Cambridge International AS & A Level
ACCOUNTING

9706/43

Paper 4 Cost and Management Accounting

October/November 2023

MARK SCHEME
Maximum Mark: 50

Published

This mark scheme is published as an aid to teachers and candidates, to indicate the requirements of the
examination. It shows the basis on which Examiners were instructed to award marks. It does not indicate the
details of the discussions that took place at an Examiners’ meeting before marking began, which would have
considered the acceptability of alternative answers.
Mark schemes should be read in conjunction with the question paper and the Principal Examiner Report for
Teachers.
Cambridge International will not enter into discussions about these mark schemes.
Cambridge International is publishing the mark schemes for the October/November 2023 series for most
Cambridge IGCSE, Cambridge International A and AS Level components, and some Cambridge O Level
components.

This document consists of 14 printed pages.
© UCLES 2023

[Turn over

9706/43

Cambridge International AS & A Level – Mark Scheme
PUBLISHED
Generic Marking Principles

October/November 2023
www.dynamicpapers.com

These general marking principles must be applied by all examiners when marking candidate answers. They should be applied alongside the
specific content of the mark scheme or generic level descriptors for a question. Each question paper and mark scheme will also comply with these
marking principles.
GENERIC MARKING PRINCIPLE 1:
Marks must be awarded in line with:
•
•
•

the specific content of the mark scheme or the generic level descriptors for the question
the specific skills defined in the mark scheme or in the generic level descriptors for the question
the standard of response required by a candidate as exemplified by the standardisation scripts.

GENERIC MARKING PRINCIPLE 2:
Marks awarded are always whole marks (not half marks, or other fractions).
GENERIC MARKING PRINCIPLE 3:
Marks must be awarded positively:
•
•
•
•
•

marks are awarded for correct/valid answers, as defined in the mark scheme. However, credit is given for valid answers which go beyond
the scope of the syllabus and mark scheme, referring to your Team Leader as appropriate
marks are awarded when candidates clearly demonstrate what they know and can do
marks are not deducted for errors
marks are not deducted for omissions
answers should only be judged on the quality of spelling, punctuation and grammar when these features are specifically assessed by the
question as indicated by the mark scheme. The meaning, however, should be unambiguous.

GENERIC MARKING PRINCIPLE 4:
Rules must be applied consistently, e.g. in situations where candidates have not followed instructions or in the application of generic level
descriptors.

© UCLES 2023

Page 2 of 14

9706/43

Cambridge International AS & A Level – Mark Scheme
PUBLISHED

October/November 2023
www.dynamicpapers.com

GENERIC MARKING PRINCIPLE 5:
Marks should be awarded using the full range of marks defined in the mark scheme for the question (however; the use of the full mark range may
be limited according to the quality of the candidate responses seen).
GENERIC MARKING PRINCIPLE 6:
Marks awarded are based solely on the requirements as defined in the mark scheme. Marks should not be awarded with grade thresholds or
grade descriptors in mind.

© UCLES 2023

Page 3 of 14

Cambridge International AS & A Level – Mark Scheme
PUBLISHED
Social Science-Specific Marking Principles
(for point-based marking)

9706/43

1

October/November 2023
www.dynamicpapers.com

Components using point-based marking:
• Point marking is often used to reward knowledge, understanding and application of skills. We give credit where the candidate’s answer
shows relevant knowledge, understanding and application of skills in answering the question. We do not give credit where the answer
shows confusion.
From this it follows that we:
a
b
c
d
e
f
g

2

DO credit answers which are worded differently from the mark scheme if they clearly convey the same meaning (unless the mark
scheme requires a specific term)
DO credit alternative answers/examples which are not written in the mark scheme if they are correct
DO credit answers where candidates give more than one correct answer in one prompt/numbered/scaffolded space where extended
writing is required rather than list-type answers. For example, questions that require n reasons (e.g. State two reasons …).
DO NOT credit answers simply for using a ‘key term’ unless that is all that is required. (Check for evidence it is understood and not used
wrongly.)
DO NOT credit answers which are obviously self-contradicting or trying to cover all possibilities
DO NOT give further credit for what is effectively repetition of a correct point already credited unless the language itself is being tested.
This applies equally to ‘mirror statements’ (i.e. polluted/not polluted).
DO NOT require spellings to be correct, unless this is part of the test. However spellings of syllabus terms must allow for clear and
unambiguous separation from other syllabus terms with which they may be confused (e.g. Corrasion/Corrosion)

