Maths (9709) · May/June 2024 · Mark scheme 53

Cambridge Maths (9709) mark scheme for paper 53, May/June 2024 — 9709/53/M/J/24, file 9709_s24_ms_53.pdf.

Advertisement
Loading the paper…
Text of this paper

www.dynamicpapers.com

Cambridge International AS & A Level
MATHEMATICS

9709/53

Paper 5 Probability & Statistics 1

May/June 2024

MARK SCHEME
Maximum Mark: 50

Published

This mark scheme is published as an aid to teachers and candidates, to indicate the requirements of the
examination. It shows the basis on which Examiners were instructed to award marks. It does not indicate the
details of the discussions that took place at an Examiners’ meeting before marking began, which would have
considered the acceptability of alternative answers.
Mark schemes should be read in conjunction with the question paper and the Principal Examiner Report for
Teachers.
Cambridge International will not enter into discussions about these mark schemes.
Cambridge International is publishing the mark schemes for the May/June 2024 series for most
Cambridge IGCSE, Cambridge International A and AS Level and Cambridge Pre-U components, and some
Cambridge O Level components.

This document consists of 17 printed pages.
© Cambridge University Press & Assessment 2024

[Turn over

9709/53

Cambridge International AS & A Level – Mark Scheme
PUBLISHED
Generic Marking Principles

May/June 2024
www.dynamicpapers.com

These general marking principles must be applied by all examiners when marking candidate answers. They should be applied alongside the specific content of the
mark scheme or generic level descriptions for a question. Each question paper and mark scheme will also comply with these marking principles.
GENERIC MARKING PRINCIPLE 1:
Marks must be awarded in line with:


the specific content of the mark scheme or the generic level descriptors for the question
the specific skills defined in the mark scheme or in the generic level descriptors for the question
the standard of response required by a candidate as exemplified by the standardisation scripts.

GENERIC MARKING PRINCIPLE 2:
Marks awarded are always whole marks (not half marks, or other fractions).
GENERIC MARKING PRINCIPLE 3:
Marks must be awarded positively:




marks are awarded for correct/valid answers, as defined in the mark scheme. However, credit is given for valid answers which go beyond the scope of the
syllabus and mark scheme, referring to your Team Leader as appropriate
marks are awarded when candidates clearly demonstrate what they know and can do
marks are not deducted for errors
marks are not deducted for omissions
answers should only be judged on the quality of spelling, punctuation and grammar when these features are specifically assessed by the question as
indicated by the mark scheme. The meaning, however, should be unambiguous.

GENERIC MARKING PRINCIPLE 4:
Rules must be applied consistently, e.g. in situations where candidates have not followed instructions or in the application of generic level descriptors.
GENERIC MARKING PRINCIPLE 5:
Marks should be awarded using the full range of marks defined in the mark scheme for the question (however; the use of the full mark range may be limited
according to the quality of the candidate responses seen).
GENERIC MARKING PRINCIPLE 6:
Marks awarded are based solely on the requirements as defined in the mark scheme. Marks should not be awarded with grade thresholds or grade descriptors in
mind.

© Cambridge University Press & Assessment 2024

Page 2 of 17

9709/53

Cambridge International AS & A Level – Mark Scheme
PUBLISHED

May/June 2024
www.dynamicpapers.com

Mathematics-Specific Marking Principles
1

Unless a particular method has been specified in the question, full marks may be awarded for any correct method. However, if a calculation is required
then no marks will be awarded for a scale drawing.

2

Unless specified in the question, non-integer answers may be given as fractions, decimals or in standard form. Ignore superfluous zeros, provided that the
degree of accuracy is not affected.

3

Allow alternative conventions for notation if used consistently throughout the paper, e.g. commas being used as decimal points.

4

Unless otherwise indicated, marks once gained cannot subsequently be lost, e.g. wrong working following a correct form of answer is ignored (isw).

5

Where a candidate has misread a number or sign in the question and used that value consistently throughout, provided that number does not alter the
difficulty or the method required, award all marks earned and deduct just 1 A or B mark for the misread.

6

Recovery within working is allowed, e.g. a notation error in the working where the following line of working makes the candidate’s intent clear.

