Mark Scheme (Results)
October 2021
Pearson Edexcel International Advanced Subsidiary
In Information Technology (WIT14/ 01)
Unit 4

Edexcel and BTEC Qualifications
Edexcel and BTEC qualifications are awarded by Pearson, the UK’s largest awarding body. We
provide a wide range of qualifications including academic, vocational, occupational and specific
programmes for employers. For further information visit our qualifications websites at
www.edexcel.com or www.btec.co.uk. Alternatively, you can get in touch with us using the details
on our contact us page at www.edexcel.com/contactus.

Pearson: helping people progress, everywhere
Pearson aspires to be the world’s leading learning company. Our aim is to help everyone
progress in their lives through education. We believe in every kind of learning, for all kinds of
people, wherever they are in the world. We’ve been involved in education for over 150 years,
and by working across 70 countries, in 100 languages, we have built an international
reputation for our commitment to high standards and raising achievement through
innovation in education. Find out more about how we can help you and your students at:
www.pearson.com/uk

October 2021
Question Paper Log Number P69296A
Publications Code WIT14_01_2110_MS
All the material in this publication is copyright
© Pearson Education Ltd 2021

General Marking Guidance
•

All candidates must receive the same treatment. Examiners must mark the
first candidate in exactly the same way as they mark the last.

•

Mark schemes should be applied positively. Candidates must be rewarded
for what they have shown they can do rather than penalised for omissions.

•

Examiners should mark according to the mark scheme not according to
their perception of where the grade boundaries may lie.

•

There is no ceiling on achievement. All marks on the mark scheme should
be used appropriately.

•

All the marks on the mark scheme are designed to be awarded. Examiners
should always award full marks if deserved, i.e. if the answer matches the
mark scheme. Examiners should also be prepared to award zero marks if
the candidate’s response is not worthy of credit according to the mark
scheme.

•

Where some judgement is required, mark schemes will provide the
principles by which marks will be awarded and exemplification may be
limited.

•

When examiners are in doubt regarding the application of the mark scheme
to a candidate’s response, the team leader must be consulted.

•

Crossed out work should be marked UNLESS the candidate has replaced it
with an alternative response.

Question
number
1(a)i

Answer

Additional
Guidance

Presence check and format check for LastName
A1 Presence check on LastName field
Required set to yes
OR validation rule of ‘Is Not Null’
A2
A3

Mark

1

2

Input mask or suitable validation rule on LastName
field
Force uppercase for first letter (1)
Max of 24 lowercase characters (1)
Input mask >L<????????????????????????
Total

1(a)ii
A4

Data type
Availability set to Yes/No
OR
Email set to Hyperlink

1

Total
Question
number
1(b)

Answer

Additional
Guidance

Edit venue form
B1 Form does not include Language field
B2 ProgrammerID is disabled
B3 Three from:
• Form labels are appropriate (not database field
names)
• Form has meaningful title
• Entry boxes on form are resized appropriately
to reflect the data they will be used to enter
• Instructions on how to use
• Asterisk on any field except ProgrammerID
• ProgrammerID or Email fields disabled
B4 Button present and suitably labelled e.g. Save/ image
of a disc
B5 Email address would be generated

B6
B7
B8

3

1
Mark

1
1
1

1
1

[email protected]
FirstName, LastName, Email, Available would save in
programmer table
Save message would display
Save message would display only if record has saved

1

Total

1
1
8

Question
number
1(c)

Answer

Additional
Guidance

Table Structure

C1

Use of appropriate table and field names and naming
conventions
C2
Customer table is present with suitable fields
C3
Project table is present with suitable fields
C4
ProjectPhase table is present with suitable fields
C5
1:M relationship between Customer and Project
C6
1:M relationship between Project and ProjectPhase
C7
1:M relationship between Programmer and
ProjectPhase
C8
Appropriate primary key used for Customer table
C9
Appropriate primary key used for Project table
C10 Appropriate composite key used for ProjectPhase
C11 Date/Time is used for at least one of ProjectStartDate,
TargetEndDate, ActualPhaseStartDate
And
Text used for CustomerMobile
And
Number used for PhaseDurationDays

1
1
1
1
1
1
1
1
1
1
1

Total

Question
number
1(d)

