Maths (9709) · May/June 2023 · Mark scheme 52
Cambridge Maths (9709) mark scheme for paper 52, May/June 2023 — 9709/52/M/J/23, file 9709_s23_ms_52.pdf.
Text of this paper
www.dynamicpapers.com
Cambridge International AS & A Level
MATHEMATICS
9709/52
Paper 5 Probability & Statistics 1
May/June 2023
MARK SCHEME
Maximum Mark: 50
Published
This mark scheme is published as an aid to teachers and candidates, to indicate the requirements of the
examination. It shows the basis on which Examiners were instructed to award marks. It does not indicate the
details of the discussions that took place at an Examiners’ meeting before marking began, which would have
considered the acceptability of alternative answers.
Mark schemes should be read in conjunction with the question paper and the Principal Examiner Report for
Teachers.
Cambridge International will not enter into discussions about these mark schemes.
Cambridge International is publishing the mark schemes for the May/June 2023 series for most
Cambridge IGCSE, Cambridge International A and AS Level and Cambridge Pre-U components, and some
Cambridge O Level components.
This document consists of 18 printed pages.
© UCLES 2023
[Turn over
9709/52
Cambridge International AS & A Level – Mark Scheme
PUBLISHED
Generic Marking Principles
May/June 2023
www.dynamicpapers.com
These general marking principles must be applied by all examiners when marking candidate answers. They should be applied alongside the specific content of the
mark scheme or generic level descriptors for a question. Each question paper and mark scheme will also comply with these marking principles.
GENERIC MARKING PRINCIPLE 1:
Marks must be awarded in line with:
the specific content of the mark scheme or the generic level descriptors for the question
the specific skills defined in the mark scheme or in the generic level descriptors for the question
the standard of response required by a candidate as exemplified by the standardisation scripts.
GENERIC MARKING PRINCIPLE 2:
Marks awarded are always whole marks (not half marks, or other fractions).
GENERIC MARKING PRINCIPLE 3:
Marks must be awarded positively:
marks are awarded for correct/valid answers, as defined in the mark scheme. However, credit is given for valid answers which go beyond the scope of the
syllabus and mark scheme, referring to your Team Leader as appropriate
marks are awarded when candidates clearly demonstrate what they know and can do
marks are not deducted for errors
marks are not deducted for omissions
answers should only be judged on the quality of spelling, punctuation and grammar when these features are specifically assessed by the question as
indicated by the mark scheme. The meaning, however, should be unambiguous.
GENERIC MARKING PRINCIPLE 4:
Rules must be applied consistently, e.g. in situations where candidates have not followed instructions or in the application of generic level descriptors.
GENERIC MARKING PRINCIPLE 5:
Marks should be awarded using the full range of marks defined in the mark scheme for the question (however; the use of the full mark range may be limited
according to the quality of the candidate responses seen).
GENERIC MARKING PRINCIPLE 6:
Marks awarded are based solely on the requirements as defined in the mark scheme. Marks should not be awarded with grade thresholds or grade descriptors in
mind.
© UCLES 2023
Page 2 of 18
9709/52
Cambridge International AS & A Level – Mark Scheme
PUBLISHED
May/June 2023
www.dynamicpapers.com
Mathematics Specific Marking Principles
1
Unless a particular method has been specified in the question, full marks may be awarded for any correct method. However, if a calculation is required then
no marks will be awarded for a scale drawing.
2
Unless specified in the question, answers may be given as fractions, decimals or in standard form. Ignore superfluous zeros, provided that the degree of
accuracy is not affected.
3
Allow alternative conventions for notation if used consistently throughout the paper, e.g. commas being used as decimal points.
4
Unless otherwise indicated, marks once gained cannot subsequently be lost, e.g. wrong working following a correct form of answer is ignored (isw).
5
Where a candidate has misread a number in the question and used that value consistently throughout, provided that number does not alter the difficulty or
the method required, award all marks earned and deduct just 1 mark for the misread.