© Cambridge University Press & Assessment 2024

Page 3 of 17

9709/53

Cambridge International AS & A Level – Mark Scheme
PUBLISHED
Mark Scheme Notes

May/June 2024
www.dynamicpapers.com

The following notes are intended to aid interpretation of mark schemes in general, but individual mark schemes may include marks awarded for specific reasons
outside the scope of these notes.
Types of mark
M

Method mark, awarded for a valid method applied to the problem. Method marks are not lost for numerical errors, algebraic slips or errors in units.
However, it is not usually sufficient for a candidate just to indicate an intention of using some method or just to quote a formula; the formula or idea
must be applied to the specific problem in hand, e.g. by substituting the relevant quantities into the formula. Correct application of a formula
without the formula being quoted obviously earns the M mark and in some cases an M mark can be implied from a correct answer.

A

Accuracy mark, awarded for a correct answer or intermediate step correctly obtained. Accuracy marks cannot be given unless the associated method
mark is earned (or implied).

B

Mark for a correct result or statement independent of method marks.

DM or DB

FT
•
•
•
•
•

When a part of a question has two or more ‘method’ steps, the M marks are generally independent unless the scheme specifically says otherwise;
and similarly, when there are several B marks allocated. The notation DM or DB is used to indicate that a particular M or B mark is dependent on
an earlier M or B (asterisked) mark in the scheme. When two or more steps are run together by the candidate, the earlier marks are implied and full
credit is given.
Implies that the A or B mark indicated is allowed for work correctly following on from previously incorrect results. Otherwise, A or B marks are
given for correct work only.

A or B marks are given for correct work only (not for results obtained from incorrect working) unless follow through is allowed (see abbreviation FT above).
For a numerical answer, allow the A or B mark if the answer is correct to 3 significant figures or would be correct to 3 significant figures if rounded (1
decimal place for angles in degrees).
The total number of marks available for each question is shown at the bottom of the Marks column.
Wrong or missing units in an answer should not result in loss of marks unless the guidance indicates otherwise.
Square brackets [ ] around text or numbers show extra information not needed for the mark to be awarded.

© Cambridge University Press & Assessment 2024

Page 4 of 17

9709/53

Cambridge International AS & A Level – Mark Scheme
PUBLISHED

May/June 2024
www.dynamicpapers.com

Abbreviations
AEF/OE

Any Equivalent Form (of answer is equally acceptable) / Or Equivalent

AG

Answer Given on the question paper (so extra checking is needed to ensure that the detailed working leading to the result is valid)

CAO

Correct Answer Only (emphasising that no ‘follow through’ from a previous error is allowed)

CWO

Correct Working Only

ISW

Ignore Subsequent Working

SOI

Seen Or Implied

SC

Special Case (detailing the mark to be given for a specific wrong solution, or a case where some standard marking practice is to be varied in the
light of a particular circumstance)

WWW

Without Wrong Working

AWRT

Answer Which Rounds To

© Cambridge University Press & Assessment 2024

Page 5 of 17

9709/53

Cambridge International AS & A Level – Mark Scheme
PUBLISHED

Question
1(a)

Answer

Marks

May/June 2024
www.dynamicpapers.com
Guidance

x

2

3

4

5

6

P(X = x)

1
36

4
36

10
36

12
36

9
36

B1 Table with correct X values and at least one correct probability
associated with the correct X value.
Values need not be in order, lines may not be drawn, may be
vertical, X and P(X) may be omitted.
Condone any additional X values if probability stated as 0.

1
36

1
9

5
18

1
3

1
4

B1 Three other probabilities associated with correct x values, need not
be in table, accept unsimplified.
B1 Five correct probabilities linked with correct outcomes, may not be
in table.
Decimals correct to at least 3sf.
SC B1 for five probabilities summing to 1 placed in a probability
distribution table with the correct x values.

Decimal equivalent 3sf:
0.0278, 0.111, 0.278, 0.333, 0.25

3

© Cambridge University Press & Assessment 2024

Page 6 of 17

9709/53

Cambridge International AS & A Level – Mark Scheme
PUBLISHED

Question
1(b)

Answer
E(X) =

Marks

1  2  4  3  10  4  12  5  9  6

36

[=

Guidance

M1 Accept unsimplified expression or sum of fractions seen. May be
calculated in variance.
FT their table with five probabilities summing to
0.999 ⩽ total ⩽ 1 (0 < p < 1).

