D1: Critical path analysis – Edexcel IAL Decision Mathematics (WDM1)
33 questions · page 2 of 3 · Clear filters
Question text
1.
D(5)
E(2)
L(12)
A(4)
J(6)
B(3)
G(5)
F(6)
C(7)
H(6)
K(5)
I(6)
Figure 1
A project is modelled by the activity network shown in Figure 1. The activities are
represented by the arcs. The number in brackets on each arc gives the time, in hours, to
complete the corresponding activity. Each activity requires one worker. The project is to
be completed in the shortest possible time using as few workers as possible.
(a) Complete Diagram 1 in the answer book to show the early event times and the late
event times.
(4)
(b) Calculate the total float for activity D. You must make the numbers used in your
calculation clear.
(1)
(c) Calculate a lower bound for the minimum number of workers required to complete
the project in the shortest possible time. You must show your working.
(2)
(d) Draw a cascade chart for this project on Grid 1 in the answer book.
(4)
(e) Use your cascade chart to determine the minimum number of workers needed to
complete the project in the shortest possible time. You must make specific reference
to time and activities. (You do not need to provide a schedule of the activities.)
(2)
(Total for Question 1 is 13 marks)
Question text
4.
Activity
Immediately preceding activities
A
–
B
–
C
A, B
D
A, B
E
B
F
C, D, E
G
F
H
B
I
F
J
F
K
G
L
G, H, I, J
M
G, I
(a) Draw the activity network described in the precedence table, using activity on arc
and the minimum number of dummies.
(5)
(b) Given that
•
the activity network contains only one critical path
•
activity E is on this critical path
state
(i) which activities could never be critical,
(ii) which activities must be critical.
(2)
(Total for Question 4 is 7 marks)
Question text
1.
D(5)
L(12)
E(2)
A(4)
B(3)
G(5)
J(6)
Key:
F(6)
early
C(7)
H(6)
K(5)
event
time
late
event
I(6)
time
Diagram 1
Question 1 continued
0
2
4
6
8
10
12
14
16
18
20
22
24
26
28
Grid 1
(Total for Question 1 is 13 marks)
Question text
4.
Question 4 continued
Only use this blank space if you need to redraw your activity network.
(Total for Question 4 is 7 marks)
Question text
1.
I(2)
E(5)
F(6)
A(5)
N(3)
D(4)
B(7)
P(6)
J(7)
K(5)
G(2)
Q(5)
C(6)
L(4)
H(4)
M(8)
Figure 1
A project is modelled by the activity network shown in Figure 1. The activities are
represented by the arcs. The number in brackets on each arc gives the time, in days,
to complete the activity. Each activity requires exactly one worker. The project is to be
completed in the shortest possible time.
(a) Complete Diagram 1 in the answer book to show the early event times and the late
event times.
(4)
(b) Calculate the maximum number of days by which activity H could be delayed
without lengthening the completion time of the project. You must make the numbers
used in your calculation clear.
(1)
(c) Calculate a lower bound for the number of workers needed to complete the project
in the minimum time. You must show your working.
(2)
(d) Schedule the activities on Grid 1 in the answer book, using the minimum number of
workers, so that the project is completed in the minimum time.
(3)
(Total for Question 1 is 10 marks)
Question text
5.
Activity
Immediately preceding activities
A
-
B
-
C
-
D
A
E
A
F
B, C, E
G
B, C, E
H
C
I
C
J
D, F, G, H, I
K
D, F, G, H, I
L
I
(a) Draw the activity network described in the precedence table above, using activity on
arc and the minimum number of dummies.
(5)
A project is modelled by the activity network drawn in (a). Each activity requires
exactly one worker. The project is to be completed in the shortest possible time.
The table below gives the time, in hours, to complete three of the activities.
Activity
Duration (in hours)
A
10
E
7
F
8
The length of the critical path AEFK is 33 hours.
(b) Determine the range of possible values for the duration of activity J. You must make
your method and working clear.
(2)
(Total for Question 5 is 7 marks)
Question text
1.
Key:
E(5)
I(2)
Early
event
time
Late
event
N(3)
F(6)
A(5)
time
D(4)
B(7)
J(7)
K(5)
P(6)
G(2)
Q(5)
C(6)
L(4)
H(4)
M(8)
Diagram 1
Question 1 continued
0
2
4
6
8
10
12
14
16
18
20
22
24
26
28
30
32
34
36
Grid 1
(Total for Question 1 is 10 marks)
Question text
4.
