Mathematics A · June 2013 · Mark scheme · Paper 2F
Edexcel International GCSE Mathematics A mark scheme for Paper 2F, June 2013 — 4MA0/2F, file 4MA0_2F_msc_20130822.pdf.
Text of this paper
Mark Scheme (Results)
Summer 2013
International GCSE Mathematics
(4MA0) Paper 2F
Level 1/Level 2 Certificate in Mathematics
(KMA0) Paper 2F
Edexcel and BTEC Qualifications
Edexcel and BTEC qualifications come from Pearson, the world’s leading
learning company. We provide a wide range of qualifications including
academic, vocational, occupational and specific programmes for
employers. For further information, please visit our website at
www.edexcel.com.
Our website subject pages hold useful resources, support material and live
feeds from our subject advisors giving you access to a portal of
information. If you have any subject specific questions about this
specification that require the help of a subject specialist, you may find our
Ask The Expert email service helpful.
www.edexcel.com/contactus
Pearson: helping people progress, everywhere
Our aim is to help everyone progress in their lives through education. We
believe in every kind of learning, for all kinds of people, wherever they are
in the world. We’ve been involved in education for over 150 years, and by
working across 70 countries, in 100 languages, we have built an
international reputation for our commitment to high standards and raising
achievement through innovation in education. Find out more about how
we can help you and your students at: www.pearson.com/uk
Summer 2013
Publications Code UG037226
All the material in this publication is copyright
© Pearson Education Ltd 2013
General Marking Guidance
All candidates must receive the same treatment. Examiners must
mark the first candidate in exactly the same way as they mark the
last.
Mark schemes should be applied positively. Candidates must be
rewarded for what they have shown they can do rather than
penalised for omissions.
Examiners should mark according to the mark scheme not
according to their perception of where the grade boundaries may
lie.
There is no ceiling on achievement. All marks on the mark scheme
should be used appropriately.
All the marks on the mark scheme are designed to be awarded.
Examiners should always award full marks if deserved, i.e. if the
answer matches the mark scheme.
Examiners should also be prepared to award zero marks if the
candidate’s response is not worthy of credit according to the mark
scheme.
Where some judgement is required, mark schemes will provide the
principles by which marks will be awarded and exemplification may
be limited.
When examiners are in doubt regarding the application of the mark
scheme to a candidate’s response, the team leader must be
consulted.
Crossed out work should be marked UNLESS the candidate has
replaced it with an alternative response.
Types of mark
o M marks: method marks
o A marks: accuracy marks
o B marks: unconditional accuracy marks (independent of M
marks)
Abbreviations
o awrt – answers which round to
o cao – correct answer only
o ft – follow through
o isw – ignore subsequent working
o SC - special case
o oe – or equivalent (and appropriate)
o dep – dependent
o indep – independent
o eeoo – each error or omission
No working
If no working is shown then correct answers normally score full
marks
If no working is shown then incorrect (even though nearly correct)
answers score no marks.
With working
If there is a wrong answer indicated on the answer line always
check the working in the body of the script (and on any diagrams),
and award any marks appropriate from the mark scheme.
If it is clear from the working that the “correct” answer has been
obtained from incorrect working, award 0 marks.
Any case of suspected misread loses A (and B) marks on that part,
but can gain the M marks.
If working is crossed out and still legible, then it should be given
any appropriate marks, as long as it has not been replaced by
alternative work.
If there is a choice of methods shown, then no marks should be
awarded, unless the answer on the answer line makes clear the
method that has been used.
If there is no answer on the answer line then check the working for
an obvious answer.
Ignoring subsequent work
It is appropriate to ignore subsequent work when the additional
work does not change the answer in a way that is inappropriate for
the question: eg. Incorrect cancelling of a fraction that would
otherwise be correct.
It is not appropriate to ignore subsequent work when the additional
work essentially makes the answer incorrect eg algebra.
Transcription errors occur when candidates present a correct
answer in working, and write it incorrectly on the answer line; mark
the correct answer.