2 12 40 60 54  14

 



or 4.67 

36 36 36 36 36  3

1  22  4  32  10  42  12  52  9  62  14 
Var(X) =
 
36
 3

May/June 2024
www.dynamicpapers.com

M1 Appropriate variance formula using their (E(X))2 value.
FT their table with 4 or more probabilities.
(0 < p < 1) which need not sum to 1.
Note: If table is correct, then
2
206
 824
  196
 14  
or
or
22.89

or
21.78
or



   implies M1.
9
 36
  9
 3  

2

A1

824 196
10

 22.89  21.78] =
9
36
9

1
1 , 1.111 , 1.1
9

3
1(c)

M1

10 9

P(X even | X > 3) = 36 36
31
36

=

their P  4   P  5   P  6 

, all probabilities (0 < p < 1).

If sample space seen in any part of the question, then M1
A1 0.613

19
31

2

© Cambridge University Press & Assessment 2024

their P  4   their P  6 

Page 7 of 17

their 19
.
their 31

9709/53

Cambridge International AS & A Level – Mark Scheme
PUBLISHED

Question
2(a)

Answer

Marks

May/June 2024
www.dynamicpapers.com
Guidance

1.93  1.64 

PZ 
  P(Z > 1.16)
0.25 

M1 Using ± standardisation formula with 1.93, 1.64 and 0.25
substituted, not  2 , not  , no continuity correction.

1 – 0.8770

M1 Appropriate area Φ resulting from a standardisation, from final
process, must be probability.
Note: the appropriate probability answer implies this M1.

0.123

A1 0.123 ⩽ p < 0.12303
If M0 M0, SC B1 if no standardisation shown.
3

2(b)

1.56  


1.86  

B1 −0.441 < z1 < −0.439 or
0.439 < z1 < 0.441 seen.

 0.44

B1 z2 = 0.674 or z2 = – 0.674 seen, CAO, critical value.

 0.674

M1 Use of the ±standardisation formula once with μ, σ equating to a zvalue (not 0.33, 0.67. 0.25, 0.75, 0.6293, 0.5987, 0.7486, 0.7734,
(1 – 0.44), (1 – 0.674)). Condone continuity correct ± 0.005, not
 2,  .

Solve, obtaining values for  and σ

M1 Solve two equations in μ and σ using the elimination method,
substitution method or other appropriate approach to obtain values
for both μ and σ.

  1.68,   0.269

A1 AWRT   1.68,   0.269.
If one or both of the M marks have not been awarded, SC B1 for
both correct.
5

© Cambridge University Press & Assessment 2024

Page 8 of 17

9709/53

Cambridge International AS & A Level – Mark Scheme
PUBLISHED

Question
3(a)

Answer
Box A

Marks

May/June 2024
www.dynamicpapers.com
Guidance

B1 Correct structure and probabilities for Box A branches.

Box B

B1 Completely correct structure and one correct probability for a Box
B branch including label for G or Y.
B1 Completely correct structure and second correct probability on a
Box B branch including label G or Y.
B1 Completely correct structure and remaining two probabilities
correct on Box B branches, including labels for G or Y.
SC B1 if correct shape diagram but only four correct algebraic
probs for GG, GY, YG and YY.

4
3(b)

P(same colour) =

6
5
3 1 x

 
9 5 x 9 5 x

M1 P(GG) + P(YY) =
3
6
6
 5  3
 1 x 
 or   their 
   or   their 

9
9
9
5 x 9
5 x

6
5
3 1 x 8
and arrange as a linear equation

 

9 5  x 9 5  x 15

M1

15  x  11  24  x  5  OE
Accept sum of their products equated to
a linear equation.

Solve: x  5

A1
3

© Cambridge University Press & Assessment 2024

Page 9 of 17

8
and rearranged to form
15

9709/53

Cambridge International AS & A Level – Mark Scheme
PUBLISHED

Question

Answer

4(a)

Penguins

8

Marks

5

3

6

Guidance

B1 Correct stem, ignore extra values (not in reverse, not split).
If a split stem-and-leaf plot is used (i.e. stem values are repeated),
the remaining B marks are available.

