Mathematics · June 2025 · Examiner report · Paper 31
Edexcel A Level Mathematics examiner report for Paper 31, June 2025 — 9MA0/31, file 9ma0-31-pef-20250814.pdf.
Text of this paper
Examiners’ Report
Principal Examiner Feedback
Summer 2025
Pearson Edexcel GCE
In Mathematics (9MA0)
Paper 31 Statistics
Edexcel and BTEC Qualifications
Edexcel and BTEC qualifications are awarded by Pearson, the UK’s largest awarding body.
We provide a wide range of qualifications including academic, vocational, occupational and
specific programmes for employers. For further information visit our qualifications websites
at www.edexcel.com or www.btec.co.uk. Alternatively, you can get in touch with us using
the details on our contact us page at www.edexcel.com/contactus.
Pearson: helping people progress, everywhere
Pearson aspires to be the world’s leading learning company. Our aim is to help everyone
progress in their lives through education. We believe in every kind of learning, for all kinds
of people, wherever they are in the world. We’ve been involved in education for over 150
years, and by working across 70 countries, in 100 languages, we have built an international
reputation for our commitment to high standards and raising achievement through
innovation in education. Find out more about how we can help you and your students at:
www.pearson.com/uk
Summer 2025
Publications Code 9MA0_31_2506_ER*
All the material in this publication is copyright
© Pearson Education Ltd 2025
General Comments
The standard of work seen on this paper this year was encouraging with most learners being
able to make a start on all questions but some of the later parts such as 2(c), 4(e) and (f) and
6(c) provided some discrimination.
Comments on individual questions
Question 1
Most learners appeared comfortable working with tree diagrams and could find the
probability of selecting a yellow bead from bag B correctly. A small minority wrote down a
3
but did not solve it correctly but the vast majority
correct equation such as 4 × p =
12
16
obtained p = 9 and were able to go on and complete the tree diagram correctly. A few
16
responses had different pairs of probabilities on the branches for bag B.
Part (b) was usually answered well, but the most common error was to overlook the “at least”
condition and omit the case for two yellows. The most popular approach was to identify the 4
cases from the tree diagram but a few used 1 − P (Y Y ) =1 − 2 × 7 and some used
3 16
1 − P ( RR ) − P ( GR ) . Few responses did not present their answers in (b) and (c) as exact
fractions as required.
In part (c) many could write down
P (W ∩ X )
but appreciating that W ∩ X meant that the
P( X )
case GY was required defeated a large number. It was fairly common to see the answer to part
(b) or 9 appearing in both the numerator and denominator and leading to an incorrect
16
answer of 1 .
4
Question 2
The majority of learners answered parts (a) and (b) very well. A very small minority used
364 902
in part (a) and a sizeable number found the variance not the standard deviation in
6612
part (b).
Part (c) proved to be more challenging with many choosing coach A on the basis that the
lower standard deviation meant that those runners would be more “consistent”. A good
number of responses chose coach B citing the larger standard deviation as a reason, but few
were able to explain that the larger standard deviation increases the likelihood of an extreme
value such as the fastest time. A small minority of responses did not consider standard
deviation and instead incorrectly focused on the different sample sizes.
Question 3
Part (a) was usually answered well. Some explicitly stated the correct model but others
achieved this mark by giving one of the correct probabilities though accuracy marks were
often not gained as a number of responses truncated in (i) to give 0.0847 and others simply
gave 0.002 in (ii) rather than to the 3 significant figures expected. In part (ii) the most
commonly seen incorrect answer was 0.0167 caused by thinking that the phrase
“more than 3” included 3 or using 1 − P(𝐷𝐷 ⩽ 2) as the complement for P(D > 3).
In part (b) most responses had the correct binomial model or inferred it by stating a suitable
probability. A common mistake though was to use P(X = 8) rather than 𝑃𝑃(𝑋𝑋 ⩾ 8) which did
not gain either of the remaining marks. Those with the correct probability sometimes gave a
comparison with 0.05 rather than 0.025 and did not gain the final mark and others did not
give a conclusion in context. Although a critical region was not required here (we will only
ask for this if it can be found using the tables provided) some did use this approach. Many
were successful but a few did not give both tails of the critical region and others did not state
the critical region properly for example by just stating P ( X 9
) = 0.0177... and not writing
the critical region as 𝑋𝑋 ⩾ 9 and X = 0. A small number attempted to use a normal
approximation here.
Question 4
On the whole this question proved quite challenging as it tested a number of topics: sampling,
regression, correlation and hypothesis testing as well as using the large data set and having a
number of parts requiring a written explanation. However, there was something for all
learners and very few blank responses were seen and parts (e) and (f) provided an opportunity
for differentiation.
