Mathematics B · June 2012 · Mark scheme · Paper 1
Edexcel International GCSE Mathematics B mark scheme for Paper 1, June 2012 — 4MB0/01, file 4MB0_01_rms_20120823.pdf.
Text of this paper
Mark Scheme (Results)
Summer 2012
International GCSE Mathematics
(4MB0) Paper 01
Edexcel and BTEC Qualifications
Edexcel and BTEC qualifications come from Pearson, the world’s leading learning
company. We provide a wide range of qualifications including academic, vocational,
occupational and specific programmes for employers. For further information, please
visit our website at www.edexcel.com.
Our website subject pages hold useful resources, support material and live feeds from
our subject advisors giving you access to a portal of information. If you have any subject
specific questions about this specification that require the help of a subject specialist,
you may find our Ask The Expert email service helpful.
www.edexcel.com/contactus
Pearson: helping people progress, everywhere
Our aim is to help everyone progress in their lives through education. We believe in
every kind of learning, for all kinds of people, wherever they are in the world. We’ve
been involved in education for over 150 years, and by working across 70 countries, in
100 languages, we have built an international reputation for our commitment to high
standards and raising achievement through innovation in education. Find out more about
how we can help you and your students at: www.pearson.com/uk
Summer 2012
Publications Code UG032646
All the material in this publication is copyright
© Pearson Education Ltd 2012
General Marking Guidance
•
All candidates must receive the same treatment. Examiners must mark the first
candidate in exactly the same way as they mark the last.
•
Mark schemes should be applied positively. Candidates must be rewarded for what
they have shown they can do rather than penalised for omissions.
•
Examiners should mark according to the mark scheme not according to their
perception of where the grade boundaries may lie.
•
There is no ceiling on achievement. All marks on the mark scheme should be used
appropriately.
•
All the marks on the mark scheme are designed to be awarded. Examiners should
always award full marks if deserved, i.e. if the answer matches the mark scheme.
Examiners should also be prepared to award zero marks if the candidate’s
response is not worthy of credit according to the mark scheme.
•
Where some judgement is required, mark schemes will provide the principles by
which marks will be awarded and exemplification may be limited.
•
When examiners are in doubt regarding the application of the mark scheme to a
candidate’s response, the team leader must be consulted.
•
Crossed out work should be marked UNLESS the candidate has replaced it with an
alternative response.
•
Types of mark
•
•
o
M marks: method marks
o
A marks: accuracy marks
o
B marks: unconditional accuracy marks (independent of M marks)
Abbreviations
o
cao – correct answer only
o
ft – follow through
o
isw – ignore subsequent working
o
SC - special case
o
oe – or equivalent (and appropriate)
o
dep – dependent
o
indep – independent
o
eeoo – each error or omission
No working
If no working is shown then correct answers normally score full marks
If no working is shown then incorrect (even though nearly correct) answers score
no marks.
•
With working
If there is a wrong answer indicated on the answer line always check the working
in the body of the script (and on any diagrams), and award any marks appropriate
from the mark scheme.
If it is clear from the working that the “correct” answer has been obtained from
incorrect working, award 0 marks.
Any case of suspected misread loses A (and B) marks on that part, but can gain
the M marks.
If working is crossed out and still legible, then it should be given any appropriate
marks, as long as it has not been replaced by alternative work.
If there is a choice of methods shown, then no marks should be awarded, unless
the answer on the answer line makes clear the method that has been used.
If there is no answer on the answer line then check the working for an obvious
answer.
•
Follow through marks
Follow through marks which involve a single stage calculation can be awarded
without working since you can check the answer yourself, but if ambiguous do not
award.
Follow through marks which involve more than one stage of calculation can only
be awarded on sight of the relevant working, even if it appears obvious that there
is only one way you could get the answer given.
•
Ignoring subsequent work
It is appropriate to ignore subsequent work when the additional work does not
change the answer in a way that is inappropriate for the question: eg. Incorrect
cancelling of a fraction that would otherwise be correct.
It is not appropriate to ignore subsequent work when the additional work
essentially makes the answer incorrect eg algebra.
