D1: Critical path analysis – Edexcel IAL Decision Mathematics (WDM1)

3 questions · Clear filters

0 / 0Answer a question to start your score.
Quick quiz (10)Saved 0
Advertisement
1
WDM1 D1 · Oct/Nov 2021 · Question 3Oct/Nov 2021D126 marks
Loading question…
Question text

3.
The table below represents a complete network that shows the least costs of travelling between
eight cities, A, B, C, D, E, F, G and H.
A
B
C
D
E
F
G
H
A
–
36
38
40
23
39
38
35
B
36
–
35
36
35
34
41
38
C
38
35
–
39
25
32
40
40
D
40
36
39
–
37
37
26
33
E
23
35
25
37
–
42
24
43
F
39
34
32
37
42
–
45
38
G
38
41
40
26
24
45
–
40
H
35
38
40
33
43
38
40
–
Srinjoy must visit each city at least once. He will start and finish at A and wishes to minimise his
total cost.
(a) Use Prim’s algorithm, starting at A, to find a minimum spanning tree for this network. You
must list the arcs that form the tree in the order in which you select them.
(3)
(b) State the weight of the minimum spanning tree.
(1)
(c) Use your answer to (b) to help you calculate an initial upper bound for the total cost of Srinjoy’s
route.
(1)
(d) Show that there are two nearest neighbour routes that start from A. You must make the routes
and their corresponding costs clear.
(4)
(e) State the best upper bound that can be obtained by using your answers to (c) and (d).
(1)
(f) Starting by deleting A and all of its arcs, find a lower bound for the total cost of Srinjoy’s route.
You must make your method and working clear.
(3)
(g) Use your results to write down the smallest interval that must contain the optimal cost of
Srinjoy’s route.
(2)
(Total 15 marks)
4.
F(w)
12
y
13
z
G(5)
K(6)
C(v)
H(7)
L(5)
5
13
20
25
13
20
25
D(4)
x
A(5)
E(7)
M(4)
I(10)
0
6
20
0
6
21
B(6)
J(4)
Figure 2
The network in Figure 2 shows the activities that need to be carried out by a company to complete
a project. Each activity is represented by an arc, and the duration, in days, is shown in brackets.
Each activity requires one worker. The early event times and the late event times are shown at each
vertex.
(a) Complete the precedence table in the answer book.
(2)
A cascade chart for this project is shown on Grid 1.
0
2
4
6
8
10
12
14
16
18
20
22
24
26
B
E
H
L
A
C
D
F
G
I
J
K
M
Grid 1
(b) Use Figure 2 and Grid 1 to find the values of v, w, x, y and z.
(3)
The project is to be completed in the minimum time using as few workers as possible.
(c) Calculate a lower bound for the minimum number of workers required. You must show your
working.
(1)
(d) On Grid 2 in your answer book, construct a scheduling diagram for this project.
(3)
Before the project begins it is found that activity F will require an additional 5 hours to complete.
The durations of all other activities are unchanged. The project is still to be completed in the
shortest possible time using as few workers as possible.
(e) State the new minimum project completion time and state the new critical path.
(2)
(Total 11 marks)

2
WDM1 D1 · Oct/Nov 2020 · Question 2Oct/Nov 2020D127 marks
Loading question…
Question text

2.
(a) (i) Describe how to carry out the first pass of a bubble sort when it is used to sort a list of n
numbers into ascending order.
(ii) Write down the circumstances under which the bubble sort stops.
(4)
A bubble sort, starting at the left-hand end of the list, is used to sort a list of ten numbers into
ascending order. After a number of passes the list reads
0.9 1.2 1.5 0.5 1.4 1.1 0.7 1.7 2.2 3.2
(b) Determine the maximum number of passes that could have taken place on this list. You must
give a reason for your answer.
(2)
(c) Complete the bubble sort to produce a list of the numbers in ascending order. You only need to
give the state of the list after each complete pass.
(4)
(d) Use the first-fit decreasing bin packing algorithm to determine how the ten numbers listed
above can be packed into bins of size 4
(3)
(Total 13 marks)
3.
1
A
A
1
2
B
B
2
3
C
C
3
4
D
D
4
5
E
E
5
6
F
F
6
Figure 1
Figure 2
Figure 1 shows the possible allocations of six workers, A, B, C, D, E and F, to six .tasks, 1, 2, 3, 4,
5 and 6.
Figure 2 shows an initial matching.
(a) Starting from this initial matching, use the maximum matching algorithm to find an improved
matching. You should state the alternating path you use and list your improved matching.
(3)
(b) Explain why it is not possible to find a complete matching.
(1)
After training, task 1 is added to worker A’s possible allocations.
(c) Taking the improved matching found in (a) as the new initial matching, use the maximum
matching algorithm to find a complete matching. You should state the alternating path you use
and list your complete matching.
(3)
(Total 7 marks)
4.
(a) Draw the activity network described by the precedence table below, using activity on arc.
Use dummies only where necessary.
(5)
Activity
Immediately preceding activities
A
–
B
–
C
A
D
A, B
E
C, D
F
D
G
C
H
G
I
G
J
E, F, I
K
F
Given that K is a critical activity,
(b) state which other activities must also be critical.
(1)
Given instead that all activities shown in the precedence table have the same duration and K is not
necessarily critical,
(c) state the critical path for the network.
(1)
(Total 7 marks)

3
WDM1 D1 · Oct/Nov 2020 · Question 4Oct/Nov 2020D126 marks
Loading question…
Question text

4.
(a) Draw the activity network described by the precedence table below, using activity on arc.
Use dummies only where necessary.
(5)
Activity
Immediately preceding activities
A
–
B
–
C
A
D
A, B
E
C, D
F
D
G
C
H
G
I
G
J
E, F, I
K
F
Given that K is a critical activity,
(b) state which other activities must also be critical.
(1)
Given instead that all activities shown in the precedence table have the same duration and K is not
necessarily critical,
(c) state the critical path for the network.
(1)
(Total 7 marks)
5.
D(12)
J(5)
M(7)
E(3)
A(7)
N(9)
B(8)
I(3)
L(3)
H(4)
C(5)
F(2)
P(14)
K(2)
G(3)
Figure 1
A project is modelled by the activity network shown in Figure 1. The activities are represented by
the arcs. The number in brackets on each arc gives the time, in days, to complete the corresponding
activity. Each activity requires exactly one worker. The project is to be completed in the shortest
possible time.
(a) Complete Diagram 1 in the answer book to show the early event times and the late event times.
(4)
(b) Calculate a lower bound for the number of workers needed to complete the project in the
minimum time. You must show your working.
(2)
(c) Schedule the activities on Grid 1 in the answer book using the minimum number of workers so
that the project is completed in the minimum time.
(4)
Additional resources become available, which can shorten the duration of one of activities D, G or
P by one day.
(d) Determine which of these three activities should be shortened to allow the project to be
completed in the minimum time. You must give reasons for your answer.
(2)
(Total 12 marks)
6.
y
4y = 7x + 8
7
6
B
5
4y = x + 8
4
R
3
C
2
A
1
3x + 4y = 24
0
x
0
1
2
3
4
5
6
7
8
Figure 2
The graph in Figure 2 is being used to solve a linear programming problem in x and y. The three
constraints have been drawn on the graph and the rejected regions have been shaded out. The three
vertices of the feasible region R are labelled A, B and C.
(a) Determine the inequalities that define R.
(2)
The objective function, P, is given by
P = ax + by
where a and b are positive constants.
The minimum value of P is 8 and the maximum value of P occurs at C.
(b) Find the range of possible values of a. You must make your method clear.
(5)
(Total 7 marks)