6
Recovery within working is allowed, e.g. a notation error in the working where the following line of working makes the candidate’s intent clear.
© UCLES 2023
Page 3 of 18
9709/52
Cambridge International AS & A Level – Mark Scheme
PUBLISHED
Mark Scheme Notes
May/June 2023
www.dynamicpapers.com
The following notes are intended to aid interpretation of mark schemes in general, but individual mark schemes may include marks awarded for specific reasons
outside the scope of these notes.
Types of mark
M
Method mark, awarded for a valid method applied to the problem. Method marks are not lost for numerical errors, algebraic slips or errors in units.
However, it is not usually sufficient for a candidate just to indicate an intention of using some method or just to quote a formula; the formula or idea
must be applied to the specific problem in hand, e.g. by substituting the relevant quantities into the formula. Correct application of a formula
without the formula being quoted obviously earns the M mark and in some cases an M mark can be implied from a correct answer.
A
Accuracy mark, awarded for a correct answer or intermediate step correctly obtained. Accuracy marks cannot be given unless the associated method
mark is earned (or implied).
B
Mark for a correct result or statement independent of method marks.
DM or DB
FT
When a part of a question has two or more ‘method’ steps, the M marks are generally independent unless the scheme specifically says otherwise;
and similarly, when there are several B marks allocated. The notation DM or DB is used to indicate that a particular M or B mark is dependent on
an earlier M or B (asterisked) mark in the scheme. When two or more steps are run together by the candidate, the earlier marks are implied and full
credit is given.
Implies that the A or B mark indicated is allowed for work correctly following on from previously incorrect results. Otherwise, A or B marks are
given for correct work only.
A or B marks are given for correct work only (not for results obtained from incorrect working) unless follow through is allowed (see abbreviation FT above).
For a numerical answer, allow the A or B mark if the answer is correct to 3 significant figures or would be correct to 3 significant figures if rounded (1
decimal place for angles in degrees).
The total number of marks available for each question is shown at the bottom of the Marks column.
Wrong or missing units in an answer should not result in loss of marks unless the guidance indicates otherwise.
Square brackets [ ] around text or numbers show extra information not needed for the mark to be awarded.
© UCLES 2023
Page 4 of 18
9709/52
Cambridge International AS & A Level – Mark Scheme
PUBLISHED
May/June 2023
www.dynamicpapers.com
Abbreviations
AEF/OE
Any Equivalent Form (of answer is equally acceptable) / Or Equivalent
AG
Answer Given on the question paper (so extra checking is needed to ensure that the detailed working leading to the result is valid)
CAO
Correct Answer Only (emphasising that no ‘follow through’ from a previous error is allowed)
CWO
Correct Working Only
ISW
Ignore Subsequent Working
SOI
Seen Or Implied
SC
Special Case (detailing the mark to be given for a specific wrong solution, or a case where some standard marking practice is to be varied in the
light of a particular circumstance)
WWW
Without Wrong Working
AWRT
Answer Which Rounds To
© UCLES 2023
Page 5 of 18
9709/52
Question
1(a)
May/June 2023
www.dynamicpapers.com
Cambridge International AS & A Level – Mark Scheme
PUBLISHED
Answer
3k 3k 8k 1, so k
Marks
Guidance
B1
1
14
x
2
2
3
P(x)
3
, 0.214
14
3
,0.214
14
8
,0.571
14
B1 FT Table with correct values of x, and at least one correct
probability linked with outcome. FT their k.
Condone any additional X values if probability stated as
0.
B1 FT The outcomes in the table must be –2, 2 and 3.
2 further correct probabilities in table
or 3 correct probabilities not in table linked to outcomes,
or 3 correct FT probabilities in table using their k,
or 3 incorrect probabilities summing to 1 in table if k not
stated.
If k not calculated, SC B1 for the below.
3
© UCLES 2023
Page 6 of 18
x
2
2
3
P(x)
3k
3k
8k
9709/52
Cambridge International AS & A Level – Mark Scheme
PUBLISHED
Question
1(b)
Answer
Marks
Guidance
M1 Accept unsimplified expression. May be calculated in
variance.
