Examiners’ Report
Principal Examiner Feedback
October 2020
Pearson Edexcel International GCE
In Statistics 1 (WST01)
Paper : 01 Statistics S1

Edexcel and BTEC Qualifications
Edexcel and BTEC qualifications are awarded by Pearson, the UK’s largest awarding body.
We provide a wide range of qualifications including academic, vocational, occupational and
specific programmes for employers. For further information visit our qualifications websites
at www.edexcel.com or www.btec.co.uk. Alternatively, you can get in touch with us using
the details on our contact us page at www.edexcel.com/contactus.

Pearson: helping people progress, everywhere
Pearson aspires to be the world’s leading learning company. Our aim is to help everyone
progress in their lives through education. We believe in every kind of learning, for all kinds
of people, wherever they are in the world. We’ve been involved in education for over 150
years, and by working across 70 countries, in 100 languages, we have built an international
reputation for our commitment to high standards and raising achievement through
innovation in education. Find out more about how we can help you and your students at:
www.pearson.com/uk

October 2020
Publications Code: WST01_01_2020_ER
All the material in this publication is copyright
© Pearson Education Ltd 2020

General
This paper was accessible to all candidates with all of the questions having opening parts that
all prepared candidates should have been able to engage with.
Report on individual questions
Question 1
This proved to be a good introductory question to the paper with many students scoring full
marks and few failing to score anything at all. Some did not realise they could find the value
41
for k and simply found E(X) = and a few, who did use the fact that the sum of the
k
25
1
= 1 and gave their value of k as
probabilities = 1, made a slip in solving
k
25
Question 2
The tree diagram was usually completed accurately in part (a) and most were able to use their
diagram to find an expression in p and q for P(Water) in part (b), there were some careless
errors made in simplifying this expression though such as 0.25 × 0.1 being given as 0.25
though fortunately this did not affect the mark here. Part (c) proved more challenging with
most attempting P (V ∩ W ) = P(V) × P(W) using their answer for P(W) from part (b). There

were numerous errors occurring here with equations such as 0.4 =0.25 × ( 0.4 p + 0.35q + 0.1)
appearing quite often. Those who did apply this rule successfully often made careless
arithmetic errors in simplifying their equation which had implications for part (d). It was
disappointing that very few students realised that if W and V are independent then they could
simply write down P(W) = 0.4 from the tree diagram.
Part (d) revealed that many students’ grasp of conditional probabilities was shaky. Those
who did understand this topic were often able to secure the first two marks for forming an
equation in p and q using the given probability. They were then left with the daunting task of
solving two, unpleasant, linear equations in p and q. Of course the question was much
simpler: those who realised that P(W) = 0.4 and therefore P(J) = 0.6 could use the given
2
−q
P(=
J ) 0.4 and find q and then p very easily. Few fully
probability to quickly obtain 1=
3
correct solutions for p and q were found. In the final part few used conditional probabilities
as intended though they were sometimes able to make a correct conclusion based on their
values.

Question 3
The standard normal distribution calculations in parts (a) and (b) were answered quite well
but parts (c) and (d) was more challenging.
In part (a) the vast majority could standardise correctly and obtain a probability from the
tables. However a small number were still not sure what to do with this value and failed to
subtract it from 1 and some poor rounding ( 0.555… rounded to 0.55 rather than 0.56) meant
that others had a slightly inaccurate value and lost the final mark. Many made good progress
with part (b) though many of the usual errors were still seen. Some standardised and set
equal to 0.8 (from the probability of 80%) rather than a suitable z value. Others found the z
value of 0.8416 from tables but then used 1 – 0.8416 in their equation. Those who did use a z
value of 0.84 or better could score at least one mark here but many did not realise that a
negative value of z was required and an answer of 4.56 was common. A few attempted to use
their calculators with mixed success; if a calculator is used then they must give evidence of
using values at least as accurate as the tables and so an answer of just 3.04 without showing
their calculator value of 3.0425…first was insufficient to secure all 3 marks. In part (c) few
students realised that a conditional probability was involved but a number did arrive at a
1
probability statement of the form P(D > g) = (a) and some of these went on to find a
3
correct value of g. A significant minority confused medals with certificates and so we had
1
4
P(D > g) = × 0.80 =but a special case was available on the mark scheme and those who
3
15
arrived at g = 4.36 were still able to obtain 2 marks here. Part (d) of course did not require a
knowledge of the normal distribution but simply some careful thought about the
arrangements for the group of 3 medal winners. Some did give a probability of the form

