Accounting (9706) · May/June 2024 · Question paper 42
Cambridge Accounting (9706) question paper for paper 42, May/June 2024 — 9706/42/M/J/24, file 9706_s24_qp_42.pdf.
Text of this paper
www.dynamicpapers.com
Cambridge International AS & A Level
* 8 1 2 3 8 3 0 5 8 2 *
ACCOUNTING
9706/42
Paper 4 Cost and Management Accounting
May/June 2024
1 hour
You must answer on the question paper.
You will need:
Insert (enclosed)
INSTRUCTIONS
●
Answer all questions.
●
Use a black or dark blue pen.
●
Write your name, centre number and candidate number in the boxes at the top of the page.
●
Write your answer to each question in the space provided.
●
Do not use an erasable pen or correction fluid.
●
Do not write on any bar codes.
●
You may use an HB pencil for any diagrams, graphs or rough working.
●
You may use a calculator.
●
You should present all accounting statements in good style.
●
You should show your workings.
INFORMATION
●
The total mark for this paper is 50.
●
The number of marks for each question or part question is shown in brackets [ ].
●
The insert contains all of the sources referred to in the questions.
This document has 12 pages. Any blank pages are indicated.
DC (PB (GB) 326881/4
© UCLES 2024
[Turn over
2
1
www.dynamicpapers.com
Read Source A in the insert.
(a) Prepare the production budget (in units) for each of the months April, May, June and
July 2025.
[4]
Additional information
The budgeted cost structure of each unit is as follows:
$
Direct
materials
25
These are purchased on credit in the month of production.
•
•
•
One fifth (20%) is paid for in the month following purchase after a
5% discount.
Another fifth (20%) is paid for in the month following purchase but
without any discount.
The remainder (60%) is paid for in the second month after
purchase.
Direct labour
30
This is all paid in the month of production.
Other costs
40
These are all paid in the month after production, with the exception of a
$4 per unit charge for depreciation.
© UCLES 2024
9706/42/M/J/24
3
www.dynamicpapers.com
(b) Prepare an extract from the cash budget for each of the months June and July 2025 to show
the payments related to production.
Workings:
[7]
© UCLES 2024
9706/42/M/J/24
[Turn over
4
www.dynamicpapers.com
Additional information
The company usually makes all its sales on a cash basis for a selling price of $150 per unit. It
expects to operate with a bank overdraft throughout 2025.
The company has received an order from a prospective new customer who is based overseas.
This order is for 900 units to be supplied in June 2025. The customer is prepared to pay $156 per
unit, paying in six equal monthly instalments starting in August 2025.
(c) Calculate the change in the expected bank overdraft at the end of each of the months June,
July and August 2025 if the order was accepted. Assume that all the extra production would
take place in the month in which the units are supplied.
[7]
© UCLES 2024
9706/42/M/J/24
5
www.dynamicpapers.com
(d) Advise the directors whether or not the company should accept the order. Justify your answer.
[7]
[Total: 25]
© UCLES 2024
9706/42/M/J/24
[Turn over
6
2
www.dynamicpapers.com
Read Source B in the insert.
(a) State why cost drivers are used in the application of activity based costing (ABC).
[1]
(b) Calculate the selling price of one unit of each product.
Workings:
[9]
© UCLES 2024
9706/42/M/J/24
7
www.dynamicpapers.com
Additional information
Sooraj is considering using machine hours rather than carrying values to allocate the depreciation
cost.
(c) Calculate the change in selling price of one unit of each product if Sooraj uses machine
hours as the cost driver for depreciation cost.
[5]
(d) Explain the relationship between the choice of cost driver and profit.
[3]
© UCLES 2024
9706/42/M/J/24
[Turn over
8
www.dynamicpapers.com
Additional information
In recent months, actual results have been unfavourable in comparison with the budgeted figures.
On one occasion, the manufacture of Product A had been stopped and sales lost because the sole
supplier of some of the components of that product had been unable to fulfil Sooraj’s orders.
Sooraj is considering manufacturing these components in his own factory instead of buying them
in. He estimates that the total direct material cost of Product A would fall to $30 per unit and
that the labour requirement for Product A would increase to 5 hours per unit, with the wage rate
unchanged.
The budgeted depreciation cost would increase by $8000 per annum. Sooraj is unclear whether
overheads other than depreciation would be affected.
(e) Advise Sooraj whether or not he should manufacture these components for Product A in
his own factory. Justify your answer. Your answer should include any effect on the costs of
Product B.
© UCLES 2024
9706/42/M/J/24
9
www.dynamicpapers.com
[7]
[Total: 25]
© UCLES 2024
9706/42/M/J/24
10
BLANK PAGE
© UCLES 2024
9706/42/M/J/24
www.dynamicpapers.com
11
BLANK PAGE
© UCLES 2024
9706/42/M/J/24
www.dynamicpapers.com
12
www.dynamicpapers.com
BLANK PAGE
Permission to reproduce items where third-party owned material protected by copyright is included has been sought and cleared where possible. Every
reasonable effort has been made by the publisher (UCLES) to trace copyright holders, but if any items requiring clearance have unwittingly been included, the
publisher will be pleased to make amends at the earliest possible opportunity.
To avoid the issue of disclosure of answer-related information to candidates, all copyright acknowledgements are reproduced online in the Cambridge
Assessment International Education Copyright Acknowledgements Booklet. This is produced for each series of examinations and is freely available to download
at www.cambridgeinternational.org after the live examination series.
Cambridge Assessment International Education is part of Cambridge Assessment. Cambridge Assessment is the brand name of the University of Cambridge
Local Examinations Syndicate (UCLES), which is a department of the University of Cambridge.
© UCLES 2024
9706/42/M/J/24