Dolphins
9

May/June 2024
www.dynamicpapers.com

5

5

4

2

4

1 3 8 9

9

9

8

6

0

5

0 1 4 6

6

8

6

1

6

0 1 4

2

7

1

B1 Correct Penguins labelled on left, leaves in order from right to left
and lined up vertically (less than halfway to next column), no
commas or other punctuation.
B1 Correct Dolphins labelled on same diagram, leaves in order and
lined up vertically (less than halfway to next column), no commas
or other punctuation.
If the correct data for Penguins & Dolphins is transposed, treat as a
single error in Penguins and condone in Dolphins.

Key: 2 | 4 | 1 means 42 seconds for Penguins and 41 seconds for
Dolphins

B1 Correct key for their diagram, need both clubs labelled and ‘sec’ or
‘s’ stated at least once here, or in leaf headings or title.
If two separate diagrams drawn: SC B1 if both keys meet these
criteria.
4

© Cambridge University Press & Assessment 2024

Page 10 of 17

9709/53

Cambridge International AS & A Level – Mark Scheme
PUBLISHED

Question

Answer

Marks

May/June 2024
www.dynamicpapers.com
Guidance

4(b)

For Dolphins, median is 51

B1 Plotted on box.

LQ = 48, UQ = 60

B1 Plotted on box.

Correct end points for whiskers and diagram labelled Dolphins

B1 Correct end points of whiskers (36 and 71).
Whiskers not through box, not drawn at corners of boxes, diagram
labelled.
3

4(c)

B1 Reason given in context.
Can be reference to either the central tendency or spread.

Dolphins have more consistent times than Penguins
or
Penguins are faster (have faster times) than Dolphins

1

© Cambridge University Press & Assessment 2024

Page 11 of 17

9709/53
Question
5(a)

May/June 2024
www.dynamicpapers.com

Cambridge International AS & A Level – Mark Scheme
PUBLISHED
Answer

Marks

Guidance

B1 AWRT

 0.35 4  0.65   0.00975

1
5(b)

 0.35   0.65
3

2

M1

4

= 0.0725

 0.35   0.65
3

2

 k , where k is an integer.
1 ⩽ k ⩽ 5 no + or 

A1
2

5(c)

Method 1
[1 – P(5, 6, 7) =]
1 – (7C5 0.655 0.352 + 7C6 0.6560.351+ 0.657)
[= 1 – (0.29848 + 0.18478 + 0.049022)]

M1 One term 7Cx  p  x 1  p 7  x , 0  p  1, 0  x  7.

= 0.468

B1 AWRT

A1 Correct expression, accept unsimplified, no terms omitted leading
to final answer

Method 2
[P(0, 1, 2, 3, 4) =]
0.357 +7C1 0.651 0.356 +7C2 0.652 0.355 +7C3 0.653 0.354 +7C4 0.654
0.353
[0.00064 + 0.00836 + 0.04660 + 0.14424 + 0.26787]

(M1) One term 7Cx  p  x 1  p 7  x , 0  p  1, 0  x  7.

(A1) Correct expression, accept unsimplified, no terms omitted leading
to final answer.
= 0.468

(B1) AWRT
3

© Cambridge University Press & Assessment 2024

Page 12 of 17

9709/53

Cambridge International AS & A Level – Mark Scheme
PUBLISHED

Question
5(d)

Answer

Marks

May/June 2024
www.dynamicpapers.com
Guidance

[Mean =] 84 0.65  54.6
[Var =] 84 0.65  0.35  19.11

B1 54.6 and 19.11 seen, allow unsimplified. May be seen in the
standardisation formula
7 39
([σ = ] 4.371 or
implies correct variance).
10
Incorrect notation is penalised, but condone use of values in
standardisation formula.

50.5  54.6 

P(X > 50) = P  Z 

19.11 

M1 Substituting their µ and their positive σ into the ± standardising
formula (any number), not their σ2, or their  .
M1 Use continuity correction 49.5 or 50.5 in their standardisation
formula.
4.1
4.1
or 
seen gains M2 BOD.
Note:
4.371
19.11

P ( Z   0.9379) = Φ  0.9379 

M1 Appropriate area Φ, from final process, must be a probability.

