Computer Science (9608) · May/June 2019 · Mark scheme 13
Cambridge Computer Science (9608) mark scheme for paper 13, May/June 2019 — 9608/13/M/J/19, file 9608_s19_ms_13.pdf.
Text of this paper
www.dynamicpapers.com
Cambridge Assessment International Education
Cambridge International Advanced Subsidiary and Advanced Level
COMPUTER SCIENCE
9608/13
Paper 1 Written Paper
May/June 2019
MARK SCHEME
Maximum Mark: 75
Published
This mark scheme is published as an aid to teachers and candidates, to indicate the requirements of the
examination. It shows the basis on which Examiners were instructed to award marks. It does not indicate the
details of the discussions that took place at an Examiners’ meeting before marking began, which would have
considered the acceptability of alternative answers.
Mark schemes should be read in conjunction with the question paper and the Principal Examiner Report for
Teachers.
Cambridge International will not enter into discussions about these mark schemes.
Cambridge International is publishing the mark schemes for the May/June 2019 series for most
Cambridge IGCSE™, Cambridge International A and AS Level and Cambridge Pre-U components, and
some Cambridge O Level components.
This document consists of 10 printed pages.
© UCLES 2019
[Turn over
9608/13
Cambridge International AS/A Levelwww.dynamicpapers.com
– Mark Scheme
May/June 2019
PUBLISHED
Generic Marking Principles
These general marking principles must be applied by all examiners when marking candidate answers.
They should be applied alongside the specific content of the mark scheme or generic level descriptors
for a question. Each question paper and mark scheme will also comply with these marking principles.
GENERIC MARKING PRINCIPLE 1:
Marks must be awarded in line with:
•
•
•
the specific content of the mark scheme or the generic level descriptors for the question
the specific skills defined in the mark scheme or in the generic level descriptors for the question
the standard of response required by a candidate as exemplified by the standardisation scripts.
GENERIC MARKING PRINCIPLE 2:
Marks awarded are always whole marks (not half marks, or other fractions).
GENERIC MARKING PRINCIPLE 3:
Marks must be awarded positively:
•
•
•
•
•
marks are awarded for correct/valid answers, as defined in the mark scheme. However, credit
is given for valid answers which go beyond the scope of the syllabus and mark scheme,
referring to your Team Leader as appropriate
marks are awarded when candidates clearly demonstrate what they know and can do
marks are not deducted for errors
marks are not deducted for omissions
answers should only be judged on the quality of spelling, punctuation and grammar when these
features are specifically assessed by the question as indicated by the mark scheme. The
meaning, however, should be unambiguous.
GENERIC MARKING PRINCIPLE 4:
Rules must be applied consistently e.g. in situations where candidates have not followed
instructions or in the application of generic level descriptors.
GENERIC MARKING PRINCIPLE 5:
Marks should be awarded using the full range of marks defined in the mark scheme for the question
(however; the use of the full mark range may be limited according to the quality of the candidate
responses seen).
GENERIC MARKING PRINCIPLE 6:
Marks awarded are based solely on the requirements as defined in the mark scheme. Marks should
not be awarded with grade thresholds or grade descriptors in mind.
