Cambridge International Examinations
Cambridge Ordinary Level

5054/32

PHYSICS

October/November 2017

Paper 3 Practical Test
CONFIDENTIAL INSTRUCTIONS
* 9 5 9 0 9 8 0 0 4 6 *

Great care should be taken to ensure that any confidential information given does not reach the
candidates either directly or indirectly.
No access to the Question Paper is permitted in advance of the examination.

If you have any problems or queries regarding these Instructions, please contact Cambridge stating the
Centre number, the nature of the query and the syllabus number quoted above.
email
phone
fax

[email protected]
+44 1223 553554
+44 1223 553558
This document consists of 11 printed pages and 1 blank page.

DC (ST/SW) 131695/2
© UCLES 2017

[Turn over

2

www.dynamicpapers.com

Instructions for preparing apparatus
These Confidential Instructions detail the apparatus required for each experiment in this paper. No
access is permitted to the Question Paper in advance of the examination session.
Number of sets of apparatus
In addition to a few spare sets, the minimum number of sets of apparatus to be provided should be
sufficient to enable candidates to spend 20 minutes with the apparatus for each of Questions 1, 2 and
3, and one hour with the apparatus for Question 4. The order in which candidates answer the questions
will be determined by the Supervisor. Candidates may spend one hour circulating around Questions 1,
2 and 3, followed by an hour on Question 4, or vice versa.
It is assumed that candidates will supply their own calculator and geometrical instruments, such as a
set square, 0° to 180° protractor, pair of compasses and 30 cm ruler. Candidates should be advised
in advance that they may, if they wish, use wristwatches with stopwatch facilities, providing that such
wristwatches afford the required precision.
Instructions for the supervision of the examination
The Supervisor, who may be a physics teacher, is responsible for the administration of the examination
according to the procedures detailed in the Handbook for Centres. In all instances, a physics teacher
should be present. Preferably, this teacher should have been responsible for the preparation of the
apparatus. Two invigilators must be present at all times: it is not acceptable for a teacher who has been
responsible for preparing the candidates for this paper to be the sole Supervisor or Invigilator.
Supervisors may make the following announcement at the start of the examination.
‘The Examiners do not want you to waste time if you are unable to do any experiment. Any candidate
who is unable to get results with an experiment may ask for help. The extent of the help given will be
reported to the Examiners, who may make a deduction of marks.’
Supervisors should note that a candidate may only be given enough assistance to allow some raw
readings or observations to be made. On no account should any assistance be given with the treatment
or analysis of these readings and observations.
Supervisors may draw to the attention of the candidates any significant deviation between the apparatus
provided and that detailed in the Question Paper, particularly where diagrams are given in the paper.
Candidates should be reminded that all their work should be written on the Question Paper. Rough
paper must not be used.
The Supervisor must complete the Report at the back of these Instructions. Details should be given
of any significant deviation between the apparatus used and that specified in these Instructions. A
sample set of results can often help Examiners. A copy of this Report must be included in each packet
of scripts.

© UCLES 2017

5054/32/CI/O/N/17

www.dynamicpapers.com

3
Question 1

Items to be supplied by the Centre (per set of apparatus, unless otherwise specified)
Two expendable steel springs, with a spring constant of approximately 25 N / m, e.g. Griffin catalogue
number 12463080 or legacy number XBV-590-010H (see Note 1).
100 g mass hanger and seven 100 g slotted masses (see Note 2).
Stand, boss and clamp to support the two springs.
Blu-tack.
Second clamp and boss to act as a fiducial marker.
Stopwatch, to a precision of at least 0.1 s.
Notes
1.

The springs should be as identical as possible.

2.

The slotted masses should be placed on the hanger and taped together. The total mass of 800 g
should be labelled M.

3.

The Supervisor should set up the apparatus as shown in Fig. 1.1. The loops at the tops of the
springs should be about 2 cm apart on the rod of the clamp and each held in place by a small
piece of Blu-tack. The hook of the mass hanger should pass through the bottom loop of both
springs. The second clamp should be held on the same stand, close to the bottom of the stand.
The rod of the clamp should be on the same side as the springs.
Blu-tack
rod of clamp
springs in parallel

stand
M

boss

rod A
bench
Fig. 1.1

© UCLES 2017

5054/32/CI/O/N/17

[Turn over

4
4.

www.dynamicpapers.com

At the changeover the Supervisor should restore the apparatus as shown in Fig. 1.1. The mass
M will need to be suspended from both springs and the second clamp moved to the bottom of the
stand.

Information required by Examiners
Sample set of numerical results, clearly labelled “Supervisor’s Results”, obtained out of sight of the
candidates.

© UCLES 2017

5054/32/CI/O/N/17

5

www.dynamicpapers.com

Question 2
Items to be supplied by the Centre (per set of apparatus, unless otherwise specified)
4.5 V to 5 V d.c. power supply (see Note 1).
Switch or plug key.
Negative temperature coefficient disc thermistor (see Note 2).
Resistor of nominal value 2.2 kΩ (see Note 3).
Voltmeter capable of measuring a potential difference of up to 5.0 V to a precision of 0.1 V or better. An
analogue or digital meter is suitable.
250 cm3 beaker containing about 200 cm3 of water at room temperature (see Note 4).
250 cm3 beaker containing about 200 cm3 of an ice and water mixture.
Connecting leads (see Note 5).
Card on which is printed “Component X” (see Note 6).
Stirrer.
Paper towels or cloths to mop up spillages.
Notes
1.

