Mark Scheme (Result)
October 2020
Pearson Edexcel GCE
In AS Level Mathematics
8MA0 Paper 21 Statistics

Edexcel and BTEC Qualifications
Edexcel and BTEC qualifications are awarded by Pearson, the UK’s largest awarding body. We
provide a wide range of qualifications including academic, vocational, occupational and specific
programmes for employers. For further information visit our qualifications websites at
www.edexcel.com or www.btec.co.uk. Alternatively, you can get in touch with us using the
details on our contact us page at www.edexcel.com/contactus.

Pearson: helping people progress, everywhere
Pearson aspires to be the world’s leading learning company. Our aim is to help everyone progress in
their lives through education. We believe in every kind of learning, for all kinds of people, wherever they
are in the world. We’ve been involved in education for over 150 years, and by working across 70
countries, in 100 languages, we have built an international reputation for our commitment to high
standards and raising achievement through innovation in education. Find out more about how we can
help you and your students at: www.pearson.com/uk

October 2020
Publications Code 8MA0_21_2010_MS
All the material in this publication is copyright
© Pearson Education Ltd 2020

General Marking Guidance

•

All candidates must receive the same treatment. Examiners must mark
the first candidate in exactly the same way as they mark the last.

•

Mark schemes should be applied positively. Candidates must be
rewarded for what they have shown they can do rather than penalised
for omissions.

•

Examiners should mark according to the mark scheme not according to
their perception of where the grade boundaries may lie.

•

There is no ceiling on achievement. All marks on the mark scheme
should be used appropriately.

•

All the marks on the mark scheme are designed to be awarded.
Examiners should always award full marks if deserved, i.e. if the answer
matches the mark scheme. Examiners should also be prepared to
award zero marks if the candidate’s response is not worthy of credit
according to the mark scheme.

•

Where some judgement is required, mark schemes will provide the
principles by which marks will be awarded and exemplification may be
limited.

•

When examiners are in doubt regarding the application of the mark
scheme to a candidate’s response, the team leader must be consulted.

•

Crossed out work should be marked UNLESS the candidate has replaced
it with an alternative response.

Question

1

Scheme

1 square is

78
 78

= 
= 1.5 and ( 8  1 + 1 8)  "1.5"
12  3 + 3  4 + 2  2  52

24 students took less than 11 minutes

"24"
100
78 + "24"+ 1 8  "1.5"+ 3  4  "1.5"
= 18.18…
awrt 18%

Percentage of students =

Marks

AOs

M1

3.1a

A1

1.1b

M1

3.1b

A1
(4)

1.1b
Total 4

1

M1:

A1:
M1:
A1:

Notes
For clear use of frequency density to establish the fd scale and then use the area to find
frequency of <11 minutes. Allow maximum of 3 errors in either the heights or widths in
total if working shown. They may calculate the area using other size squares.
Allow for realising they need to find the total number of squares (88) maximum of 4 errors
in either the heights or widths and number < 11 minutes(16) - must have a maximum of 1
error in either the heights or widths (and not use the 78 as part of calulation)
For correct values seen. Allow for 88 and 16
For realising the need to find the total and calculating a percentage. ( with “their 24” as the
numerator). Allow ( 8 1 + 2  8 )  "1.5" instead of "24"+ 1 8  "1.5" If working shown can
allow maximum of 2 errors in either the heights or widths in the calculation of the total.
Allow “their 24” / 132 oe
awrt 18

Question

Scheme

2(a)

0 to 500 m

(b)

1100 + 1600 + 1.5  1600 [= 5100]
5300 > 5100 therefore outlier

(c)

As the humidity increases the mean visibility decreases

(d)

(Hours of) sunshine

Marks

AOs

B1
(1)
M1
A1
(2)
B1
(1)
B1
(1)

1.2
2.1
1.1b
2.4
2.2b
(5 marks)

Notes

(a) B1:
(b) M1:
A1:
(c)

B1:

(d) B1:

For realising it is the maximum distance and distance given with correct units.
Allow 0 to 50dm or < 500m or < 50dm
Attempt to find Q3 and the upper limit
5100, if a value for the point is stated it must be above 5100 otherwise it is A0. For a
statement comparing and conclusion it is an outlier or it is above Q3 +1.5IQR. Allow accept
the point circled is greater than 5100 oe
For a suitable interpretation of a negative correlation mentioning humidity and visibility
A correct deduction that the unlabelled variable is the hours of sunshine. Condone missing
hours. Do not allow if more than one variable given.
Must be quantative variable
Not cloud cover since values bigger than 8
Not wind speed since values not integers
Not daily mean temperature since mean temperature near to zero are unlikely in June