1 − p 3 and a few obtained the correct answer.
Question 4
Part (a) was answered very well with nearly everyone finding the correct value for Q3 and
most finding the outliers correctly. A few thought that the lower outlier limit was
1.5 × IQR − Q1 and some thought the upper limit was 1.5 × Q3 In part (b) most drew the box
plot correctly with a majority having whiskers going to 10 and 45 though some used 9 and
49. Part (c) was answered very well indeed and most scored both of the marks here though a
small minority gave a correct comparison but then concluded that the data was positively
skewed. Most students failed to recognise the change in IQR and therefore the need to recalculate the limits for the outliers. Those who did show this step invariably completed the
box plot correctly. The final part was rarely answered correctly and required some careful
reasoning. For the median to be the same, the values must be either side of the median, for
the lower quartile to increase then the lower value must be inside the left hand said e of the
box. For the upper quartile to remain the same the values must be either side of the upper
quartile and so the other value must be in the upper whisker.

Question 5
In part (a) most realised that they simply needed to substitute x = 80 into the given equation.
However some then failed to give an answer for the rent in dollars and they either missed
including a $ symbol or failed to multiply their answer of 16.946 by 1000. Part (b) was
probably the easiest part of the paper and nearly all students scored full marks here. Most
students knew how to find the correlation coefficient r and realised that they required a value
for Sxy but far fewer were able to find this successfully. Those who realised that it was
simply the gradient of the regression line multiplied by Sxx usually went on to score all 4
marks here. A few students gave their final answer as 0.91 rather than to 3 significant figures
as instructed on the front of the question paper. Part (d) proved, unsurprisingly, challenging.
A good number of students were able to show that the new mean and the old mean were both
equal to 90 but few went on to state that since the new value of x = 90 then the extra ( x − x )

term would be zero and so Sxy was unchanged. Some students recognised in part (e) that the
gradient of the regression line would be the same and those who also calculated the new
value of y were able to obtain a correct new equation. In part (f) most stated that 3000 m2
was too large an area to use but few gave a suitable reason by either comparing 3000 m2 with
the mean area of 900 m2 or comparing 300 with the mean of x = 90.

Question 6
Parts (a) to (d) here were familiar territory for many students and there were many good
answers to these parts. The usual errors in (b) were very occasionally seen: thinking Var(A)
= E(A2), subtracting E(A) instead of [E(A)]2 and rarely dividing a correct expression for E(A2)
by 5. There was still some confusion over the correct terminology in part (c) with “discrete
random variable” being quite common whilst other invented their own title such as “fair
distribution” or “even distribution”. Most students obtained k = 6 in part (d) by calculating
E(B), it was extremely rare to see a student using “symmetry” as their reason.
The final 3 parts of this question were, as expected, more challenging. In part (e) many
1
attempts found the z value for Sam as − but few realised that for Tim this meant that
6
3.5 − A
1
< − and therefore A > 4.2 leading to a probability of 0.25 + 0.15 = 0.4 In part (f)
4
6
most students gave their value of a and their value of b either directly or in a suitable
standardisation and then we could easily see whether they were working with a correct z
value of – 3.5 It was unfortunate that those who simply looked up 3.5 in the tables would
see a value of 0.9998 and without supporting working this could not be awarded full marks.
Those who clearly had used A = 7 and B = 1 were often able to score the final 2 marks in part
(g) but some failed to relate this part back to the earlier distributions and thought some
complex calculation involving a normal distribution was required here.

Pearson Education Limited. Registered company number 872828