Transcription errors occur when candidates present a correct answer in working,
and write it incorrectly on the answer line; mark the correct answer.
•
Probability
Probability answers must be given a fractions, percentages or decimals. If a
candidate gives a decimal equivalent to a probability, this should be written to at
least 2 decimal places (unless tenths).
Incorrect notation should lose the accuracy marks, but be awarded any implied
method marks.
If a probability answer is given on the answer line using both incorrect and correct
notation, award the marks.
If a probability fraction is given then cancelled incorrectly, ignore the incorrectly
cancelled answer.
•
Linear equations
Full marks can be gained if the solution alone is given on the answer line, or
otherwise unambiguously indicated in working (without contradiction elsewhere).
Where the correct solution only is shown substituted, but not identified as the
solution, the accuracy mark is lost but any method marks can be awarded.
•
Parts of questions
Unless allowed by the mark scheme, the marks allocated to one part of the
question CANNOT be awarded in another.
Question Working
Number
1
5 x £ 12.50 + 4 x 7.20
Notes
£ 91.30
A1
Question Working
Number
2
2x – 40 + 3x + 10 = 180
x = 42
Question Working
Number
3
5 + 7 = 2√x
(o.e.)
Mark
M1
2
Notes
Mark
M1
A1
2
Notes
OR
14√x -10√x = 49 – 25
x = 36, 62
Question Working
Number
4
145 + 180
Mark
2
Notes
360 -35
325° (o.e.)
Question Working
Number
5
(3 x 60)/24
7.5 secs
Question Working
Number
6
6x2 -4x -9x + 6 (allow one sign error)
6x2 – 13x + 6
2
M1
A1
OR
2
2
Mark
M1
A1
2
Notes
2
Mark
M1
A1
2
Notes
2
Mark
M1
A1
2
2
Question Working
Number
7
Any multiple of 18 seen (but nothing for 72,
162 or 270)
OR
Correct prime factors of 2 of 72, 162,and 270
18 (or 2 x 32)
Question Working
Number
8
Mark
B1
B1
2
Notes
3
−10
Question Working
Number
9
1.25 x 10-5 x 6000 OR 0.075
7.5 x 10-2
Question Working
Number
10
√(a – b) where a = 25 or b = 9
4, -4, ±4
Question Working
Number
11
Factor of 3
(3x - 2y)(3x + 2y)
OR
Notes
2
Mark
B1
B1
2
Notes
2
Mark
M1
A1
2
Notes
2
Mark
M1
A1
2
Notes
2
Mark
B1
M1
(9x - 6y)(3x + 2y)
OR (3x - 2y)(9x + 6y)
3(3x - 2y)(3x + 2y)
A1
3
3
Question
Number
12
Working
Notes
(a) 21
B1
(b) 5 + 9 + 13 + 17 + “21”
(attempt at summing 5 terms, at least 3
correct)
65
OR Using the formula for the sum of an
Arithmetic Progession:
n
S n = ∑ ai =
i =1
A1
2
Notes
Mark
M1 dep
12 km/litre
A1
Working
3
Notes
B1
1
(b) 46
B1
1
(c) 12
B1
1
Notes
Working
B1
24000
x
(b) 1500 = "
x =
24000
"
x
16
(o.e)
3
Mark
(a) 5
(a) A =
3
M1
612/(“68 x ¾”)
Question
Number
15
M1
M1
A1
Question Working
Number
13
68 x ¾ (= 51l)
14
1
n
{2a1 + (n − 1)d } , d = ai − ai −1
2
Correct subst.