FT their table with 3 probabilities summing to 0.999 ⩽
total ⩽ 1 (0 < p < 1) or in terms of k.
3
3
8
E X 2 14 2 14 3 14
6 6 24
14 14 14
2
3
3
8
2
2
2
Var X (2) 14 2 14 3 14 their E X
3
3
8
12
4 9 their
14
14
14
7
2
12 12 72
12
their
14
7
May/June 2023
www.dynamicpapers.com
M1 Appropriate variance formula using their (E(X))2 value.
FT their table with 3 or more probabilities (0 < p < 1)
which need not sum to 1, or in terms of k with an
expression no more evaluated than shown.
2
4
A1 Answers for E(X) and Var(X) must be identified. E(X)
may be identified by correct use in Variance (condone E,
V, μ, σ2, etc.).
If A0 earned, SC B1 for identified correct final answers.
12
5
, 1.71, 1
7
7
192
45
, 3.92, 3
Var(X) =
49
49
E(X) =
3
Question
2(a)
Answer
[P(no rain) = 0.6 0.8 =] 0.3072,
3
Marks
B1 Exact value required
192
625
1
© UCLES 2023
Page 7 of 18
Guidance
9709/52
Cambridge International AS & A Level – Mark Scheme
PUBLISHED
Question
2(b)
Answer
Marks
0.6 0.8 0.2
= 0.096[0],
May/June 2023
www.dynamicpapers.com
Guidance
M1 a b c where a, b = 0.6, 0.8, c = 0.2, 0.4, 0.7 .
Condone including Wednesday with both 0.3 and 0.7
used.
A1
12
125
2
2(c)
B1 Correct probability for one clearly identified outcome
evaluated accept unsimplified.
A correct unsimplified expression is not sufficient.
48
625
18
P DRDD 0.6 0.2 0.3 0.8 = 0.0288,
625
18
P DDRD 0.6 0.8 0.2 0.3 = 0.0288,
625
48
P DDDR 0.6 0.8 0.8 0.2 = 0.0768,
625
P RDDD 0.4 0.3 0.8 0.8 = 0.0768,
M1 Add 4 probability values, 0 < p < 1, for appropriate
identified scenarios. Accept unsimplified.
Ways of identifying scenarios for this mark:
Stating the days.
All the unsimplified probability calculations exactly as
stated in the mark scheme.
Identifying the correct branches on a tree diagram and
linking with the values.
No repeated scenarios. No incorrect scenarios.
0.2112,
A1 Accept 0.211
132
625
If 0/3 scored SC B1 for 0.2112,
3
© UCLES 2023
Page 8 of 18
132
.
625
9709/52
Cambridge International AS & A Level – Mark Scheme
PUBLISHED
Question
3(a)
Answer
Marks
May/June 2023
www.dynamicpapers.com
Guidance
Median = 2710
B1 Must be identified, condone Q2.
Ignore units throughout.
2840 – 2610
M1 2820 ⩽ UQ ⩽ 2850 – 2600 ⩽ LQ ⩽ 2620.
230
A1 www
If M0 scored SC B1 for 230 www.
If key ignored consistently:
B0 Median = 271
SC M1 282 ⩽ UQ ⩽ 285 – 260 ⩽ LQ ⩽ 262
SC A1 23.
3
3(b)
B1 All 5 key values for B plotted accurately in standard
format using a linear scale with 3 identified values.
Labelled B.
Scale at least 1 cm = $100.
Box-and-whisker plot on provided grid.
B:
A:
2540
2500
2600
2610
2690
2710
2780
2840
B1FT All 5 key values for A, FT from (a), plotted accurately in
standard format using a linear scale with 3 identified
values. Labelled A.
Scale at least 1cm = $100
3090
3010
B1 Whiskers not through box for both, not drawn at corners
of boxes, single linear scale for the diagram and labelled
‘salaries’ (oe) and $.