© UCLES 2019
Page 2 of 10
Cambridge International AS/A Levelwww.dynamicpapers.com
– Mark Scheme
May/June 2019
PUBLISHED
9608/13
Question
1(a)
Answer
1 mark for each correct entry
4
Management task
1(b)(i)
Marks
Description
Memory management
Handles the allocation of memory to
processes // Ensures two programs do
not attempt to use the same memory
locations // Keeps track of allocated and
free memory locations
Security management
Provides user accounts and
passwords
Interrupt processing
Handles the signals sent when the
attention of the processor is required
elsewhere
Provision of a
software platform
Provides an environment within which
programs can be run
1 mark per bullet point to max 2 for formatter, max 2 for defragmenter
4
hard disk formatter
• Makes existing data inaccessible
• Partitions the disk into logical drives
• Sets up the (specified) file system
• Prepares the disk for initial use
• May check for errors on the disk
hard disk defragmenter
• Re-organises the disk contents
• Moves split files so they are contiguous
• Creates a larger area of (contiguous) free space
1(b)(ii)
1 mark per bullet point
3
For example:
•
•
•
•
© UCLES 2019
Backup software
File compression
Virus checker
Disk contents analysis / repair
Page 3 of 10
Cambridge International AS/A Levelwww.dynamicpapers.com
– Mark Scheme
May/June 2019
PUBLISHED
9608/13
Question
2(a)
Answer
1 mark per bullet point
•
•
2(b)
Marks
2
Security: keep data safe from accidental/malicious damage/loss
Privacy: keep data confidential // only seen by authorised personnel
1 mark for identifying method 2 marks for description to max 2 × 3
6
For example:
• User accounts
• User has a username and password Access to resources can be limited
to specific accounts
• Cannot access system without valid username and password // prevents
unauthorised access to the system
2(c)(i)
•
•
•
•
•
Firewall
All incoming and outgoing network traffic goes through firewall
Blocks signals that do not meet requirements
Keeps a log of signals
Applications can have network access restricted
•
•
•
•
•
Anti-malware
Scans for malicious software
Quarantines or deletes any malicious software found
Scans can be scheduled at regular intervals
Should be kept up to date
•
•
•
Auditing
Logging all actions/changes to the system
In order to identify any unauthorised use
•
•
•
Application Security (accept equivalent)
Applying regular updates / patches
Finding, fixing and preventing security vulnerabilities in any (installed)
application
1 mark per bullet to max 4
•
•
•
•
•
2(c)(ii)
Each byte has a parity bit // horizontal parity
An additional parity byte is sent with vertical (and horizontal) parity
Each row and column must have an even/odd number of 1s
Identify the incorrect row and column
The intersection is the error
1 mark for correct answer
•
© UCLES 2019
4
1
Errors in an even number of bits (could cancel each other out)
Page 4 of 10
Cambridge International AS/A Levelwww.dynamicpapers.com
– Mark Scheme
May/June 2019
PUBLISHED
9608/13
Question
2(d)
Answer
1 mark per bullet point to max 3
Marks
3
For example: He should ...
• ...Keep the client’s personal data private
• ...Involve the client in the development // Communicate with the client
•
Provide the solution that the client asked for
• ...Keep the project running on time // budget
• ...Keep the client informed of any problems/delays
2(e)
1 mark per bullet point to max 3
•
•
•
•
He uses a compiler because it creates a separate executable file
The executable means the client cannot access the source code // edit
the program
The executable means the client does not need the IDE / compiler
It will (probably) be faster to run the executable than to interpret the
source code every time the program is run
Question
3(a)(i)
Answer
1 mark per bullet point
•
•
3(a)(ii)
Stores all the information about the database // data about the
data // metadata about the data
For example, fields, data types, validation, keys
•
•
Primary key uniquely identifies each tuple // Each tuple in the table is
unique
Primary key can be used as a foreign key in another table
.. to form a link/relationship between the tables
By example:
• Identification of a primary key in a table
• Describing that primary key in another table as a foreign key
© UCLES 2019
2
Allows the user to enter criteria
Searches for data which meets the entered criteria
Organises the results to be displayed to the user
1 mark per bullet point to max 2
•
Marks
2
1 mark per bullet point to max 2
•
•
•
3(b)
3
Page 5 of 10
2
Cambridge International AS/A Levelwww.dynamicpapers.com
– Mark Scheme
May/June 2019
PUBLISHED
9608/13
Question
Answer
Marks
3(c)
1 mark for each correct link
3
3(d)