Immediately
Immediately
Immediately
Activity
Activity
Activity
preceded by
preceded by
preceded by
A
–
G
M
D, G
B
–
H
N
C
–
I
P
D
A
J
Q
E
C
K
D, G
R
F
C
L
D, G
Key:
early
D(12)
L(6)
event
time
late
M(6)
A(9)
G(11)
event
K(7)
time
0
B(4)
H(8)
N(13)
0
I(12)
P(7)
R(3)
E(3)
C(9)
F(13)
J(5)
Q(5)
Diagram 1
Question 4 continued
0
2
4
6
8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 40 42 44
C
A
B
Diagram 2
(Total for Question 4 is 13 marks)
Question text
4.
D(12)
L(6)
K(7)
A(9)
G(11)
M(6)
B(4)
H(8)
N(13)
I(12)
P(7)
R(3)
C(9)
E(3)
F(13)
J(5)
Q(5)
Figure 2
[The sum of the durations of all the activities is 133 days]
A project is modelled by the activity network shown in Figure 2. The activities are
represented by the arcs. The number in brackets on each arc gives the time, in days, to
complete the activity. Each activity requires one worker. The project is to be completed
in the shortest possible time.
(a) Complete the precedence table in the answer book.
(2)
(b) Complete Diagram 1 in the answer book to show the early event times and the late
event times.
(4)
(c) State the critical activities.
(1)
(d) Calculate the total float for activity J. You must make the numbers you use in your
calculation clear.
(1)
(e) Calculate a lower bound for the number of workers needed to complete the project
in the minimum time. You must show your working.
(1)
Diagram 2 in the answer book shows a partly completed scheduling diagram for
this project.
(f) Complete the scheduling diagram, using the minimum number of workers, so that
the project is completed in the minimum time.
(4)
(Total for Question 4 is 13 marks)
Question text
2.
26
13
D(8)
I( y)
L(4)
22
26
E(1)
A(4)
F(6)
J(2)
K(5)
0
B(5)
M(3)
0
9
N(x)
C(7)
G(6)
H(9)
Figure 1
The network in Figure 1 shows the activities that need to be undertaken to complete a
project. Each activity is represented by an arc and the duration of the activity, in days,
is shown in brackets. The early event times and late event times are to be shown at each
vertex and some have been completed.
Given that
•
CHN is the critical path for the project
•
the total float on activity B is twice the duration of the total float on activity I
(a) find the value of x and show that the value of y is 7
(2)
(b) Calculate the missing early event times and late event times and hence complete
Diagram 1 in your answer book.
(3)
Each activity requires one worker, and the project must be completed in the shortest
possible time.
(c) Draw a cascade chart for this project on Grid 1 in your answer book, and use it to
determine the minimum number of workers needed to complete the project in the
shortest possible time. You must make specific reference to time and activities.
(6)
(Total for Question 2 is 11 marks)
Question text
5. The precedence table shows the eleven activities required to complete a project.
Activity
Immediately preceding activities
A
–
B
–
C
–
D
A, B
E
A, B
F
B, C
G
B, C
H
D
I
D, E, F, G
J
H, I
K
D, E, F
(a) Draw the activity network for the project, using activity on arc and the minimum
number of dummies.
(5)
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
F
C
I
J
A
D
H
K
E
B
G
Figure 3
Figure 3 shows a schedule for the project. Each of the activities shown in the
precedence table requires one worker. The time taken to complete each activity is
in hours and the project is to be completed in the minimum possible time.
(b) (i) State the minimum completion time for the project.
(ii) State the critical activities.
(iii) State the total float on activity G and the total float on activity K.
(4)
(Total for Question 5 is 9 marks)
Question text
2.
(a)
13
26
I( y)
D(8)
L(4)
22
26
E(1)
A(4)
J(2)
F(6)
K(5)
0
M(3)
B(5)
9
0
N(x)
C(7)
G(6)
Key:
Early
event
time
H(9)
Late
event
time
Diagram 1
Question 2 continued
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
Grid 1
(Total for Question 2 is 11 marks)
Question text
5.
Activity
Immediately preceding activities
A
–
B
–
C
–
D
A, B
E
A, B
F
B, C
G
B, C
H
D
I
D, E, F, G
J
H, I
K
D, E, F
Question 5 continued
Please redraw your activity network on this page if you need to do so.
(Total for Question 5 is 9 marks)
Question text
3.
The table below represents a complete network that shows the least costs of travelling between
eight cities, A, B, C, D, E, F, G and H.