The following are suitable power sources but all the candidates at a centre must be supplied with
the same type of source.
•
•
•

three 1.5 V dry cells in suitable holders connected in series,
four 1.2 V rechargeable cells in suitable holders connected in series,
d.c. power supply of 4.5 V or 5 V.

If a variable d.c. power supply is used, the variable control should be taped to prevent candidates
altering the output voltage.
2.

A suitable disc thermistor has a resistance of about 500 Ω at 25 °C and 1500 Ω at 0 °C. The RS
component code of such a thermistor is RS 191-2229. The thermistor will require long leads as the
beakers of water at room temperature and the ice and water mixture will be separated from the
remainder of the circuit. The ends of the leads should have suitable terminals to enable them to be
connected into the remainder of the circuit. The thermistor should be labelled X with a permanent
marker pen.

3.

The value of the resistor should be concealed from the candidates and the resistor should be
labelled R. The resistor should have suitable terminals to enable it to be connected into the
remainder of the circuit. The RS component code of a suitable resistor is RS 135-881.

4.

A container containing sufficient water for all candidates should be left overnight in the laboratory
prior to the examination so that it is at the temperature of the laboratory.

© UCLES 2017

5054/32/CI/O/N/17

[Turn over

6
5.

www.dynamicpapers.com

The Supervisor should set up the apparatus as shown in Fig. 2.1. Supervisors should check that
when the thermistor is placed in the beaker of water at room temperature the reading on the
voltmeter is in the region of 4 V. If a different thermistor to that described in Note 2 is used then the
value of R will need to be changed. Generally a larger value of R will give a larger reading on the
voltmeter.

R

beaker
with
water

V
d.c.
power
supply

beaker with
ice/water
mixture

X

Fig. 2.1
6.

After testing the circuit, the thermistor should be removed from the water, dried and placed on the
card on the bench. The thermistor should remain connected to the circuit with the switch opened.

7.

At the changeover, the Supervisor should
•
•
•

ensure that there is sufficient ice in the ice and water mixture,
remove the thermistor from one of the beakers, dry it and place it on the card. The thermistor
should be still connected to the circuit with the switch open,
ensure that the apparatus has been restored to its original state as in Fig. 2.1. If cells are
used in the circuit, they should be checked and replaced, if necessary.

Information required by Examiners
Sample set of numerical results, clearly labelled “Supervisor’s Results”, obtained out of sight of the
candidates.
If a different value of R is used, Supervisors should record the value of the resistance used.

© UCLES 2017

5054/32/CI/O/N/17

7

www.dynamicpapers.com

Question 3
Items to be supplied by the Centre (per set of apparatus, unless otherwise specified)
Ramp (see Note 1).
Glass sphere of diameter between 1 cm and 2 cm, e.g. a marble.
Fine dry sand (see Note 2).
Tray to hold the sand (see Note 3).
Two metre rules with mm divisions.
Piece of stiff card, wide enough to smooth the sand in the tray.
Notes
1.

The ramp should be made of stiff wood and have a minimum length of 60 cm. It should be inclined
at an angle of approximately 15° to the horizontal. The bottom of the ramp should be supported
about 10 cm above the bench, hence, for a 60 cm ramp, the top of the ramp should be about 25 cm
above the bench to create this angle. Supervisors should ensure that the glass sphere will roll
down the ramp when it is set at this angle. The ramp should be fixed to the supports so that it does
not move, e.g. use of Blu-tack.

2.

Any commercially available fine sand will do but it is important that the sand is dry. It may be
necessary to dry the sand in an oven at low temperature. The glass sphere will roll down the ramp
from a point that is 50.0 cm from the bottom of the ramp. It will roll off the end of the ramp to land in
the sand. It is important that the glass sphere will leave an imprint in the sand when this procedure
is carried out. As long as the initial landing point is clear it does not matter if the sphere rolls along
the sand.

3.

The Supervisor should set up the apparatus as shown in Fig. 3.1 with one end of the tray vertically
below the lower edge of the ramp. The Supervisor should try out the procedure described in
Note 2. If the sphere overshoots the tray, then a longer tray should be used. The position of the
tray should then be marked so that it can easily be returned to this position at the changeover.
ramp

supports for ramp

sand

tray
bench

Fig. 3.1
4.

At the changeover the Supervisor should ensure that the apparatus is set up as in Fig. 3.1. The
surface of the sand should be smooth and the metre rules should be on the bench.