Parts of questions
Unless allowed by the mark scheme, the marks allocated to one
part of the question CANNOT be awarded in another.
Apart from Questions 10bii and 18 (where the mark scheme states otherwise) the correct answer, unless clearly obtained by an
incorrect method, should be taken to imply a correct method.
Question
Working
Answer
Mark
Notes
Number
1 (a) (i)
30
1
B1
(a) (ii)
1 – a(i)
70
1
B1 ft ft if 0 < ans to a(i)< 100
(b)
6 petals shaded
1
B1
Total 3 marks
2 (a)
(b) (i)
5.7
Arrow at 6 marks beyond 3.7
1
1
(ii)
(iii)
(c)
4
7/10
3.765
1
1
1
Label A at 1
Label B at 1cm to 2.5 cm
from 0
Label C at 0.5
1
1
B1
B1
1
B1
3 (i)
(ii)
(iii)
B1
accept trailing zeros (eg 5.70)
B1
accept any mark (eg arrow, cross...etc) in correct
position
B1
accept trailing zeros
B1
accept 1/10, tenth(s), (0).7, 0.70
B1
accept trailing zeros (eg 3.7650)
Total 5 marks
Total 3 marks
4
(a)
(b) (i)
(b)(ii)
(b)(iii)
(c)
Thursday
8
40
26
1
1
1
1
5/12
2
10/24
B1
B1
B1 cao
B1 cao
M1
A1
Total 6 marks
5
(a)
(b)
(c) (i)
(c) (ii)
5.8 to 6.0 inc
26° to 30° inc
radius
segment
1
1
1
1
B1
B1
B1
B1
Total 4 marks
6 (a)
(b)
(c)
1
6 x 5 +1
31
2
12
2
(61 – 1) ÷ 5
B1
M1
A1
M1
A1
brackets not necessary
Total 5 marks
7
(a)
(b)
Cardiff
1
−8
2
−3 −5 or −3 + −5
B1
M1
A1
Total 3 marks
8 (a)
25 ÷ 3.95 (=6.3 )
M1
A1 cao
M1 25 – total cost of the plants
A1 with correct money notation. Allow £1.30p
Total 4 marks
6
2
1.30
2
9 (a)
(b)
correct lines marked
correct angle marked
1
1
B1
B1
(c)
(d)
(e)
(−3,1)
y=1
12
1
1
B1
B1
B2
cm2
3
(b)
25 – “6” x 3.95
Marked internally at (1,4) or internally at (1,1)
or externally at (1,3)
B2 for 11≤ area ≤13
B1 for 9≤ area <11 or 13< area ≤15
B1indep accept sq cms etc
Total 7 marks
10 (a) (i)
(ii)
(b) (i)
(ii)
3t
5ab
1
1
1.5 oe
2
8 x = 9 +3
5y = 14 or 7y - 2y = 14 or 5y =
8+6
or 5y - 14 = 0
3
B1
B1
accept t3
any combination but do NOT accept multiplication
signs
or 9+3 ÷8 with or without brackets
M1
A1
M2
for correct rearrangement with y terms on one
side and numbers on the other AND correct collection of
terms on at least one side or for correct collection of to 2
terms
M1
for correct rearrangement with y terms on one
side and numbers on the other eg 7y – 2y = 8 +6
or
correct collection and simplification of either numbers or
y terms eg. 5y - 6 = 8 or 5y = a or by = 14
(c)
11
(a)
2
2.8
x – 6 x +9 x – 54
x 2 +3 x – 54
2
630
2
600
2
71
2
450 x 1.4(0)
(b)
840 ÷ 1.4(0)
(c)
100 ÷ 1.4(0) (=71.4...)