Presentation of mark scheme:
• Slashes (/) or the word ‘or’ separate alternative ways of making the same point.
• Semi colons (;) bullet points (•) or figures in brackets (1) separate different points.
• Content in the answer column in brackets is for examiner information/context to clarify the marking but is not required to earn the mark
(except Accounting syllabuses where they indicate negative numbers).

© UCLES 2023

Page 4 of 14

9706/43

Cambridge International AS & A Level – Mark Scheme
PUBLISHED

October/November 2023
www.dynamicpapers.com

3

Calculation questions:
• The mark scheme will show the steps in the most likely correct method(s), the mark for each step, the correct answer(s) and the mark
for each answer
• If working/explanation is considered essential for full credit, this will be indicated in the question paper and in the mark scheme. In all
other instances, the correct answer to a calculation should be given full credit, even if no supporting working is shown.
• Where the candidate uses a valid method which is not covered by the mark scheme, award equivalent marks for reaching equivalent
stages.
• Where an answer makes use of a candidate’s own incorrect figure from previous working, the ‘own figure rule’ applies: full marks will be
given if a correct and complete method is used. Further guidance will be included in the mark scheme where necessary and any
exceptions to this general principle will be noted.

4

Annotation:
• For point marking, ticks can be used to indicate correct answers and crosses can be used to indicate wrong answers. There is no direct
relationship between ticks and marks. Ticks have no defined meaning for levels of response marking.
• For levels of response marking, the level awarded should be annotated on the script.
• Other annotations will be used by examiners as agreed during standardisation, and the meaning will be understood by all examiners
who marked that paper.

© UCLES 2023

Page 5 of 14

Cambridge International AS & A Level – Mark Scheme
PUBLISHED

9706/43
ANNOTATIONS

The following annotations are used in marking this paper and should be used by examiners.
Annotation

Use or meaning

Correct and relevant point made in answering the question.

×

Incorrect point or error made.

LNK

Two statements are linked.

REP

Repeat

A

An extraneous figure

N0

No working shown

AE

Attempts evaluation

R1

Required item 1

R2

Required item 2

OF

Own figure

EVAL

Evaluation

NAQ

Not answered question

BOD

Benefit of the doubt given.

SEEN

Noted but no credit given

Highlight

Highlight

Off page
Comment

Off page comment

© UCLES 2023

Page 6 of 14

October/November 2023
www.dynamicpapers.com

9706/43

Cambridge International AS & A Level – Mark Scheme
PUBLISHED

October/November 2023
www.dynamicpapers.com

Abbreviations and guidance
The following abbreviations may be used in the mark scheme:
OF = own figure. The answer will be marked correct if a candidate has correctly used their own figure from a previous part or calculation.
W = working. The working for a figure is given below. Where the figure has more than one mark associated with it, the working will show where
individual marks are to be awarded.
CF = correct figure. The figure has to be correct i.e. no extraneous items have been included in the calculation
Extraneous item = an item that should not have been included in a calculation, including indirect expenses such as salaries in calculation of
gross profit when there is one OF mark for gross profit’
Curly brackets, }, are used to show where one mark is given for more than one figure. If the figures are not adjacent, each is marked with a
curly bracket and a symbol e.g. }*
row = all figures in the row must be correct for this mark to be awarded
Marks for figures are dependent on correct sign/direction
Accept other valid responses. This statement indicates that marks may be awarded for answers that are not listed in the mark scheme but are
equally valid.

© UCLES 2023

Page 7 of 14

Cambridge International AS & A Level – Mark Scheme
PUBLISHED

9706/43
Question
1(a)

Answer
Prepare the flexible budget statement for the month of April.