3
© UCLES 2023
Page 9 of 18
9709/52
Cambridge International AS & A Level – Mark Scheme
PUBLISHED
Question
3(c)
Answer
Marks
Examples:
Mean less appropriate than median because of extreme value for company B
[at $3090].
No, extreme value in company B.
No, $3090 is an anomaly.
May/June 2023
www.dynamicpapers.com
Guidance
B1 Must refer to company B, may be implied by appropriate
use of $3090.
Must include an indication that the mean is not
appropriate.
No contradictory statements can be present, e.g.
acceptable comment with ‘but mean could be used for
company A’.
Condone reference to $309.
1
Question
4(a)
Answer
[P(X = 4) = 0.8 0.2 ] 0.1024,
3
Marks
B1 Condone 0.102 .
64
625
1
© UCLES 2023
Page 10 of 18
Guidance
9709/52
Question
4(b)
May/June 2023
www.dynamicpapers.com
Cambridge International AS & A Level – Mark Scheme
PUBLISHED
Answer
Marks
M1 1 0.8d , d = 5, 6.
[P(X < 6 ) =] 1 0.85
= 0.672,
Guidance
A1 0.67232 to at least 3SF.
2101
3125
If M0 awarded, SC B1 for
2101
or 0.67232 only.
3125
Alternative Method for Question 4(b)
2
3
4
1 4 1 4 1 4 1 4 1
[P(X < 6 ) = ]
5 5 5 5 5 5 5 5 5
M1 If answer correct, condone omission of 2 from 3 middle
terms.
Allow M1 for
2
3
4
5
1 4 1 4 1 4 1 4 1 4 1
5 5 5 5 5 5 5 5 5 5 5
= 0.672,
A1 0.67232 to at least 3SF.
2101
3125
If M0 awarded, SC B1 for
2
© UCLES 2023
Page 11 of 18
2101
or 0.67232 only.
3125
9709/52
Cambridge International AS & A Level – Mark Scheme
PUBLISHED
Question
4(c)
Answer
May/June 2023
www.dynamicpapers.com
Marks
P X 0 X 2
P X 0|X 2
P X 2
14
= 25
19
25
14
, 0.737
=
19
M1
Guidance
14
, 0.56[0] seen as numerator or
25
denominator of conditional probability fraction.
[P( X > 0 ∩ X ≠ 2) = ]
M1
19
, 0.76[0] seen as denominator of
25
conditional probability fraction.
A1
14
, 0.7368421… to at least 3SF.
19
If A0, SC B1 for correct final answer www.
[P(X ≠ 2) = ]
Final answer =
Alternative Method for Question 4(c)
1
2
3
4
5
1
0
1
2
3
4
2
1
0
1
2
3
3
2
1
0
1
2
4
3
2
1
0
1
M1 Number of outcome X 0 X 2 14 seen as
numerator or denominator of conditional probability
fraction.
5
4
3
2
1
0
M1 Number of outcome X 2 19 seen as denominator
of conditional probability fraction.
Number of outcome X 0 X 2
P X 0|X 2
Number of outcomes X 2
14
, 0.737
19
A1
3
© UCLES 2023
Page 12 of 18
Final answer =
14
, 0.7368421… to at least 3SF.
19
9709/52
Question
4(d)
May/June 2023
www.dynamicpapers.com
Cambridge International AS & A Level – Mark Scheme
PUBLISHED
Answer
[P(X >2) = 1 – P(0, 1, 2) with p =
9
1
Marks
M1 One term 9Cx p x 1 p 9 x , 0 p 1, 0 x 9.
6
]
25
8
Guidance
2
7
19
6 19
6 19
1 – (9C0 + 9C1 + 9C2 )
25
25 25
25 25
[1 – (0.08459 + 0.2404 + 0.3037)]
A1 1 – (9C0 1 p 9 + 9C1 p 1 1 p 8
0.371
B1 0.371 ⩽ p < 0.3715 .
