F
A, B, C
G
A, B, C
H
C
I
G, H
J
E, F, I
K
D, J
L
E, F, I
M
G, H
N
G, H
(a) Draw the activity network described in the precedence table above, using activity on
arc and the minimum number of dummies.
(5)
Given that all of the activities have the same duration,
(b) determine the critical activities.
(2)
(Total for Question 2 is 7 marks)

8
WDM1 D1 · Jan 2023 · Section 1, Question 4January 2023D113 marks
Loading question…
Question text

4.
Immediately
Immediately
Immediately
Activity
Activity
Activity
preceded by
preceded by
preceded by
A
–
G
M
D, G
B
–
H
N
C
–
I
P
D
A
J
Q
E
C
K
D, G
R
F
C
L
D, G
Key:
early
D(12)
L(6)
event
time
late
M(6)
A(9)
G(11)
event
K(7)
time
0
B(4)
H(8)
N(13)
0
I(12)
P(7)
R(3)
E(3)
C(9)
F(13)
J(5)
Q(5)
Diagram 1
Question 4 continued
0
2
4
6
8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 40 42 44
C
A
B
Diagram 2
(Total for Question 4 is 13 marks)

Advertisement
9
WDM1 D1 · Jun 2024 · Section 2, Question 2May/June 2024D110 marks
Loading question…
Question text

2.
Key:
G(2)
Early
event
D(4)
time
Late
L(3)
H(4)
F(3)
event
time
E(3)
I(6)
M(2)
A(5)
B(4)
J(7)
N(2)
C(7)
K(7)
Diagram 1
Question 2 continued
0
2
4
6
8
10
12
14
16
18
20
22
24
(Total for Question 2 is 10 marks)

10
WDM1 D1 · Jun 2022 · Section 2, Question 5May/June 2022D19 marks
Loading question…
Question text

5.
Activity
Immediately preceding activities
A
–
B
–
C
–
D
A, B
E
A, B
F
B, C
G
B, C
H
D
I
D, E, F, G
J
H, I
K
D, E, F
Question 5 continued
Please redraw your activity network on this page if you need to do so.
(Total for Question 5 is 9 marks)