Sales revenue ($184 000/2 000)  2180

$
200 560

Direct materials ($84 000/2 000)  2180
Direct labour ($60 000/2 000)  2180
Fixed overhead ($18 000/2 000)  2180
Total cost

91 560
65 400
19 620
176 580

Budgeted profit
1(b)(i)

October/November 2023
www.dynamicpapers.com
Marks
3

}
}
} (1)
(1)

23 980 (1) OF

Calculate the following variances:

2

sales price
Sales price variance
$184 000/2000 = $92
(2180  $92) – $196 200= $4360 (1) A (1)
1(b)(ii)

Calculate the following variances:

2

sales volume (as a measure of change in profit)
Sales volume variance
$22 000/2000 =$11
(2180 – $2000)  $11=$1980 (1) F (1)
1(b)(iii)

Calculate the following variances:
fixed overhead expenditure

2

Fixed overhead expenditure
$18 400 – $18 000 = $400 (1) A (1)

© UCLES 2023

Page 8 of 14

9706/43

Cambridge International AS & A Level – Mark Scheme
PUBLISHED

Question
1(b)(iv)

October/November 2023
www.dynamicpapers.com

Answer

Marks

Calculate the following variances:
fixed overhead volume

2

Fixed overhead volume
$19 620 OF – $18 000 = $1620 (1) F (1)
1(c)

Prepare a statement to reconcile the flexible budgeted profit as calculated in (a) with the actual profit. Your
statement should start with the flexible budgeted profit.

Flexible budgeted profit
Sales price variance
Direct materials variance ($113 796 – $91 560)
Direct labour variance ($65 400 – 55 590)
Fixed overhead expenditure
Fixed overhead volume
Actual profit

© UCLES 2023

$
23 980
(4 360)
(22 236)
9 810
(400)
1 620
8 414

(1)OF
A}
A
F
A}
F}

Page 9 of 14

(2)
(2)
(1)OF
(1)

7

9706/43
Question
1(d)

Cambridge International AS & A Level – Mark Scheme
PUBLISHED

October/November 2023
www.dynamicpapers.com

Answer
Advise the directors which supplier they should choose. Justify your answer and support it with relevant
calculations.
Calculations
The unit cost for both suppliers is the same – (2.8  $13.75) = (2.5  $15.40) = $38.50 (1)
The unit cost $38.5 by either supplier is lower than the budgeted cost of $42 ($84 000/2 000) and actual cost of $52.20
($113 796/2 180) (1)
Max 2
Comments
The quality of materials from supplier B is better than from A (1) because of less wastage (1)
Direct material of poor quality may affect the efficiency of workers as well as the quality of final product (1)
The unit purchase price of supplier A is lower than B (1)
Additional costs may be incurred for supplier B, i.e. import duty, freight charge and insurance (1)
As delivery takes time, prompt delivery from supplier B may not be possible (1) for an urgent order (1)
Max 4
Decision supported by a comment (1)
Accept other valid responses.

© UCLES 2023

Page 10 of 14

Marks
7

Question
2(a)(i)

October/November 2023
www.dynamicpapers.com

Cambridge International AS & A Level – Mark Scheme
PUBLISHED

9706/43

Answer

Marks

Prepare a statement showing the net cash flow for each year from Year 0 to Year 3 for:

5

model IM3
Option 1 – Model IM3

Purchase price
Cost of improvement
Sales W1
Operating cost W2
Other fixed overheads W3
Net cash flow

Year 0
$
(141 000) }
(57 000) }(1)

(198 000)

Year 1
$

Year 2
$

Year 3
$

624 000
(288 000)
(261 000)
75 000

780 000
(360 000)
(261 000)
159 000

520 000
(240 000)
(261 000)
19 000

(1) row
(1) row
(1) row
(1)OF row

Alternative presentation
Purchase price

Year 0
Year 1
Year 2
Year 3

$
(141 000)}

Cost of
improvement
$
(57 000)} (1)

Sales
W1
$
624 000
780 000
520 000
(1) col

Operating cost
W2
$
(288 000)
(360 000)
(240 000)
(1) col

Other fixed
overheads
W3
$
(261 000)
(261 000)
(261 000)
(1) col

W1 12 000  $52=$624 000, 15 000  $52=$780 000, 10 000  $52=$520 000
W2 12 000  $4.80  5=$288 000, 15 000  $4.80 x5=$360 000, 10 000  $4.80 x5=$240 000
W3 Depreciation ($141 000 + $57 000)/3=$66 000
$327 000 – $66 000=$261 000