65
Question
Number
Mark
3
Mark
1
M1
A1
2
3
Question
Number
Working
16
Notes
(a) 6
B1
(b) 360/30
M1
OR
(n – 2)*180 = (180 – 30)*n
1
(oe)
12 (final answer only, do NOT isw)
Question Working
Number
17
5x + 3x < 15 + 2
Mark
A1
2
Notes
(allow one error)
3
Mark
M1
x < 17/8 (= 2.125)
A1
2
A1
3
3
(allow equality sign for first two marks)
Question Working
Number
18
(17 2 − 82 )
Notes
Mark
M1
A1
15
OR
(sin ∠BAC =
8
⇒ ∠BAC = 28.072o )
17
tan”28.072” = 8/AB
15
8/”15”
M1
A1
A1 ft
3
3
Question Working
Number
19
Question
Number
20
Question
Number
20
Question
Number
21
Notes
a=1
B1
b = -2
B1
λ=3
B1
Working
Notes
(a) 306°
B1
7
× "306"
17
M1
126° (accept answer on diagram)
A1
Working
(b)
cyclic (quadrilateral)
Working
(a) 14/100 x 15 000
(b)
3
B1
3
Mark
3
Notes
Mark
1
Notes
4
Mark
M1
2100
A1
16
× x = "2100" (o.e.)
100
M1
13125 (integer value only)
Mark
2
A1
2
4
Question Working
Number
22
1
Notes
=
24
M1
k
60 2
A1
k
= 150
y=
"150"
10 2
y = 1.5,
M1 dep
3
2
A1
Question Working
Number
23
16/0.25 OR 64 OR 0.25/16 OR 1/64
(o.e eg
16000/250)
3
Mark
0.25 /16 OR
3
4
Notes
4
Mark
B1
16 / 0.25 (o.e) used
in expression involving rS
OR
0.25/16 or 16/0.25 (o.e) used in
expression
involving rS3
rS = 24 × 3
6 cm
0.25
(o.e)
16
B1
M1
A1
4
4
Question
Number
24
Question
Number
24
Working
(a) 93
B1
Working
M1
12t2
A1
1
A1
Mark
3
4
12t2-2t – 2
Working
(a) construction; accuracy
(line must intersect AB and DC for A1)
(b) construction; accuracy
(line from D and must intersect AB for
A1)
(c) shaded and labelled
Question
Number
26
Mark
Notes
(b) tn →tn-1
-2t - 2
NB: Answer is
Question
Number
25
Notes
Working
Notes
Mark
M1, A1
2
M1, A1
2
B1
1
Notes
B1, B1,
B1
(a)
5 3 4
, , (or decimal equivalent to 2 dp)
8 7 7
(b)
3 2 5
4
× + " "× " "
8 7 8
7
M1
13
(o.e.)
28
A1
5
Mark
3
2
5
Question Working
Number
27
16 seen
342 − "16"2
30
π “30”2
2830 cm2
Question Working
Number
28
2x + 3(2x - 1) = 3x.(2x - 1)
Notes
Mark
B1
M1
A1
M1 dep
A1
5
Notes
5
Mark
M1
(removing denominators)
6x2 - 11x + 3 (= 0)
Attempt to factorise c’s trinomial
quadratic
x = 1/3
x = 3/2
A1
M1
A1
A1
5
5
Question
Number
29
Working
Notes
(a) 0 < x ≤ 2
B1
(b) using a consistent value:
M1
Mark
1
mid class, lower class boundary, upper
class boundary
complete and correct method for finding
mean
i.e.
1× 35 + 3 × 20 + 5 ×13 + 7 × 8 + 9 × 4
80
3.15
(c) 2 +
5
× 2 (o.e.)
20
M1 dep
A1
3
M1
(accept 5.5/20)
2.5 (accept 2.55)
Question
Number
30
Working
(a) one term correctly differentiated
3x2 - 2x
(b) “3x2 - 2x” = 5
A1
2
Notes
6
Mark
M1
A1
2
M1
3x2 - 2x - 5 ( = 0)
A1
Attempt to factorise c’s quadratic
M1
x = -1
x = 5/3
A1
A1
5
7
Further copies of this publication are available from
Edexcel Publications, Adamsway, Mansfield, Notts, NG18 4FN
Telephone 01623 467467
Fax 01623 450481
Email [email protected]
Order Code UG032646 Summer 2012
For more information on Edexcel qualifications, please visit our website
www.edexcel.com
Pearson Education Limited. Registered company number 872828
with its registered office at Edinburgh Gate, Harlow, Essex CM20 2JE