+ 9C2 p 1 p ) , 0 p 1 .
Correct expression from their p, accept unsimplified, no
terms omitted leading to final answer.
Condone omission of last bracket only.
2
7
Alternative Method for Question 4(d)
[P(X>2) = P(3,4,5,6,7,8,9) with p =
3
6
4
M1 One term 9Cx p x 1 p 9 x , 0 p 1, 0 x 9.
6
]
25
5
8
1
6 19
6 19
6 19
6
C3 + 9C4 + … + 9C8 + 9C9
25 25
25 25
25 25
25
–5
–6
[0.2238 + 0.1060 + … + 7.529 10 + 2.642 10 ]
9
9
A1 9C3 p 3 1 p 6 + 9C4 p 4 1 p 5 + … + 9C8
p 1 p
+ 9C9 p , 0 p 1 .
Correct expression from their p, accept unsimplified, no
terms omitted leading to final answer.
8
B1 0.371 ⩽ p < 0.3715 .
0.371
3
© UCLES 2023
1
Page 13 of 18
9
9709/52
Cambridge International AS & A Level – Mark Scheme
PUBLISHED
Question
5(a)
Answer
[P(15.4 < X < 16.8 ) =] P(
[= P( 1.833 Z 0.5) ]
Marks
15.4 16.5
16.8 16.5
)
Z
0.6
0.6
May/June 2023
www.dynamicpapers.com
Guidance
M1 Use of ± standardisation formula once with 16.5, 0.6 and
either 15.4 or 16.8 substituted.
[= Φ 0.5 Φ 1.833 1 ]
0.6915 0.9666 – 1
M1 Calculating the appropriate probability area (leading to
their final answer, expect > 0.5).
0.6915 – (1 – 0.9666)
or
(0.6915 – 0.5) + (0.9666 – 0.5) OE are alternatives.
= 0.658
A1 0.658 ≤ p < 0.6585 .
If A0 scored, SC B1 for 0.658 ⩽ p < 0.6585 .
[Expected number =] 0.6581 150
= 98, 99
B1 FT FT their 4SF (or better) probability from a normal
calculation.
Must be a positive single integer answer.
No approximation notation.
4
5(b)
B1 0.5825 < z ⩽ 0.583 or – 0.583 ⩽ z < – 0.5825 seen.
17.1 18.4
0.72
P Z
17.1 18.4
0.583
M1 Use of the ± standardisation formula with 17.1, 18.4, σ
and a z-value (not 0.28, 0.72, 0.4175, 0.2358, 0.7642,
0.6103, 0.3897, …).
Condone continuity correct ± 0.05, not 2 , .
2.23
A1 AWRT
3
© UCLES 2023
Page 14 of 18
9709/52
Cambridge International AS & A Level – Mark Scheme
PUBLISHED
Question
5(c)
Answer
Marks
[Mean = 120 0.72 =] 86.4
[Var = 120 0.72 0.28 =] 24.192
P(X < 80) = P( Z
May/June 2023
www.dynamicpapers.com
B1
79.5 86.4
)
24.192
Guidance
2
24
and 24
, 24.192 to at least 3SF seen, allow
5
125
unsimplified.
May be seen in standardisation formula.
(4.918 ⩽ σ ⩽ 4.919 implies correct variance)
Incorrect notation is penalised.
86.4, 84
M1 Substituting their mean (not 18.4) and their positive
4.9185 into ± standardisation formula (any number for
79.5), condone their 4.9182 and √their 4.918 .
M1 Using continuity correction 79.5 or 80.5 in their
standardisation formula.
[P( Z 1. 4029) = 1− Φ 1.403 ]
1 − 0.9196
M1 Appropriate area Φ, from final process, must be a
probability. Expect final answer < 0.5 .
Note: correct final answer implies this M1.