1 mark per bullet point to max 3
3
•
•
•
3(e)(i)
There are no repeating groups (1NF)
There are no partial dependencies (2NF)
There are no non-key dependencies // There are no transitive
dependencies (3NF)
1 mark for correct answer
1
CREATE DATABASE EMPLOYEES;
3(e)(ii)
1 mark per bullet
•
•
•
•
•
5
Create table EMPLOYEE_DATA with open and close brackets
EmployeeID as VarChar restricted to max 7, Gender as a
VarChar restricted to max 6, DepartmentNumber as a VarChar
restricted to max 2
FirstName and LastName as VarChar (any max lengths must
be reasonable)
Date of birth as Date
Declaring EmployeeID as PK
CREATE TABLE EMPLOYEE_DATA (
EmployeeID VarChar(7),
FirstName VarChar,
LastName VarChar,
DateOfBirth Date,
Gender VarChar(6),
DepartmentNumber VarChar(2),
PRIMARY KEY (EmployeeID)
);
© UCLES 2019
Page 6 of 10
Cambridge International AS/A Levelwww.dynamicpapers.com
– Mark Scheme
May/June 2019
PUBLISHED
9608/13
Question
3(e)(iii)
Answer
Marks
1 mark per bullet
•
•
•
•
•
5
Select FirstName and LastName only
From both tables
Where DepartmentName = “Finance”
AND Gender = “Female”
Joining tables (either AND, or inner join)
SELECT FirstName, LastName
FROM EMPLOYEE_DATA, DEPARTMENT
WHERE DepartmentName = "Finance"
AND Gender = "Female"
AND DEPARTMENT.DepartmentNumber =
EMPLOYEE_DATA.DepartmentNumber;
Question
4(a)
Answer
1 mark per bullet
•
•
4(b)
2
LDM #300
LDD 300
The (denary) number 300 is loaded (into the register)
The contents of address 300 are loaded (into the
register)
1 mark for JPN correct
1 mark for both of ADD and DEC correct
1 mark for LDR correct
Description
© UCLES 2019
Marks
3
Jump
instruction
LDR #3
Load the number 3
to the Index Register
ADD #2
Add 2 to the
Accumulator
JPN 22
Move to the
instruction at
address 22
DEC ACC
Subtract 1 from the
Accumulator
Arithmetic
Data
operation movement
9
9
9
Page 7 of 10
9
Cambridge International AS/A Levelwww.dynamicpapers.com
– Mark Scheme
May/June 2019
PUBLISHED
9608/13
Question
4(c)(i)
Answer
1 mark for hardware interrupt 1 mark for software interrupt
Marks
2
For example:
Hardware interrupt
• Printer out of paper
• No CD in drive
Software interrupt
• A running program needs input
• Runtime error, e.g. division by zero
4(c)(ii)
•
•
•
•
•
•
•
•
•
•
•
© UCLES 2019
5
1 mark per bullet to max 5
At the start / end of each fetch-execute cycle the processor checks
for interrupt(s)
Check if an interrupt flag is set // Check if bit set in interrupt register
Processor identifies source of interrupt
Processor checks priority of interrupt
If interrupt priority is high enough // Lower priority interrupts are
disabled
Processor saves current contents of registers // saves current job
on stack
Processor calls interrupt handler / Interrupt Service Routine (ISR)
Address of ISR is loaded into Program Counter (PC)
When servicing of interrupt complete, processor restores
registers // job from stack is restored
Lower priority interrupts are re-enabled
Processor continues with next F–E cycle
Page 8 of 10
Cambridge International AS/A Levelwww.dynamicpapers.com
– Mark Scheme
May/June 2019
PUBLISHED
9608/13
Question
5(a)
Answer
1 mark for each correctly linked box on the right
Maximum number
of colurs
Marks
3
Minimum number
of bits
1
68
2
256
3
127
7
2
8
249
9
5(b)(i)
1 mark for correct answer
1
40 images or frames are displayed/recorded each second
5(b)(ii)
•
•
Progressive – each frame contains (all the lines for) the complete
image
Interlaced – each frame contains half the (number of lines) of the
complete image
•
•
Progressive – frames are not divided into fields
Interlaced – each frame divided into two fields // One field contains
the data for the even numbered rows / lines and the other has the
data for the odd numbered rows / lines.
•
•
Progressive – complete frames are displayed in sequence
Interlaced – data from two frames is displayed simultaneously
•
Progressive – the number of images stored is the same as the
frame rate // the rate of picture display is the same as the frame
rate.
Interlaced – the rate of picture display (the field rate) is twice the
rate of image frame display (the frame rate).
•
© UCLES 2019
4
1 mark per bullet to max 4
•
•
Progressive means the entire frame is refreshed each time
Interlaced means only half the frame is refreshed
•
•
Progressive has high bandwidth requirements
Interlaced halves the transmission bandwidth requirements.
Page 9 of 10
9608/13
Cambridge International AS/A Levelwww.dynamicpapers.com
– Mark Scheme
May/June 2019
PUBLISHED
Question
5(c)
Answer
1 mark per bullet
2
88.2 kHz
• The sound wave is sampled 88200 times per second
32 bits
• Each sample is stored as a 32-bit binary number
© UCLES 2019
Marks
Page 10 of 10