A1 2.8 oe dependent on at least one M1
M1
4 correct terms ignoring signs
or for 3 correct terms out of 4 terms with signs
A1
Total 9 marks
M1
A1
M1
A1
M1
A1
or 1 ÷ 1.4(0)
awrt 71
Total 6 marks
12
0.8 x 0.3 x ”depth” = 108÷1000
(“depth”=) 0.108÷0.24 oe
0.45
3
M1
M1
A1
M1 for 0.8 x 0.3 or 0.24 or 108 ÷1000
Total 3 marks
13
(a)
80 x 195 ÷ 30 oe
or 6 x 80 + 40 oe
(b)
120/800 x 360 oe
M2
520
3
54
2
M1 for 195 ÷ 30 or 30 ÷ 195
or 80 ÷ 30 or 30 ÷ 80
A1
M1
A1
Total 5 marks
14
(a)
Shape in correct
position
Rotation
90° or quarter turn
anticlockwise
(0,0) or O or origin
(b)
2
B2
3
B1
B1
B1
B1 for reflection in line x =k where (k≤2) tolerance
of ½ sq
accept 90° or – 270°
Answers that give multiple transformations score
zero
Total 5 marks
15
3/5 x 15 or 15 ÷ 5 × 3
9
2
M1
A1
M1 for 3/5 or 15 ÷ 5 × 3
Total 2 marks
16
(a)
(b)
1 – (0.15 + 0.4 + 0.35)
0.1
2
0.55
2
0.15 + 0.4
M1
A1
M1
A1
Total 4 marks
17
7800 ÷ 9.75 or 7800 ÷ 585 x
60
800
3
M2
A1
M1 for 7800 ÷ 9.45 or 7800 ÷ 585 or 13.3(
Total 3 marks
18
(a)
21/24 – 20/24
B2
2
for both fractions written correctly with a common
denominator, followed , if necessary, by cancelling to
1/24
B1
(b)
5/8 x 12/7 or
15/24 ÷ 14/24
2
60/56
19
A1
60/56 from the x or 15/14 from the ÷
Total 4 marks
10 x 24, 30 x 20, 50 x 9,70 x 12, 90 x
15
10 x 24 + 30 x 20 + 50 x 9 + 70 x 12 +
90 x 15
240 + 600 + 450 + 840 +1350
for 1 correct fraction with denominator of a multiple
of 24
M1 leaving first fraction unchanged, changing ÷ to x
and inverting the second fraction
or
converting each fraction with a common denominator
of 24 oe with ÷ sign
M1
at least 4 products fx x used consistently within
interval (inc end points)
M1(dep) for fx with use of at least 4 correct ½ way
values
3480
3
A1
Total 3 marks
20
(a)
(b)
( 4.5 , 3 )
2
7.28
4
Identifies 2 & 7 as sides
“2”2 + “7”2
√(“2”2 + “7”2)
B1 B1
B1
M1
“2” & “7” must be identified as sides
M1 dep
A1
awrt 7.28
Total 6 marks
21
Factor tree or repeated division
with 2 or more correct prime
factors
(2, 2, 3, 17)
M1
condone 1s factors must multiply to
M1
condone 1s
204
Fully correct factor tree or
repeated division or 2, 2, 3, 17
2 x 2 x 3 x 17
3
A1
Total 3 marks
22.
22 x 25000 (=550000)
“550000” ÷100000
5.5
3
M1
M1
A1
or 25000 cm = 0.25km or 22 ÷100000
or 22 x 0.25 or “0.00022” × 25000
Total 3 marks
23. (a)
(b)
−6/3 ≤ x < 9/3
−2 ≤ x < 3
−2, −1 , 0, 1, 2
2
2
M1
A1
B2
M1 for −6/3 ≤ x or x < 9/3
SC B1 for −2 < x < 3
B1 for five correct values and one wrong value
or four correct values with no wrong value
Total 4 marks
TOTAL FOR PAPER: 100
Further copies of this publication are available from
Edexcel Publications, Adamsway, Mansfield, Notts, NG18 4FN
Telephone 01623 467467
Fax 01623 450481
Email [email protected]
Order Code UG037226 Summer 2013
For more information on Edexcel qualifications, please visit our website
www.edexcel.com
Pearson Education Limited. Registered company number 872828
with its registered office at Edinburgh Gate, Harlow, Essex CM20 2JE