D1: Critical path analysis – Edexcel IAL Decision Mathematics (WDM1)
14 questions · Clear filters
Question text
7.
D(10)
I(8)
A(7)
M(7)
N(9)
E(9)
B(5)
F(8)
J(5)
P(6)
G(13)
K(9)
C(8)
Q(11)
H(8)
L(6)
Figure 3
A project is modelled by the activity network shown in Figure 3. The activities are
represented by the arcs. The number in brackets on each arc gives the time, in days, to
complete the activity. Each activity requires exactly one worker. The project is to be
completed in the shortest possible time.
(a) Complete the table in the answer book to show the immediately preceding activities
for the network.
(3)
(b) Complete the diagram in the answer book to show the early event times and the late
event times.
(4)
(c) State the critical activities.
(1)
(d) Calculate a lower bound for the minimum number of workers required to complete
the project in the minimum time.
(2)
(e) On the grid in the answer book, draw a schedule to show how the activities can be
completed in the minimum time, using the minimum number of workers.
(4)
(Total for Question 7 is 14 marks)
Question text
4. Draw the activity network described in this precedence table, using activity on arc and
dummies only where necessary.
(5)
Activity
Immediately preceding activities
–
A
–
B
–
C
D
B, C
E
A
F
C
G
D, E
H
D, E
I
F, G
J
C
K
G, H
(Total for Question 4 is 5 marks)
Question text
6.
F(9)
3
5
A(4)
J(8)
E(7)
I(2)
B(5)
K(5)
8
9
1
2
6
D(4)
G(7)
C(7)
4
H(6)
7
Figure 3
A project is modelled by the activity network shown in Figure 3. The activities are
represented by the arcs. The number in brackets on each arc gives the time required,
in hours, to complete the activity. The numbers in circles are the event numbers. Each
activity requires one worker.
(a) Complete Diagram 1 in the answer book to show the early event times and the late
event times.
(4)
(b) State the minimum project completion time.
(1)
(c) Calculate a lower bound for the minimum number of workers required to complete
the project in the minimum time. You must show your working.
(2)
(d) On Grid 1 in your answer book, draw a cascade (Gantt) chart for this project.
(4)
(e) On Grid 2 in your answer book, construct a scheduling diagram to show that
this project can be completed with three workers in just one more hour than the
minimum project completion time.
(3)
(Total for Question 6 is 14 marks)
Question text
4.
Activity
Immediately preceding activities
A
‑
B
‑
C
‑
D
A
E
A, B, C
F
A, B, C
G
C
H
D, E, F
I
F
J
F, G
K
F, G
(a) Draw the activity network described in the precedence table above, using activity on
arc and the minimum number of dummies.
(5)
Given that
•
activity D has a duration of 2 hours
•
activity I has a duration of 2 hours
•
every other activity has a duration of 1 hour
•
D and I are critical activities
(b) determine which other activities are critical.
(1)
(Total for Question 4 is 6 marks)
Question text
7.
D(17)
2
7
E(5)
A(8)
N(11)
L(5)
I(10)
B(6)
F(9)
P(9)
1
3
5
8
11
J(11)
M(4)
C(7)
Q(12)
G(8)
4
6
9
10
H(6)
K(12)
R(10)
Figure 3
A project is modelled by the activity network shown in Figure 3. The activities are
represented by the arcs. The number in brackets on each arc gives the time, in days, to
complete the activity. Each activity requires exactly one worker. The project is to be
completed in the shortest possible time.
(a) Explain the purpose of the dummy between event 10 and event 11
(1)
(b) Complete Diagram 1 in the answer book to show the early event times and the late
event times.
(4)
(c) State the critical activities.
(1)
(d) Calculate the maximum number of days by which activity K could be delayed
without lengthening the completion time of the project. You must make the numbers
used in your calculation clear.
(2)
(e) Draw a Gantt (cascade) chart on the grid in the answer book.
(4)
(f) Use the Gantt chart to determine a lower bound for the minimum number of workers
required to complete the project in the minimum time. You must make specific
reference to the number of workers, activities and times.
(2)
(Total for Question 7 is 14 marks)
Question text
7.