Mark

Answer

Additional
Guidance

Import
D1 Customer table – 21 records
D2 Project table – 35 records
D3 Project Phase table – 40 records
Total

11

Mark

1
1
1
3

Question
number
1(e)

Answer
Indicative content

Mark
9

Analysis
•
•
•

•
•

There is more than one record for each programmer. This means
there is data redundancy.
Each programmer has multiple primary keys associated with
them.
Some of the details for a programmer do not match e.g. Nicole
Chapman has one record where FirstName is Nicola and email is
different. Rose Boyd has one record where FirstName is Rosie and
the email is different. This means the data is inaccurate and has
led to anomalies.
There could be further anomalies if any of the details needed to
be updated.
There is a 1:M relationship between the programmer and the
languages because a programmer can use more than one
language. This is why there is more than one record for each
programmer

Recommendations
•
•
•
•
•
•
•
•

Level
Level 1

Mark
0
1-3

Level 2

4-6

Level 3

7-9

Create a new table called tblLanguage.
Put it in a the tblLanguage and have a primary key called
LanguageID
Make a note of the languages each programmer can use
Delete the language field from tblProgrammer
Remove all duplicate records from tblProgrammer
Create a new table called tblProgrammerLanguage
Make a composite key of LanguageID and ProgrammerID
Create the records to link each programmer with the languages
they can use
Descriptor
No Awardable content
• Analysis is flawed or superficial, containing simple statements that
show limited understanding of the subject matter.
• Solution may contain some aspects that are appropriate, but is
generally ineffective.
• Analysis is sound, containing minor inaccuracies or omissions, showing
some understanding of the given issue.
• Solution is workable but may have minor issues.
• Analysis is sound and developed, containing ideas that are linked
together in a fluent and logical way, showing a thorough understanding
of the given issue.
• Solution is appropriate and workable.
Total 9
Total for question 1
35

Question
number
2(a)

Answer

Additional
Guidance

Mark

Programmers and programming languages query

Programmer table results

A1
A2
A3
A4
A5
A6

Project Phase results

Programmer table used rather than Project Phase
table
Number of programmers per language generated
Generated field has suitable field name
Number of programmers sorted into ascending order
Columns not truncated
Correct results shown

1

Total

1
1
1
1
1
6

Question Answer
number
2(b)(i)
Project check query

B1 Correct (related) tables added (customer, project, project
phase)

Additional Mark
Guidance

Follow
through
on their
database
structure

B2 Criteria correct for ProjectID
• 1 or 7
Calculation for target project length
(may be present in the report 2 (b)(ii)
B3
• TargetEndDate – ProjectStartDate
• DateDiff(“d”,[ProjectStartDate],[ActualProjectEndDate])
• TargetEndDate – ProjectStartDate + 1
• DateDiff(“d”,[ProjectStartDate],[ActualProjectEndDate])
+1

1

1

1

Total 3

Question
number
2(b)(ii)

Answer

Additional
Guidance

Mark

Project check report

Customer names may have been concatenated in query or may show them
separately here

B4
B5
B6
B7
B8
B9
B10

Title is in the page or report header – mark from
design view only (do not accept title in detail section)
Title is as given
Grouped by ProjectID– mark from design view only
Shading used on title OR phase field headings
Centre alignment used on at least one of the fields
and values shown
actual project length uses correct formula
=Sum(ActualPhaseDurationDays)
actual project length in ProjectID footer
Conditional formatting completed early or on
time

1
1
1
1
1
1
1

B11

B12
B13
B14

Rule added to check actual project length is less than
or equal to the target project length
Conditional formatting project took longer
Rule added to check actual project length is greater
than the target project length
Red or green background added
Report is as given

1

1

1
1
Total 11
Total for question 2 20

Question
number
3a

Answer

Additional
Guidance

Mark

Query for Chart

A1
A2

No inappropriate fields included
Number of projects calculated correctly e.g.
• Count(CustomerID)

A3

Criteria correct for number of projects
• >=3
• >2
Generated field has a suitable field name