Information required by Examiners
Sample set of numerical results, clearly marked “Supervisor’s Results”, obtained out of sight of the
candidates.
© UCLES 2017
5054/32/CI/O/N/17
[Turn over

8

www.dynamicpapers.com

Question 4
Items to be supplied by the Centre (per set of apparatus, unless otherwise specified)
Two expendable steel springs, with a spring constant of approximately 25 N / m, e.g. Griffin catalogue
number 12463080 or legacy number XBV-590-010H (see Note 1).
Stand, boss and clamp to support the parallel spring arrangement (see Note 2).
S-hook.
Wooden metre rule with mm divisions (see Note 3).
Two pieces of thin string, each of approximate length 10 cm (see Note 3).
Second boss and clamp to loosely pivot the metre rule at the 10 cm mark (see Note 4).
10 g slotted mass hanger with nine 10 g slotted masses.
300 mm ruler with mm divisions.
Set square.
Notes
1.

The springs should be as identical as possible. The springs are to be connected in parallel. This
can be done by tying together the two loops at one end of the springs and the two loops at the
opposite ends of the springs.

2.

Supervisors should label the clamp on this stand as “clamp B”.

3.

The metre rule should be stiff. Holes should be drilled in the metre rule at the 30.0 cm mark and
the 90.0 cm mark. A loose loop of thin string should then pass through each hole. One loop will
support the 10 g slotted mass hanger and the S-hook will pass through the other loop.

4.

The Supervisor should
•
•
•
•

Label this clamp as “clamp A”.
Tighten the jaws of clamp A at the 10.0 cm mark across the edges of the metre rule. The
graduated face of the rule should be vertical and face the candidate and the rod of the clamp
should be horizontal.
The rod of clamp A should be placed loosely in the boss as shown in Fig. 4.1.
The screw attaching the boss to the stand should be firmly tightened. The screw attaching the
rod of clamp A to the boss should not be fully tightened, so that the rod and rule can rotate
freely in the boss.

© UCLES 2017

5054/32/CI/O/N/17

www.dynamicpapers.com

9
stand

boss

clamp A
holding rule

loosely held
rod of clamp A
metre rule

loops of
thread

bench

Fig. 4.1
5.

The Supervisor should set up the apparatus as shown in Fig. 4.2. The Supervisor should ensure
that it is possible to hang the mass hanger and nine 10 g masses from the loop at the 90.0 cm
mark and to adjust the height of clamp B to make the rule horizontal. The Supervisor should then
remove the mass hanger and masses from the rule and unhook the rule from the S-hook.
stand
clamp B

boss
clamp
parallel
springs

L

clamp loosely
fitted into
boss behind rule

S-hook
loop
clamp A

metre rule
loop

Fig. 4.2 (front view)
6.

At the changeover, the Supervisor should
•
•

remove the mass hanger and masses from the rule,
unhook the rule from the S-hook.

Information required by Examiners
Sample set of numerical results, clearly marked “Supervisor’s Results”, obtained out of sight of the
candidates.

© UCLES 2017

5054/32/CI/O/N/17

[Turn over

10

www.dynamicpapers.com

BLANK PAGE

Permission to reproduce items where third-party owned material protected by copyright is included has been sought and cleared where possible. Every
reasonable effort has been made by the publisher (UCLES) to trace copyright holders, but if any items requiring clearance have unwittingly been included, the
publisher will be pleased to make amends at the earliest possible opportunity.
To avoid the issue of disclosure of answer-related information to candidates, all copyright acknowledgements are reproduced online in the Cambridge International
Examinations Copyright Acknowledgements Booklet. This is produced for each series of examinations and is freely available to download at www.cie.org.uk after
the live examination series.
Cambridge International Examinations is part of the Cambridge Assessment Group. Cambridge Assessment is the brand name of University of Cambridge Local
Examinations Syndicate (UCLES), which is itself a department of the University of Cambridge.

© UCLES 2017

5054/32/CI/O/N/17

11

www.dynamicpapers.com
5054/32

This form must be completed and returned with the candidates’ scripts.
REPORT ON PRACTICAL PHYSICS
The Supervisor is asked to give the following details, using the space provided on page 12.
(a) Information required at the end of the test, as indicated in the Instructions.
(b) Any help given to a candidate.
(c) Any general difficulties encountered in preparing the apparatus.
(d) Any difficulties experienced by particular candidates. These should include reference to difficulties
due to faulty apparatus or materials and accidental damage to apparatus or materials. Candidates
should be identified by name and candidate number.
Other cases of hardship, such as disability or illness, should be reported to Cambridge in the normal
way.
The Supervisor is asked to provide a plan of the work benches, giving details by candidate numbers
of the places occupied by the candidates for each session. The plan and report should be enclosed in
the envelope containing the candidates’ scripts. If more than one envelope is used, a copy of the report
must be enclosed in each envelope.

Declaration to be signed by the Supervisor
The preparation of this practical examination has been carried out so as to maintain fully the security
of the examination.

Signed

Name (in block capitals)

Centre number

Centre name

© UCLES 2017

5054/32/CI/O/N/17

[Turn over

12

www.dynamicpapers.com

Information required
For questions 1, 2, 3 and 4, please enclose a sample set of numerical results, obtained out of sight of
the candidates and clearly labelled “Supervisor’s Results”.
Details of difficulties and any help given to candidates

© UCLES 2017

5054/32/CI/O/N/17

Advertisement