Key:
Early
event
D(17)
time
Late
event
time
N(11)
E(5)
A(8)
L(5)
I(10)
P(9)
B(6)
F(9)
J(11)
M(4)
C(7)
G(8)
Q(12)
H(6)
K(12)
R(10)
Diagram 1
Question 7 continued
0
2
4
6
8
10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 40 42 44
(Total for Question 7 is 14 marks)
Question text
1.
D(5)
E(2)
L(12)
A(4)
J(6)
B(3)
G(5)
F(6)
C(7)
H(6)
K(5)
I(6)
Figure 1
A project is modelled by the activity network shown in Figure 1. The activities are
represented by the arcs. The number in brackets on each arc gives the time, in hours, to
complete the corresponding activity. Each activity requires one worker. The project is to
be completed in the shortest possible time using as few workers as possible.
(a) Complete Diagram 1 in the answer book to show the early event times and the late
event times.
(4)
(b) Calculate the total float for activity D. You must make the numbers used in your
calculation clear.
(1)
(c) Calculate a lower bound for the minimum number of workers required to complete
the project in the shortest possible time. You must show your working.
(2)
(d) Draw a cascade chart for this project on Grid 1 in the answer book.
(4)
(e) Use your cascade chart to determine the minimum number of workers needed to
complete the project in the shortest possible time. You must make specific reference
to time and activities. (You do not need to provide a schedule of the activities.)
(2)
(Total for Question 1 is 13 marks)
Question text
4.
Activity
Immediately preceding activities
A
–
B
–
C
A, B
D
A, B
E
B
F
C, D, E
G
F
H
B
I
F
J
F
K
G
L
G, H, I, J
M
G, I
(a) Draw the activity network described in the precedence table, using activity on arc
and the minimum number of dummies.
(5)
(b) Given that
•
the activity network contains only one critical path
•
activity E is on this critical path
state
(i) which activities could never be critical,
(ii) which activities must be critical.
(2)
(Total for Question 4 is 7 marks)
Question text
1.
D(5)
L(12)
E(2)
A(4)
B(3)
G(5)
J(6)
Key:
F(6)
early
C(7)
H(6)
K(5)
event
time
late
event
I(6)
time
Diagram 1
Question 1 continued
0
2
4
6
8
10
12
14
16
18
20
22
24
26
28
Grid 1
(Total for Question 1 is 13 marks)
Question text
4.
Question 4 continued
Only use this blank space if you need to redraw your activity network.
(Total for Question 4 is 7 marks)
Question text
4.
Immediately
Immediately
Immediately
Activity
Activity
Activity
preceded by
preceded by
preceded by
A
–
G
M
D, G
B
–
H
N
C
–
I
P
D
A
J
Q
E
C
K
D, G
R
F
C
L
D, G
Key:
early
D(12)
L(6)
event
time
late
M(6)
A(9)
G(11)
event
K(7)
time
0
B(4)
H(8)
N(13)
0
I(12)
P(7)
R(3)
E(3)
C(9)
F(13)
J(5)
Q(5)
Diagram 1
Question 4 continued
0
2
4
6
8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 40 42 44
C
A
B
Diagram 2
(Total for Question 4 is 13 marks)
Question text
4.
D(12)
L(6)
K(7)
A(9)
G(11)
M(6)
B(4)
H(8)
N(13)
I(12)
P(7)
R(3)
C(9)
E(3)
F(13)
J(5)
Q(5)
Figure 2
[The sum of the durations of all the activities is 133 days]
A project is modelled by the activity network shown in Figure 2. The activities are
represented by the arcs. The number in brackets on each arc gives the time, in days, to
complete the activity. Each activity requires one worker. The project is to be completed
in the shortest possible time.
(a) Complete the precedence table in the answer book.
(2)
(b) Complete Diagram 1 in the answer book to show the early event times and the late
event times.
(4)
(c) State the critical activities.
(1)
(d) Calculate the total float for activity J. You must make the numbers you use in your
calculation clear.
(1)
(e) Calculate a lower bound for the number of workers needed to complete the project
in the minimum time. You must show your working.
(1)
Diagram 2 in the answer book shows a partly completed scheduling diagram for
this project.
(f) Complete the scheduling diagram, using the minimum number of workers, so that
the project is completed in the minimum time.
(4)
(Total for Question 4 is 13 marks)
Question text
1.
The table below shows the distances, in km, between six data collection points, A, B, C, D, E and F.