A
B
C
D
E
F
G
H
A
–
36
38
40
23
39
38
35
B
36
–
35
36
35
34
41
38
C
38
35
–
39
25
32
40
40
D
40
36
39
–
37
37
26
33
E
23
35
25
37
–
42
24
43
F
39
34
32
37
42
–
45
38
G
38
41
40
26
24
45
–
40
H
35
38
40
33
43
38
40
–
Srinjoy must visit each city at least once. He will start and finish at A and wishes to minimise his
total cost.
(a) Use Prim’s algorithm, starting at A, to find a minimum spanning tree for this network. You
must list the arcs that form the tree in the order in which you select them.
(3)
(b) State the weight of the minimum spanning tree.
(1)
(c) Use your answer to (b) to help you calculate an initial upper bound for the total cost of Srinjoy’s
route.
(1)
(d) Show that there are two nearest neighbour routes that start from A. You must make the routes
and their corresponding costs clear.
(4)
(e) State the best upper bound that can be obtained by using your answers to (c) and (d).
(1)
(f) Starting by deleting A and all of its arcs, find a lower bound for the total cost of Srinjoy’s route.
You must make your method and working clear.
(3)
(g) Use your results to write down the smallest interval that must contain the optimal cost of
Srinjoy’s route.
(2)
(Total 15 marks)
4.
F(w)
12
y
13
z
G(5)
K(6)
C(v)
H(7)
L(5)
5
13
20
25
13
20
25
D(4)
x
A(5)
E(7)
M(4)
I(10)
0
6
20
0
6
21
B(6)
J(4)
Figure 2
The network in Figure 2 shows the activities that need to be carried out by a company to complete
a project. Each activity is represented by an arc, and the duration, in days, is shown in brackets.
Each activity requires one worker. The early event times and the late event times are shown at each
vertex.
(a) Complete the precedence table in the answer book.
(2)
A cascade chart for this project is shown on Grid 1.
0
2
4
6
8
10
12
14
16
18
20
22
24
26
B
E
H
L
A
C
D
F
G
I
J
K
M
Grid 1
(b) Use Figure 2 and Grid 1 to find the values of v, w, x, y and z.
(3)
The project is to be completed in the minimum time using as few workers as possible.
(c) Calculate a lower bound for the minimum number of workers required. You must show your
working.
(1)
(d) On Grid 2 in your answer book, construct a scheduling diagram for this project.
(3)
Before the project begins it is found that activity F will require an additional 5 hours to complete.
The durations of all other activities are unchanged. The project is still to be completed in the
shortest possible time using as few workers as possible.
(e) State the new minimum project completion time and state the new critical path.
(2)
(Total 11 marks)
Question text
2.
(a) (i) Describe how to carry out the first pass of a bubble sort when it is used to sort a list of n
numbers into ascending order.
(ii) Write down the circumstances under which the bubble sort stops.
(4)
A bubble sort, starting at the left-hand end of the list, is used to sort a list of ten numbers into
ascending order. After a number of passes the list reads
0.9 1.2 1.5 0.5 1.4 1.1 0.7 1.7 2.2 3.2
(b) Determine the maximum number of passes that could have taken place on this list. You must
give a reason for your answer.
(2)
(c) Complete the bubble sort to produce a list of the numbers in ascending order. You only need to
give the state of the list after each complete pass.
(4)
(d) Use the first-fit decreasing bin packing algorithm to determine how the ten numbers listed
above can be packed into bins of size 4
(3)
(Total 13 marks)
3.
1
A
A
1
2
B
B
2
3
C
C
3
4
D
D
4
5
E
E
5
6
F
F
6
Figure 1
Figure 2
Figure 1 shows the possible allocations of six workers, A, B, C, D, E and F, to six .tasks, 1, 2, 3, 4,
5 and 6.
Figure 2 shows an initial matching.
(a) Starting from this initial matching, use the maximum matching algorithm to find an improved
matching. You should state the alternating path you use and list your improved matching.
(3)
(b) Explain why it is not possible to find a complete matching.
(1)
After training, task 1 is added to worker A’s possible allocations.
(c) Taking the improved matching found in (a) as the new initial matching, use the maximum
matching algorithm to find a complete matching. You should state the alternating path you use
and list your complete matching.
(3)
(Total 7 marks)
4.
(a) Draw the activity network described by the precedence table below, using activity on arc.
Use dummies only where necessary.
(5)
Activity
Immediately preceding activities
A
–
B
–
C
A
D
A, B
E
C, D
F
D
G
C
H
G
I
G
J
E, F, I
K
F
Given that K is a critical activity,
(b) state which other activities must also be critical.
(1)
Given instead that all activities shown in the precedence table have the same duration and K is not
necessarily critical,
(c) state the critical path for the network.
(1)
(Total 7 marks)