Part (a) was answered well though some incorrect responses of “stratified” or “quota
sampling” were seen. There were very few responses not using the correct terminology here.
In part (b) most identified that “trace” or “tr” would need attention, but some did not link this
to the rainfall variable. In part (c) (i) there were many correct answers and some who
identified mm or hours but not in a correct combination: answers such as mm2 or even
hour mm −1 were seen, whilst others appeared not to be that familiar with the large data set and
used other incorrect units such as oktas, lumens or Hpa. Most responses gave a suitable
contextual response to part (ii) but some simply said that 0.714 was the minimum rainfall
rather than the (average) rainfall when there was no sun. The majority of responses
recognised the inconsistency between Kay’s teacher’s claim and Kay’s data and many cited
“positive correlation” for Kay’s data as their reason. A few opted to substitute two different
values into the equation of the line to demonstrate their point. A small minority believed the
teacher’s claim to be true and they were perhaps relying on their knowledge of weather
conditions rather than interpreting the data Kay had collected.
Part (e) was found to be much more challenging for learners. Many were able to state the
hypotheses correctly although some had an alternative hypothesis of ρ >0 and a few had a
null hypothesis of ρ = 0.015 though few were using r instead of ρ. Very few responses
interpreted the p-value with many comparing it to 0.16 or comparing 0.16 with 0.05 but some
gave a correct conclusion in context. Good attempts to part (f) were rare and blank responses
not uncommon. Many answers did not give full and precise definitions and others lacked
clarity so that they could have been interpreted as either the sample or a population. For part
(i) the information was given in the question but few were able to extract the relevant
information: the variables (sun and rain) for May to October (or from the large data set) from
2015. Part (ii) produced a slightly better response with successful comments such as “sun
and rain from all of 2015” or “all the variables in the large data set” or “from all across the
UK” being seen. Common mistakes often involved describing a population for which the
sample was not a subset such as using months from April to November or the year 2016.
Question 5
This question was answered very well. Most knew how to use their calculators to answer part
(a) though some didn’t appreciate the difference between discrete and continuous random
variables and in part (i) calculated P(𝑀𝑀 ⩾ 187) whilst others incorrectly applied a continuity
correction.
In part (b) many correctly formed and solved their simultaneous equations, but some made
sign errors in their z-values and a few did not standardise correctly for example using 0.4 and
0.15 as z-values. Those who sketched a diagram of the distribution usually avoided sign
errors. Some did not use accurate enough z-values (the tables give values to 4 decimal places)
and this often meant they lost an accuracy mark for their value of sigma. Many relied on their
calculator for solving the simultaneous equations which was fine if the equations were correct
but without some written attempt to eliminate one variable, we were unable to give further
credit if the equations were incorrect. Some responses accepted a negative standard deviation
without checking to identify the error.
Part (c) was completed successfully by many learners though many used their calculated
mean and standard deviation from part (b) to calculate P(170 < F < 175) rather than using the
information in the question in the calculation 1 – (0.4 + 0.15). A few responses added the two
probabilities rather than multiplying here.
Question 6
This question provided some challenge and discrimination for the end of the paper. Most
learners attempted this and made some progress.
Part (a) was a “show that” question and learners need to remember therefore to show all steps
in their working clearly and present a solution without incorrect working. Most were able to
identify that they needed to use the fact that the sum of the probabilities equalled 1. A
popular starting point was to write down 1= 2 + 4 + 6 + ... + 2n and some were then able to
k
k
k
k
recognise that an arithmetic series was involved and use a suitable formula to find the sum.
Some learners didn’t use the correct number of terms with 2n or 4 (from the 4 terms 2, 4, 6
and 2n) being common errors. Full and concisely presented solutions were rare.
Part (b) was generally answered well, though some were confused by the even number
restriction and attempted 16 + 17 + 18 + ... + 24 + 25 and a few included 26. Those who
420
attempted P(𝑅𝑅 ⩽ 24) − P(𝑅𝑅 ⩽ 14) were rarely successful but many simply listed the 5 cases
required and were readily able to reach the correct answer.
The attempts seen in part (c) were encouraging with many realising that the discriminant of
the quadratic equation was required and for “no real roots” this must be negative. Most of
these learners were able to form the correct quadratic equation in g and find the correct
critical values but the correct critical region eluded some with g < 2 and g < 10 being a
common error. From the correct inequalities for g it was a small step to identify that the
values of g required were 4, 6 and 8 and the majority of learners who got this far were able to
complete the solution and state the correct probability in the correct form.
Pearson Education Limited. Registered company number 872828