A
B
C
D
E
F
A
–
35
42
55
48
50
B
–
35
40
49
52
31
C
–
42
40
47
53
49
D
–
55
49
47
39
44
E
–
48
52
53
39
52
F
–
50
31
49
44
52
Ferhana must visit each data collection point. She will start and finish at A and wishes to minimise
the total distance she travels.
(a) Starting at A, use the nearest neighbour algorithm to obtain an upper bound for the distance
Ferhana must travel. Make your method clear.
(2)
(b) Starting by deleting B, and all of its arcs, find a lower bound for the distance Ferhana must
travel. Make your calculation clear.
(3)
(Total 5 marks)
2.
C
19
B
32
A
29
25
34
30
15
22
E
F
D
30
32
13
11
17
23
18
J
H
G
20
Figure 1
(a) Define the terms
(i) tree,
(ii) minimum spanning tree.
(3)
(b) Use Kruskal’s algorithm to find the minimum spanning tree for the network shown in Figure 1.
You must clearly show the order in which you consider the edges. For each edge, state whether
or not you are including it in the minimum spanning tree.
(3)
(c) Draw the minimum spanning tree using the vertices given in Diagram 1 in the answer book and
state the weight of the minimum spanning tree.
(2)
(Total 8 marks)
3.
4
24
D(x)
10
24
E(7)
J(9)
A(4)
I(7)
33
7
0
F(5)
K(10)
z
B(5)
33
0
17
y
L(11)
G(9)
C(7)
28
17
7
33
M(9)
H(10)
17
7
Figure 2
The network in Figure 2 shows the activities that need to be undertaken by a company to complete
a project. Each activity is represented by an arc and the duration, in days, is shown in brackets.
Each activity requires one worker. The early event times and late event times are shown at each
vertex.
The total float on activity D is twice the total float on activity E.
(a) Find the values of x, y and z.
(3)
(b) Draw a cascade chart for this project on Grid 1 in the answer book.
(4)
(c) Use your cascade chart to determine a lower bound for the minimum number of workers
needed to complete the project in the shortest possible time. You must make specific reference
to time and activities. (You do not need to provide a schedule of the activities.)
(2)
(Total 9 marks)
Question text
1.
(a) Define the term ‘bipartite graph’.
(2)
Six workers, A, B, C, D, E and F, are to be matched to six tasks, 1, 2, 3, 4, 5 and 6
The table below shows the tasks that each worker is able to do.
Worker
Tasks
A
2, 4
B
5
C
3, 4
D
2
E
4, 5, 6
F
1, 6
(b) Using Diagram 1 in the answer book, draw a bipartite graph to show the possible allocation of
workers to tasks.
(1)
Initially, workers A, C, E and F are allocated to tasks 2, 4, 5 and 6 respectively.
(c) Starting from the given initial matching, apply the maximum matching algorithm to obtain a
complete matching. You must state the alternating paths that you use, and state your improved
matching after each iteration.
(6)
(Total 9 marks)
2.
B
4
C
10
F
A
5
11
21
2
34
E
G
5
7
D
23
8
10
16
10
L
10
K
4
6
J
H
Figure 1
Figure 1 represents a network of roads. The number on each arc is the length, in km, of the
corresponding road.
(a) Use Dijkstra’s algorithm to find the shortest route from A to L. State the shortest route and its
length.
(6)
(b) Explain how you determined the shortest route from your labelled diagram.
(2)
(c) Find the length of the shortest route from J to F via A, and state your route.
(2)
(Total 10 marks)
3.
I(17)
C(7)
D(5)
J(15)
E(8)
A(6)
F(9)
K(16)
G(3)
L(11)
M(4)
B(2)
H(14)
Figure 2
A project is modelled by the activity network shown in Figure 2. The activities are represented by
the arcs. The number in brackets on each arc gives the time, in days, to complete the corresponding
activity. Each activity requires one worker. The project is to be completed in the shortest possible
time.
(a) Complete Diagram 1 in the answer book to show the early event times and the late event times.
(4)
(b) State the critical activities.
(1)
(c) Draw a cascade (Gantt) chart for this project on Grid 1 in the answer book.
(4)
(d) Use your cascade chart to determine the minimum number of workers needed to complete the
project in the shortest possible time. You must make specific reference to time and activities.
(You do not need to provide a schedule of the activities.)
(2)
(Total 11 marks)