0.0804
A1 0.0803 ⩽ p ⩽ 0.0804
5
© UCLES 2023
Page 15 of 18
9709/52
Cambridge International AS & A Level – Mark Scheme
PUBLISHED
Question
6(a)
Answer
Marks
S + 4C + 2R 6C1 8C4 11C2 [= 6 70 55] = 23 100
S + 5C + 1R 6C1 8C5 11C1 [= 6 56 11] 3696
S + 6C [+ 0R] 6C1 8C6 [ 11C0][= 6 28] = 168
May/June 2023
www.dynamicpapers.com
Guidance
M1 6Ce 8Cf 11Cg, with e + f + g = 7 seen.
B1 Correct outcome/value for 1 identified scenario, accept
unsimplified, www.
M1 Add values of 3 correct scenarios.
No incorrect scenarios, no repeated scenarios.
Condone 6Ce 8Cf 11Cg, with e + f + g = 7 to identify S,
C, R.
[Total =] 26964
A1 cao
4
6(b)
2! 3! 4! 6
M1 2! 3! 4! k, k an integer > 0. 1 can be implied.
=1728
A1 If A0 scored SC B1 for 1728 www.
2
© UCLES 2023
Page 16 of 18
9709/52
Cambridge International AS & A Level – Mark Scheme
PUBLISHED
Question
6(c)
Answer
Marks
May/June 2023
www.dynamicpapers.com
Guidance
Method 1
6! 7 6 5
M1 6! k, k an integer > 0. 1 can be implied.
151 200
M1
m!
7 n r; 6 ⩽ m ⩽ 9; a = 1, 2; b = 1, 4;
a! b!
1 ⩽ n, r ⩽ 6, n ≠ r.
M1
m!
7 6 5; 6 ⩽ m ⩽ 9; a =1, 2; b = 1, 4.
a! b!
A1 Condone 151 000.
If A0 scored SC B1 for 151 200 www.
Method 2
6! 7P3
M1 6! k, k an integer > 0. 1 can be implied.
151 200
© UCLES 2023
M1
m!
m!
× 7Pq, or
× 7 Cq q ! ; 6 ≤ m ≤ 9; a =1, 2;
a! b!
a! b!
b = 1, 4; 1 ≤ q ≤ 6.
M1
m!
m!
× 7P3, or
× 7 C3 3! ; 6 ≤ m ≤ 9; a =1, 2;
a! b!
a! b!
b = 1, 4.
A1 Condone 151 000.
If A0 scored SC B1 for 151 200 www.
Page 17 of 18
9709/52
Cambridge International AS & A Level – Mark Scheme
PUBLISHED
Question
6(c)
Answer
Marks
May/June 2023
www.dynamicpapers.com
Guidance
Method 3
6! 35 3!
M1 6! k, k an integer > 0. 1 can be implied.
151 200
M1
m!
35 q!; 6 ⩽ m ⩽ 9; a =1, 2; b = 1, 4;
a! b!
1 ⩽ q ⩽ 3.
M1
m!
35 6; 6 ⩽ m ⩽ 9; a =1, 2; b = 1, 4.
a! b!
A1 Condone 151 000.
If A0 scored SC B1 for 151 200 www.
Method 4
M1 9! – 7!r! – q, r an integer > 1, q an integer ⩽ 0. 0 and 1
may be implied.
9! – 7!3! – 3P2 6! 7 6
Or
9! – 7!3! – 3! 7! 6
M1
s!
– 7!3! – q; s = 8, 9; a =1, 2; b = 1, 3; c = 1, 4;
a ! b! c!
q an integer ⩾ 0. 0 and 1 may be implied.
M1
s!
– 7!3! – 3P2 6! 6 7, 6 ⩽ s ⩽ 9,
a ! b! c!
s!
– 7!3! – 3! 7! 6, 6 ⩽ s ⩽ 9.
or
a ! b! c!
a =1, 2 b = 1, 3 c = 1, 4. 1 may be implied.
[= 362 880 – 30 240 – 181 440]
151 200
A1 Condone 151 000.
If A0 scored SC B1 for 151 200 www.
4
© UCLES 2023