A4

Any field is
appropriate
for the
count

1
1

1

1
Total 4

Question
number
3b

Answer

Additional
Guidance

Mark

Chart
Chart data

B1
B2
B3
B4
B5

B6

Bar/column/pie chart created
Meaningful chart title used
Axis shows programmer name (or legend for pie chart)
At least one axis has suitable label (or legend for pie
chart)
Bar/column
• Axis contains suitable scale Or data values are
shown
Pie
• Data values are shown
Chart is fit for purpose

1
1
1
1
1

1

Bar/column
• No legend
• Appropriate sizing of elements on page (e.g.
title larger than axis labels, data labels)
Pie
• Appropriate sizing of elements on page (e.g.
title larger than legend labels, data values)
Total 6

Question
number
3c

Answer

Additional
Guidance

Mark

Chart button
C1 Button added to report
C2 Button would print the chart

1
1
Total 2
Total for question 3 12

Question
number
4

Answer

Additional
Guidance

Mark

Dashboard

A1
A2
A3

List box added with at least one option
Both options are as given
Data input form from 1(b) would open
OR query from 2(a) would run when option selected

1
1
1

A4

List box uses correct action depending on option
selected for both options

1

Total 4
Total for question 4 4

Question
number
5

Answer

Mark

Indicative content

9

Analysis
•

•

•

•

Some appropriate features
o Combo boxes for programming language and customer.
o Buttons to save, close and add a customer if they don’t already
exist.
o Date picker.
o Form title clearly gets purpose across
o Section titles clearly get purpose across
o Most field widths suitable.
o Labels are generally easy to read
o Asterisk for required data entry
o Disabled fields to stop accidental change of data etc.
Data accuracy
o Project end date is before the project start date.
o Programming language is showing underneath the phase ID label.
o There is a phase start date that is before the start date for the
project.
o Don’t know whether the data underneath the select language
combo box is for the language or perhaps phase ID.
User help
o Can only see titles and asterisks. They do clearly show where data
must be entered and give an indication of what the form and each
section is for.
Ease of use
o Project details section looks easy to use as just need to pick two
dates. Sensible to have that as the first section.
o Phase detail section not as easy to use as programming language
and phase ID are confusing. Also could be hard to remember a
programmer’s ID. Does make sense to have this section after the
project details section. Phases in descending order.
o Customer section quite easy to use only have to pick a customer or
click the add button if they don’t exist. Label for customer bit hard
to read.
o Save and close buttons good to have but does not make sense to
have save button right at the top when you would finish the data
input at the bottom of the page. Does not make sense to have the
buttons separated either.

Recommendations
•
•
•
•

Make the labels consistent e.g. add space in StartDate
Add validation to make sure the project start date cannot be in the
past
Add validation so that the end date has to be later than the project
start date
Add the phase ID field under the phase ID. Could possibly make it a
combo box to select the phase number. This could prevent potential
problems such as trying to duplicate the phase ID or missing a phase

•

•
•

•

•

•

Level
Level 1

Mark
0
1-3

Level 2

4-6

Level 3

7-9

out e.g. jumping from 1 to 3. Could also potentially automate it so
that the first phaseID is always 1 and then it increments by 1 after
that. It could be disabled then so prevent inaccuracies and reduce
data input. Phases could be arranged in ascending order.
Could use a date picker on the start date for the phase. Could also
validate to make sure the start date cannot be before the project
start date and that the phase dates make sense
Move the language to underneath the select language label.
Could use a combo box for the programmer that shows the
programmer names as easy to remember than IDs and would
prevent trying to use a programmer that does not exist
Move the label for the customer so that it is in line with the field.
Move the customer section to the top next to the project details
section as makes sense to pick a customer before adding the phase
details.
Move the save and close button to the bottom of the form so they
are together and near to where the user will be when they have
finished all input.
Could add a help button with further help and make sure validation
that is added has suitable error messages e.g. message to explain
that the project end date cannot be before the project start date.
Descriptor
No Awardable content
• Analysis is flawed or superficial, containing simple statements that show
limited understanding of the subject matter.
• Solution may contain some aspects that are appropriate, but is generally
ineffective.
• Analysis is sound, containing minor inaccuracies or omissions, showing
some understanding of the given issue.
• Solution is workable but may have minor issues.
• Analysis is sound and developed, containing ideas that are linked together
in a fluent and logical way, showing a thorough understanding of the given
issue.
• Solution is appropriate and workable.
Total for question 5 9