0.826

A1 0.8255 < p ≤ 0.826
5

© Cambridge University Press & Assessment 2024

Page 13 of 17

9709/53
Question
6(a)

May/June 2024
www.dynamicpapers.com

Cambridge International AS & A Level – Mark Scheme
PUBLISHED
Answer

Marks

Guidance

B1

 9! 
 2!3!   30240

1
6(b)

Method 1: Number of arrangements with E at each end – Number of arrangements with E at each end and the three Rs together
B1

7!
 5! 
3!

M1

720

7!
 e , 7P4 – e, e a positive integer.
3!
f 

5!
, f > 120, r = 1, 2
r!

A1 If no marks scored SC B1 for 840 – 120 = 720.

Method 2: Number of arrangements with E at each end and no Rs together + No of arrangements with E at each end and two Rs together
5

C3 × 4! + 4C1 × 5!
5
P3
 4! + 5P2 4!
or
3!

(B1)

5

P3
 4! , 4C1 × 5! or 5P2 4! seen.
3!

(M1) a × 4! + b × 5! where a and b are integers between 1 and 10
inclusive,
or c × 4! + d × 4! where c and d are integers between 1 and 20
inclusive.

240 + 480 = 720

(A1)
3

© Cambridge University Press & Assessment 2024

One of 5C3 × 4!,

Page 14 of 17

9709/53
Question
6(c)

May/June 2024
www.dynamicpapers.com

Cambridge International AS & A Level – Mark Scheme
PUBLISHED
Answer

Marks

Guidance

Method 1
Group of 5

B1 Correct no of ways for two correct identified scenarios other than
three Rs two Es.

3 Rs 2 Es
3 Rs 1 E = 2C1 × 4C1
3 Rs 0 Es = 4C2

=1
=8
=6

Group of 4
3 Rs 1 E = 2C1
3 Rs 0 Es = 4C1

=2
=4

[Total =] 21

M1 No of ways for five correct identified scenarios added or correct.

[Number of ways of splitting into the two groups =] 9C5 (= 126)
seen as a denominator

M1 Accept evaluated, accept 9C4.

Probability =

A1

21 1
 (0.167)
126 6

© Cambridge University Press & Assessment 2024

Page 15 of 17

9709/53
Question
6(c)

May/June 2024
www.dynamicpapers.com

Cambridge International AS & A Level – Mark Scheme
PUBLISHED
Answer

Marks

Guidance

Method 2
3Rs in Group of 5 = 6C2

= 15

3Rs in Group of 4 = 6C1

=6

(B1) One correct case evaluated accurately and linked with correct
scenario.

[Total =] 21

(M1) No of ways for two correct scenarios added or correct.

[Number of ways of splitting into the two groups =] 9C5 (= 126)
seen as a denominator

(M1) Accept evaluated, accept 9C4.

Probability =

(A1)

21 1
 (0.167)
126 6

Method 3: Considering the possible positions of R within the groups
3Rs in Group of 5
5 4 3
15
  =
9 8 7 126

(B1) For one correct product unsimplified and linked with correct
scenario.
(M1) For second correct product.

3Rs in Group of 4
4 3 2
6
  
9 8 7 126
(M1) For adding probabilities of two correct scenarios or correct.

15
6
+
126 126

Probability =

(A1)

21 1
 (0.167)
126 6

© Cambridge University Press & Assessment 2024

Page 16 of 17

9709/53

Cambridge International AS & A Level – Mark Scheme
PUBLISHED

Question
6(c)

Answer

Marks

May/June 2024
www.dynamicpapers.com
Guidance

Method 4: Probability method
(B1) Two correct probabilities linked with correct scenarios, accept
unsimplified.

Group of 5
2Es

3 2 1 2 1 5!
1
    

9 8 7 6 5 3!2! 126

1E

4 3 2 1 2 5!
8
     
9 8 7 6 5 3! 126

0E

3 2 1 4 3 5!
6
    

9 8 7 6 5 3!2! 126

(M1) Four probabilities with denominators including a factor of
9  8  7  6  n, where n is 1 or 5.

Group of 4
3 2 1 6 4!
6
    
9 8 7 6 3! 126
1 8  6  6
126

Probability =

(M1) Probabilities of four correct scenarios added or correct.

(A1)

21 1
 (0.167)
126 6

4

© Cambridge University Press & Assessment 2024

Page 17 of 17