Examiners’ Report
Principal Examiner Feedback
January 2019
Pearson Edexcel International Advanced Level
In Statistics S2 (WST02/01)
Edexcel and BTEC Qualifications
Edexcel and BTEC qualifications are awarded by Pearson, the UK’s largest awarding body. We provide
a wide range of qualifications including academic, vocational, occupational and specific programmes
for employers. For further information visit our qualifications websites at www.edexcel.com or
www.btec.co.uk. Alternatively, you can get in touch with us using the details on our contact us page
at www.edexcel.com/contactus.
Pearson: helping people progress, everywhere
Pearson aspires to be the world’s leading learning company. Our aim is to help everyone progress
in their lives through education. We believe in every kind of learning, for all kinds of people, wherever
they are in the world. We’ve been involved in education for over 150 years, and by working across
70 countries, in 100 languages, we have built an international reputation for our commitment to high
standards and raising achievement through innovation in education. Find out more about how we
can help you and your students at: www.pearson.com/uk
Grade Boundaries
Grade boundaries for all papers can be found on the website at:
https://qualifications.pearson.com/en/support/support-topics/results-certification/gradeboundaries.html
January 2019
Publications Code WST02_01_1901_ER
All the material in this publication is copyright
© Pearson Education Ltd 2019
Introduction
This paper proved to be very accessible to all students though questions 1(c), 2(d), 5(iii) and
7(d) were more discriminating.
Question 1
Part (a) proved to be challenging for many students. There were two main errors:
•
missing out the context “turning up” in their statement,
•
writing one of the necessary requirements for the binomial distribution which is
known from the question. A common incorrect answer was to write that there are 2
outcomes.
Most answered part (b) correctly although some students rounded off their answer in (i) to
obtain 0.077 rather than give at least 3 significant figures.
Part (c) was not answered well. A minority of students gained the first M1 by finding 880,
940 and 1000 or 60 and 120 but were unable to find the associated probabilities to these
values so could not work out the expected total earnings.
Question 2
Part (a) was answered well by the majority of students. The most common errors made were
to either use P( X ≤ 5) or give an incorrect answer with no working.
Many candidates identified the correct distribution, Po(6), in part (b). The vast majority then
took the approach of finding expressions for P(Y = n) and P(Y= n + 1) with many able to
obtain the correct expressions. However, some candidates were then unable to solve correctly
for n. For those candidates that took the tables approach a common incorrect answer was n =
6
In part(c) candidates struggled to write a correct expression for P(c ≤ D ≤ 12) . The most
common error seen was use of P( D ≤ c) rather than P( D ≤ c − 1) , leading to an answer of
c = 3 rather than c = 4
For those candidates that understood the demand of the question in part (d) full marks were
usually awarded. Some candidates used Po(8) or Po(12) for P( X = 2) and hence did not
obtain an answer of 0.27067... Some candidates, even those that had calculated P( X = 2)
correctly did not attempt to use the Binomial at all whilst others just had (0.2707) 4 . A few
candidates failed to include the 6C4
Question 3
Part (a) was answered well. Many students wrote down F(7) – F(3) and worked out 0.5
The most common error was to write down F(6) – F(2)
In part (b) the most popular method was to find the full cdf. A minority of students thought
this was their pdf and missed the fact that a, b and c were constants.
In part (c), most candidates made a good attempt at finding the mean and even those who had
incorrect values for part (b) scored the first two marks, although it is to be hoped that those
ending up with a mean of 30 had a little concern about the size of their answer. There were a
few candidates who decided to adopt a discrete approach and added a few values together to
reach an answer. Very few candidates chose the alternative approach mainly because they
chose not to sketch the pdf.
Question 4
This question was generally well done with fewer mistakes in part (a) than part (b) although
there were a number of scripts that were completely blank.
In part (a), the hypotheses were usually correctly stated with only a few candidates forgetting
to use p and almost all getting the inequality in H1 correct. Many candidates went on to
calculate the correct probability but a common error was to find 1 – P(X 11) or P(X = 11)
Candidates who got a probability of 0.0532 correctly compared it with 0.05 and give a correct
conclusion. The contextual statement was usually present and with sufficient clarity and
detail to gain the final mark.