© UCLES 2023

Page 11 of 14

Net cash
flow
$
(198 000)
75 000
159 000
19 000
(1) OF col

Question
2(a)(ii)

October/November 2023
www.dynamicpapers.com

Cambridge International AS & A Level – Mark Scheme
PUBLISHED

9706/43

Answer

Marks

Prepare a statement showing the net cash flow for each year from Year 0 to Year 3 for:
model IM8
Option 2 – Model IM8

Purchase price
Sales W1
Operating cost W2
Other fixed overheads W3
Net cash flow

Year 0
$
(420 000)

Year 1
$
624 000
(230 400)
(215 000)
178 600

(420 000)

Year 2
$

Year 3
$

936 000
(345 600)
(215 000)
375 400

520 000
(192 000)
(215 000)
113 000

(1) row
(1) row
(1) row
(1)OF row

Alternative presentation

Year 0
Year 1
Year 2
Year 3

Purchase price

Sales
W1

$
(420 000)}

$
624 000
936 000
520 000
(1) col

Operating cost
W2
$
(230 400)
(345 600)
(192 000)
(1) col

Other fixed
overheads
W3
$

Net cash
flow

(215 000)
(215 000)
(215 000)
(1) col

W1 12 000  $52 = $624 000, 18 000  $52 = $936 000, 10 000  $52 = $520 000
W2 12 000  $4.8  4=$230 400, 18 000x$4.8x4=$345 600, 10 000  $4.8  4 = $192 000
W3 Depreciation $420000/3 = $140 000
$355 000-$140 000 = $215 000

© UCLES 2023

Page 12 of 14

$
(420 000)
178 600
375 400
113 000
(1) col

4

Cambridge International AS & A Level – Mark Scheme
PUBLISHED

9706/43
Question
2(b)

Answer
State two advantages of using the net present value (NPV) method for investment appraisal.

October/November 2023
www.dynamicpapers.com
Marks
2

It takes into account cash flow which is more objective than profitability (1)
It takes into account the time value of money (1)
It takes into account all cash flows of an investment/a project (1)
Max 2
Accept other valid responses.
2(c)

Calculate the NPV for each model of machine.

4

NPV of IM3
Year
0
1
2
3
NPV

Net cash
flow
$
(198 000)
75 000
159 000
19 000

Discount
factor

Net cash
flow
$
(420 000)
178 600
375 400
113 000

Discount
factor

1
0.893
0.797
0.712

Present
value
$
(198 000)
66 975
126 723
13 528
9 226

}
}
}
}(1OF)
(1OF)

NPV of IM8
Year
0
1
2
3

© UCLES 2023

1
0.893
0.797
0.712

Present
value
$
(420 000)
159 490
299 194
80 456
119 140

}
}
}
}(1OF)
(1OF)

Page 13 of 14

9706/43

Cambridge International AS & A Level – Mark Scheme
PUBLISHED

Question
2(d)

October/November 2023
www.dynamicpapers.com

Answer

Marks

Advise the directors which model W Limited should choose. Justify your answer.

7

IM8 has a higher positive NPV than IM3 (1)
IM8 is more efficient than IM3, i.e. fewer machine hours resulting in lower operating costs (1)
IM8 has a higher initial outlay (1)
Opportunity cost has to be considered (1)
The method of financing IM8 has to be considered (1)
IM3 has been used before and there is no need for training of workers, but IM8 may require training (1)
IM8 is a new model and the quality of products may be better (1)
IM8 has more production capacity to meet urgent sales orders (1)
Max 6 for comments.
Decision supported by a comment (1)
Accept other valid responses.
2(e)

Calculate the change in NPV of IM3 if the additional cost is incurred.

NPV of additional revenue ($18000-$15000) x ($52 – $4.8  5) x 0.797
NPV of additional improvement cost $5000  0.893
Increase in NPV

© UCLES 2023

Page 14 of 14

3
$
66 948 (1)
(4 465) (1)
62 483 (1) OF