D1: Critical path analysis – Edexcel IAL Decision Mathematics (WDM1)

33 questions · page 3 of 3 · Clear filters

0 / 0Answer a question to start your score.
Quick quiz (10)Saved 0
Advertisement
31
WDM1 D1 · Oct/Nov 2020 · Question 4Oct/Nov 2020D126 marks
Loading question…
Question text

4.
(a) Draw the activity network described by the precedence table below, using activity on arc.
Use dummies only where necessary.
(5)
Activity
Immediately preceding activities
A
–
B
–
C
A
D
A, B
E
C, D
F
D
G
C
H
G
I
G
J
E, F, I
K
F
Given that K is a critical activity,
(b) state which other activities must also be critical.
(1)
Given instead that all activities shown in the precedence table have the same duration and K is not
necessarily critical,
(c) state the critical path for the network.
(1)
(Total 7 marks)
5.
D(12)
J(5)
M(7)
E(3)
A(7)
N(9)
B(8)
I(3)
L(3)
H(4)
C(5)
F(2)
P(14)
K(2)
G(3)
Figure 1
A project is modelled by the activity network shown in Figure 1. The activities are represented by
the arcs. The number in brackets on each arc gives the time, in days, to complete the corresponding
activity. Each activity requires exactly one worker. The project is to be completed in the shortest
possible time.
(a) Complete Diagram 1 in the answer book to show the early event times and the late event times.
(4)
(b) Calculate a lower bound for the number of workers needed to complete the project in the
minimum time. You must show your working.
(2)
(c) Schedule the activities on Grid 1 in the answer book using the minimum number of workers so
that the project is completed in the minimum time.
(4)
Additional resources become available, which can shorten the duration of one of activities D, G or
P by one day.
(d) Determine which of these three activities should be shortened to allow the project to be
completed in the minimum time. You must give reasons for your answer.
(2)
(Total 12 marks)
6.
y
4y = 7x + 8
7
6
B
5
4y = x + 8
4
R
3
C
2
A
1
3x + 4y = 24
0
x
0
1
2
3
4
5
6
7
8
Figure 2
The graph in Figure 2 is being used to solve a linear programming problem in x and y. The three
constraints have been drawn on the graph and the rejected regions have been shaded out. The three
vertices of the feasible region R are labelled A, B and C.
(a) Determine the inequalities that define R.
(2)
The objective function, P, is given by
P = ax + by
where a and b are positive constants.
The minimum value of P is 8 and the maximum value of P occurs at C.
(b) Find the range of possible values of a. You must make your method clear.
(5)
(Total 7 marks)

32
WDM1 D1 · Jan 2020 · Question 1January 2020D122 marks
Loading question…
Question text

1.
The table below shows the distances, in km, between six data collection points, A, B, C, D, E and F.
A
B
C
D
E
F
A
–
35
42
55
48
50
B
–
35
40
49
52
31
C
–
42
40
47
53
49
D
–
55
49
47
39
44
E
–
48
52
53
39
52
F
–
50
31
49
44
52
Ferhana must visit each data collection point. She will start and finish at A and wishes to minimise
the total distance she travels.
(a) Starting at A, use the nearest neighbour algorithm to obtain an upper bound for the distance
Ferhana must travel. Make your method clear.
(2)
(b) Starting by deleting B, and all of its arcs, find a lower bound for the distance Ferhana must
travel. Make your calculation clear.
(3)
(Total 5 marks)
2.
C
19
B
32
A
29
25
34
30
15
22
E
F
D
30
32
13
11
17
23
18
J
H
G
20
Figure 1
(a) Define the terms
(i) tree,
(ii) minimum spanning tree.
(3)
(b) Use Kruskal’s algorithm to find the minimum spanning tree for the network shown in Figure 1.
You must clearly show the order in which you consider the edges. For each edge, state whether
or not you are including it in the minimum spanning tree.
(3)
(c) Draw the minimum spanning tree using the vertices given in Diagram 1 in the answer book and
state the weight of the minimum spanning tree.
(2)
(Total 8 marks)
3.
4
24
D(x)
10
24
E(7)
J(9)
A(4)
I(7)
33
7
0
F(5)
K(10)
z
B(5)
33
0
17
y
L(11)
G(9)
C(7)
28
17
7
33
M(9)
H(10)
17
7
Figure 2
The network in Figure 2 shows the activities that need to be undertaken by a company to complete
a project. Each activity is represented by an arc and the duration, in days, is shown in brackets.
Each activity requires one worker. The early event times and late event times are shown at each
vertex.
The total float on activity D is twice the total float on activity E.
(a) Find the values of x, y and z.
(3)
(b) Draw a cascade chart for this project on Grid 1 in the answer book.
(4)
(c) Use your cascade chart to determine a lower bound for the minimum number of workers
needed to complete the project in the shortest possible time. You must make specific reference
to time and activities. (You do not need to provide a schedule of the activities.)
(2)
(Total 9 marks)

33
WDM1 D1 · Jan 2019 · Question 1January 2019D130 marks
Loading question…
Question text

1.
(a) Define the term ‘bipartite graph’.
(2)
Six workers, A, B, C, D, E and F, are to be matched to six tasks, 1, 2, 3, 4, 5 and 6
The table below shows the tasks that each worker is able to do.
Worker
Tasks
A
2, 4
B
5
C
3, 4
D
2
E
4, 5, 6
F
1, 6
(b) Using Diagram 1 in the answer book, draw a bipartite graph to show the possible allocation of
workers to tasks.
(1)
Initially, workers A, C, E and F are allocated to tasks 2, 4, 5 and 6 respectively.
(c) Starting from the given initial matching, apply the maximum matching algorithm to obtain a
complete matching. You must state the alternating paths that you use, and state your improved
matching after each iteration.
(6)
(Total 9 marks)
2.
B
4
C
10
F
A
5
11
21
2
34
E
G
5
7
D
23
8
10
16
10
L
10
K
4
6
J
H
Figure 1
Figure 1 represents a network of roads. The number on each arc is the length, in km, of the
corresponding road.
(a) Use Dijkstra’s algorithm to find the shortest route from A to L. State the shortest route and its
length.
(6)
(b) Explain how you determined the shortest route from your labelled diagram.
(2)
(c) Find the length of the shortest route from J to F via A, and state your route.
(2)
(Total 10 marks)
3.
I(17)
C(7)
D(5)
J(15)
E(8)
A(6)
F(9)
K(16)
G(3)
L(11)
M(4)
B(2)
H(14)
Figure 2
A project is modelled by the activity network shown in Figure 2. The activities are represented by
the arcs. The number in brackets on each arc gives the time, in days, to complete the corresponding
activity. Each activity requires one worker. The project is to be completed in the shortest possible
time.
(a) Complete Diagram 1 in the answer book to show the early event times and the late event times.
(4)
(b) State the critical activities.
(1)
(c) Draw a cascade (Gantt) chart for this project on Grid 1 in the answer book.
(4)
(d) Use your cascade chart to determine the minimum number of workers needed to complete the
project in the shortest possible time. You must make specific reference to time and activities.
(You do not need to provide a schedule of the activities.)
(2)
(Total 11 marks)

Advertisement