Question

3

Scheme

Overall method
a + b = 2c + 0.5 oe or a + b = 2 (1 − a − b )
a + b + c = 0.75 oe

3c = 0.25

1

c = 0.0833... or 12 

1
" 0.15 + 0.12
12
= 0.035 oe

P(scoring 2,4 or 4,2 or 3,3) = 2  "

Marks

AOs

M1
B1
B1

2.1
2.2a
1.1b

M1

1.1b

M1

3.1b

A1cso
1.1b
(6)
(6 marks)

Notes

3

A fully correct method with all the required steps. For gaining 2 correct equations with at
least one correct(allow if unsimplified). Attempting to solve to find a value of c followed by
correct method to find the probability
B1:
Forming a correct equation from the information given in the question
B1:
A correct equation using the sum of the probabilities equals 1
1
Correct method for solving 2 equations to find c Implied by c =
M1:
12
Recognising the ways to get a total of 6. Condone missing arrangments or repeats. Do not
ignore extras written unless ignored in the calculation. May be implied by
M1:
1
m  " " 0.15 + n  0.12 where m and n are positive integers
12
7
oe
A1cso: Cao 0.035,
200
M1:

Question

4(a)

Scheme

It is not possible to have a sampling frame

Marks

AOs

B1

2.3

(1)
(b)

Quota sampling and (catch 85 common carp, 45 mirror carp and 30
leather carp) or (ignore any fish caught of a type where the quota is full)
Quota sampling and catch 85 common carp, 45 mirror carp and 30 leather
carp and ignore any fish caught of a type where the quota is full

M1

1.1a

A1

1.1b

(2)
(c)

3053  692 
=
−

160  160 

2

= 0.6129…

awrt 0.613

M1

1.1b

A1

1.1b

(2)
(d)(i)
(ii)

This would have no effect as the piece of data would remain in the same
class
This would increase the standard deviation as change in mean is small and
6.4 − 4.6  3 therefore estimate of standard deviation will increase

B1

2.2a

B1

2.2a

(2)
(7 marks)
Notes

(a)

B1:

(b)

M1:
A1:

(c)

M1:
A1:

(d)

B1:
B1:

For the idea there cannot be a sampling frame/list
Quota sampling and either for the correct numbers of each type or for the idea that if quota
full ignore the fish.
Quota sampling and both the correct numbers of each type and for the idea that if quota full
ignore the fish or sample until all quotas are full
A correct expression for 
Awrt 0.613 allow s = awrt 0.615
Correct deduction with suitable explanation
Allow range for class.
Do not allow there is no differences
Correct deduction with suitable explanation. so would increase the standard deviation and a
suitable reason. Allow the value is bigger than any others in the table oe

Question

5(a)

Scheme

 1
B  9, 
 6

Let C = the number of successful calls. C

P ( C  3) = 1 − P ( C  2 ) = 0.1782…
(b)

awrt 0.178

Let X = the number of occasions when at least 3 calls are successful.
4
P ( X = 1) = 5  ("0.1782...")  ("0.8217...")
= 0.4061…

(c)

H0 : p =

1
6

H1 : p 

awrt 0.406

1
6

Let R = the number of successful calls R

 1
B  35, 
 6

P( R  11) = 1 − P( R  10) = 0.02...
There is sufficient evidence to support that Rowan has more successful
sales calls than Afrika.

Marks

AOs

M1

3.3

A1
(2)

1.1b

M1

1.1b

A1
(2)

1.1b

B1

2.5

M1

3.3

A1

3.4

A1

2.2b

(4)
(8 marks)
Notes
5(a)

M1:
A1:

For selecting the right model
awrt 0.178

(b)

M1:

For 5  ("their(a)")  ("1 − their( a)")

(c)

A1:
B1:
M1:
A1:
A1:

4

awrt 0.406
for correctly stating both hypotheses in terms of p or  Accept p = 0.16
For selecting a suitable model. May be implied by a correct probability or CR
Correct probability statement and answer of 0.02 or better (0.02318…)
(CR R  11 and either P ( R  9 ) = 0.9450 or P ( R  10 ) = 0.9768 or 1 − P ( R  10 ) = 0.0232 )
Dependent on M1A1 but can ignore hypotheses. For conclusion in context supporting
Rowan’s belief / Rowan is a better sales person
Do not accept Rowan can reject H0