Although this should have been very straightforward quite a number of candidates were
thrown by the unexpected nature of part (b). The mean was mostly correctly stated as was the
variance but quite a number of candidates failed to get the mark for the standard deviation by
leaving it in the form σ2 = 4.55
The best solutions calculated 7 + 2 × 2.133 and compared it with 11 although other correct
comparisons were seen. It was not unusual to see candidates attempt to use a Normal
distribution and standardise the value of 11 and obtain a probability for it.
Question 5
The majority of candidates managed to set up the required probability equation and show
their working to get to the required result in part (a)(i).
In part (a)(ii) There were two groups of students - those who slavishly applied the formulaic
approach P(X > c) =
b−c
4
leading, on substituting b = 4a, to 4/3 and those who applied
b−a
3
the substitution immediately to get P(X > 0) which was obviously 1. It was alarming that so
many of the first variety were content to leave their answer as a probability greater than 1.
Those that weren’t content with that often resorted to an answer of 0.
In part (b)(i) and (ii) most students gained full marks although a small number used “39” as
their denominator in (ii).
The common errors in part (b)(iii) were not squaring “21” and subtracting rather than adding
their answers even if they had quoted the correct formula at the start.
Question 6
Part (i)(a) was well answered although a significant number gave np < 10 or even np > 10 as
the condition.
The most notable errors made in part (ii)(b) was using or writing Po(750) and/or using
1 – P(Y 6)
Very few candidates gained either of the marks in (ii)
In part (a) very few candidates referred both list (oe) and to all the employees. The most
common error was to refer to the list of all the employees who cycle to work. A minority of
candidates gained the mark for part (b). The most common incorrect answer was to give a
specific Binomial or Normal distribution.
Nearly all candidates were able to gain marks in part (ii)(c). The distribution N(60, 36) was
often written clearly at the start of the solution which was good to see. The majority of
candidates then went on to gain the method mark and the B mark for the z value. The most
common errors were incorrectly applying a continuity correction and the sign of the z value,
1.5, not being compatible with the standardisation.
In part (ii)(d) many candidates were able to gain the method mark with only a minority
subtracting the continuity correction rather than adding it.
Question 7
Part (a) was well answered with many candidates gaining full marks. The candidates were
able to integrate the 2 parts of the pdf correctly, although quite a few candidates made sign
errors when substituting the corresponding limits into
cx 2
+ 3cx . Only a few candidates failed
2
to realise that both parts of the pdf needed to be used to find the value of c.
In part (b)(i) many candidates were able to sketch the correct pdf. However, there were quite
a few symmetrical sketches and sometimes the RHS was drawn above the LHS at the y-axis.
Some sketches used curves rather than straight lines. The labels –3 and 3 were usually seen
on the x-axis, although both of
5
1
and
were not always given on the y-axis.
12
4
In general candidates were able to explain why the mode was at X = 0 in part (b)(ii).
It was pleasing to see many fully correct cumulative distribution functions. The most
common error was just integrating
1
5
( t + 3) and ( 3 − x ) without adding constants and
36
12
hence, without using F(–3) = 0 and F(3) = 1 respectively. For those candidates that used the
correct limits the common error was to fail to realise that the when integrating the second line
of the pdf they also needed to add F(0). In a few cases one of 0, x < −3 and 1, x > 3 was
omitted.
Part (d) proved to be a challenge for many of the candidates. For those candidates that
understood the demands of conditional probability many correct solutions were seen.
However, some candidates wrote P( X > d ) ∩ P( X > 0) not realising that this is simply
P( X > d )
The most common errors were
3
5
instead of for 1 – F(0) and after an incorrect equation
8
8
had been obtained (but the first M1 awarded) the majority of candidates did not show how
their answer was obtained as there was usually no explicit substitution into the quadratic
formula or equivalent. Some candidates used the wrong line from their CDF. Others found
F(d) (or equivalent) correctly but did not proceed any further.
Pearson Education Limited. Registered company number 872828
with its registered office at 80 Strand, London, WC2R 0RL, United Kingdom